Skip to content
Others · 2 buildings · 127 unitsRERA P52100024025

Vitthal Heights

Deedo IDDP-PUN-TMKD

Its promised completion date, Jul 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 42% of its units are booked.

Kiwale, Pune 412101 · Property rates in Kiwale · by Pawana Associates Llp

Delivery1 yr 4 mo past duePromised Jul 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales42% booked53 of 127 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Jul 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 14 Jan 2020, completion promised 31 Jul 2025, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100024025
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002402514 Jan 202031 Jul 202531 Jul 2025Pawana Associates LLPProject page
Documents132

1 document held by Deedo, 131 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan card PA partnership.pdf · uploaded 24 Dec 2019Source

Legal

  • Legal Title reportSearch and Title Report 01.pdf · uploaded 24 Dec 2019Source
  • Legal Title reportSearch and Title Report 02.pdf · uploaded 24 Dec 2019Source
  • Declaration Form Bform b_compressed.pdf · uploaded 8 Jan 2020Source

Migrated

  • 1 PAN CardPan card PA partnership.pdf · uploaded 24 Dec 2019Source
  • 1 Copy of the legal title reportSearch and Title Report 01.pdf · uploaded 24 Dec 2019Source
  • 2 Copy of the legal title reportSearch and Title Report 02.pdf · uploaded 24 Dec 2019Source
Show all 132 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentPlan Pass 01.pdf · uploaded 24 Dec 2019Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan Pass 02.pdf · uploaded 24 Dec 2019Source
  • 3 Building Plan Approval / NA Order for plotted developmentPlan Pass 03.pdf · uploaded 24 Dec 2019Source
  • 4 Building Plan Approval / NA Order for plotted developmentPlan Pass 04.pdf · uploaded 24 Dec 2019Source
  • 5 Building Plan Approval / NA Order for plotted developmentPlan Pass 05.pdf · uploaded 24 Dec 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 24 Dec 2019Source
  • 1 Details of encumbrancesencumbursment certificate.pdf · uploaded 26 Dec 2019Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Cert_compressed.pdf · uploaded 30 Dec 2019Source
  • 1 Proforma of Allotment letterAllotment Letter.Pdf · uploaded 30 Dec 2019Source
  • 1 Declaration in FORM Bform b_compressed.pdf · uploaded 8 Jan 2020Source
  • 2 Proforma of Allotment letterFlat Agreement - 2 (1).pdf · uploaded 8 Jan 2020Source
  • 1 Copy of Layout Approval (in case of layout)Plan Pass 01.pdf · uploaded 9 Jan 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERT.pdf · uploaded 12 Jan 2020Source
  • 1 Declaration about Commencement CertificateC C DECLARATION.pdf · uploaded 26 Feb 2022Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Wing A.pdf · uploaded 26 Feb 2022Source
  • 2 Disclosure of sold/ booked inventorySold Unsold Wing B.pdf · uploaded 26 Feb 2022Source
  • 2 Copy of Layout Approval (in case of layout)Adobe_Scan_Feb_27,_2022-1-2-1[1].pdf · uploaded 27 Feb 2022Source
  • 6 Building Plan Approval / NA Order for plotted developmentAdobe_Scan_Feb_27,_2022-1-2-2[1].pdf · uploaded 27 Feb 2022Source
  • 7 Building Plan Approval / NA Order for plotted developmentPLAN 3.pdf · uploaded 27 Feb 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Kaagaz_20220226_200539524478.pdf · uploaded 27 Feb 2022Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Kaagaz_20220226_200703603688.pdf · uploaded 27 Feb 2022Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Kaagaz_20220226_20080909534.pdf · uploaded 27 Feb 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Kaagaz_20220226_200539524478.pdf · uploaded 27 Feb 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report.pdf · uploaded 27 Feb 2022Source
