Agam
Deedo IDDP-PUN-S4Y3Its promised completion date, Oct 2022, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.
Kothrud, Pune 411038 · Property rates in Kothrud · Promoter: M/s. Gokhale Promoters LLP
Its promised completion date, Oct 2022, has passed and MahaRERA does not show it completed
- This projectRegistered 10 Oct 2018, completion promised 30 Oct 2022, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100018114
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100018114 | 10 Oct 2018 | 30 Oct 2022 | 30 Oct 2022 | M/s. Gokhale Promoters LLP | Project page |
Documents50
1 document held by Deedo, 49 filings listed on MahaRERA's project page
Finance
- PAN CardGOKHALE PROMOTERS LLP_PAN.pdf · uploaded 12 Sep 2018Source
Legal
Show all 50 documentsShow fewer documents
Migrated
- 1 Proforma of Allotment letterAgreement-RERA-Agam.pdf · uploaded 14 Sep 2018Source
- 2 Proforma of Allotment letterAllotment letter - RERA.pdf · uploaded 14 Sep 2018Source
- 1 Declaration in FORM BAgam Declaration.pdf · uploaded 21 Sep 2018Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Agam Architect Cert.pdf · uploaded 28 Sep 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Agam Eng Cert.pdf · uploaded 28 Sep 2018Source
- 1 Copy of Layout Approval (in case of layout)Agam plans.pdf · uploaded 4 Oct 2018Source
- 1 Building Plan Approval (IOD)Agam plans.pdf · uploaded 4 Oct 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 4 Oct 2018Source
- 1 Certificates of CA (Form 3)Agam Form 3.pdf · uploaded 4 Oct 2018Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)agam_Arch Cert June 2019.pdf · uploaded 2 Jul 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5)Agam.PDF · uploaded 30 Sep 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)zAgam.PDF · uploaded 22 Nov 2019Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)soc reg cert.pdf · uploaded 22 Nov 2019Source
- 2 Details of encumbrancesSBI mortgage.pdf · uploaded 12 Dec 2019Source
- 2 Copy of the legal title reportAgam title Opinion-2020.pdf · uploaded 24 Sep 2020Source
- 2 Annual Audit Report of Statutory CA (Form 5)16Agam.pdf · uploaded 29 Sep 2020Source
- 2 Copy of Layout Approval (in case of layout)Sanction Plan1.pdf · uploaded 28 Aug 2021Source
- 2 Commencement Certificates / NA Order for plotted developmentCC Revised.pdf · uploaded 28 Aug 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)ENGINEERS CERTIFICATE.pdf · uploaded 28 Aug 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 Agam.pdf · uploaded 30 Sep 2021Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION CERTIFICATE.PDF · uploaded 18 Mar 2022Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.PDF · uploaded 18 Mar 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Agam SIGNED.pdf · uploaded 30 Sep 2022Source
- 2 Architect’s Certificate on Completion of Project (Form 4)Form 4 Agam.pdf · uploaded 19 Apr 2023Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - 31 03 2020.pdf · uploaded 23 Jan 2024Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - 31 03 2021.pdf · uploaded 23 Jan 2024Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - 31 12 2021.pdf · uploaded 23 Jan 2024Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - 03 03 2022.pdf · uploaded 23 Jan 2024Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - 31 03 2020.pdf · uploaded 23 Jan 2024Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - 31 03 2021.pdf · uploaded 23 Jan 2024Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - 31 12 2021.pdf · uploaded 23 Jan 2024Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - 03 03 2022.pdf · uploaded 23 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)AGAM 2018-2019.PDF · uploaded 14 May 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)AGAM 2019-2020.PDF · uploaded 14 May 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)AGAM 2020-2021.PDF · uploaded 14 May 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)AGAM 2021-2022.PDF · uploaded 14 May 2024Source
- 1 Disclosure of sold/ booked inventorySold Unsold Agam - Signed.pdf · uploaded 22 May 2024Source
Technical
Technical (Architect)
- DocumentForm 1 - 03 03 2022.pdf · uploaded 23 Jan 2024Source
Technical (Engineer)
- DocumentForm 2 - 03 03 2022.pdf · uploaded 23 Jan 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals824
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1 BHK, 2 BHK, 3 BHK28 units in all
- Address
- 824, Ideal Colony, KothrudPIN 411038
- Village
- Kothrud, Haveli taluka
- Designated bank account
- 171
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot No 37 of Krishnanayan Society
- South
- Plot No 39 Ideal Colony Kothrud Pune
- East
- Sumarg and Navketan Society
- West
- Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking28 units
28 of 28 units booked (100%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 30.86 sq m · 332 sq ft | 1 | 1 |
| 2 BHK | 52.35 sq m · 563 sq ft | 2 | 2 |
| 2 BHK | 56.46 sq m · 608 sq ft | 1 | 1 |
| 2 BHK | 56.85 sq m · 612 sq ft | 1 | 1 |
| 2 BHK | 57.26 sq m · 616 sq ft | 2 | 2 |
| 2 BHK | 57.35 sq m · 617 sq ft | 1 | 1 |
| 2 BHK | 59.07 sq m · 636 sq ft | 1 | 1 |
| 2 BHK | 60.11 sq m · 647 sq ft | 1 | 1 |
Show all 19 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2 BHK | 60.24 sq m · 648 sq ft | 1 | 1 |
| 2 BHK | 61.02 sq m · 657 sq ft | 2 | 2 |
| 2 BHK | 61.18 sq m · 659 sq ft | 1 | 1 |
| 3 BHK | 76.85 sq m · 827 sq ft | 2 | 2 |
| 3 BHK | 80.4 sq m · 865 sq ft | 2 | 2 |
| 3 BHK | 80.42 sq m · 866 sq ft | 1 | 1 |
| 3 BHK | 82 sq m · 883 sq ft | 2 | 2 |
| 3 BHK | 82.59 sq m · 889 sq ft | 1 | 1 |
| 3 BHK | 83.09 sq m · 894 sq ft | 2 | 2 |
| 3 BHK | 83.27 sq m · 896 sq ft | 3 | 3 |
| 3 BHK | 88.34 sq m · 951 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | A Design Studio Mr Siddharth Harishchandrakar | — |
| Engineer | JW Consultants Mr Umesh Joshi | — |
| Registered real estate agent | Sham Ramakant Yawatkar | — |
Source: MahaRERA project page. Contact details are not shown.