  • 2 CERSAI detailsCersai Undertaking.pdf · uploaded 27 Feb 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 MARCH 2021.pdf · uploaded 27 Feb 2022Source
  • 3 Disclosure of sold/ booked inventorySold Unsold Wing B.pdf · uploaded 13 Mar 2022Source
  • 4 Disclosure of sold/ booked inventorySold Unsold Wing A.pdf · uploaded 13 Mar 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Rera Certificate Pawana Associates.pdf · uploaded 30 Sep 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 WING A SEP 22.pdf · uploaded 1 Feb 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 WING B SEP 22.pdf · uploaded 1 Feb 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 SEP 22_compressed.pdf · uploaded 1 Feb 2023Source
  • 5 Disclosure of sold/ booked inventoryInventory WING A_compressed.pdf · uploaded 1 Feb 2023Source
  • 6 Disclosure of sold/ booked inventoryInventory WING B_compressed.pdf · uploaded 1 Feb 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 SEP 22_compressed.pdf · uploaded 1 Feb 2023Source
  • 8 Building Plan Approval / NA Order for plotted developmentSanction Plan_30-12-2022_Vitthal Heights_1.pdf · uploaded 3 Feb 2023Source
  • 9 Building Plan Approval / NA Order for plotted developmentSanction Plan_30-12-2022_Vitthal Heights_2.pdf · uploaded 3 Feb 2023Source
  • 10 Building Plan Approval / NA Order for plotted developmentSanction Plan_30-12-2022_Vitthal Heights_3 (1).pdf · uploaded 3 Feb 2023Source
  • 11 Building Plan Approval / NA Order for plotted developmentSanction Plan_30-12-2022_Vitthal Heights_4.pdf · uploaded 3 Feb 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC_30-12-2022_Vitthal Heights.pdf · uploaded 3 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Pawana Associates- Form 5.pdf · uploaded 24 Jul 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)PAWANA ASSOCIATES FORM -1_A-WING_01 MAR 2020.pdf · uploaded 14 Aug 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)PAWANA ASSOCIATES FORM -1_B-WING_01 MAR 2020.pdf · uploaded 14 Aug 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)PAWANA ASSOCIATES FORM -1_A-WING_02 MAR 2021.pdf · uploaded 14 Aug 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)PAWANA ASSOCIATES FORM -1_B-WING_02 MAR 2021.pdf · uploaded 14 Aug 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)PAWANA ASSOCIATES FORM -1_B-WING_03 MAR 2022.pdf · uploaded 14 Aug 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)PAWANA ASSOCIATES FORM -1_B-WING_03 MAR 2022.pdf · uploaded 14 Aug 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)PAWANA ASSOCIATES FORM -1_A-WING_03 MAR 2022.pdf · uploaded 14 Aug 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)PAWANA ASSOCIATES FORM -1_B-WING_03 MAR 2022.pdf · uploaded 14 Aug 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)PAWANA ASSOCIATES FORM -1_A-WING_03 MAR 2022.pdf · uploaded 14 Aug 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)PAWANA ASSOCIATES FORM 2 MAR 2020.pdf · uploaded 14 Aug 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)PAWANA ASSOCIATES FORM 2 MAR 2021.pdf · uploaded 14 Aug 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)PAWANA ASSOCIATES FORM 3 MAR 2020_compressed.pdf · uploaded 14 Aug 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)PAWANA ASSOCIATES FORM 3 MAR 2021_compressed.pdf · uploaded 14 Aug 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)PAWANA ASSOCIATES FORM 3 MAR 2022_compressed (1).pdf · uploaded 14 Aug 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA FORM 5 PAWANA ASSOCIATES F Y 22-23.pdf · uploaded 30 Sep 2023Source
  • 12 Building Plan Approval / NA Order for plotted developmentPA BP1 2024.pdf · uploaded 30 Mar 2024Source
  • 13 Building Plan Approval / NA Order for plotted developmentPA BP2 2024.pdf · uploaded 30 Mar 2024Source
  • 14 Building Plan Approval / NA Order for plotted developmentPA BP3 2024.pdf · uploaded 30 Mar 2024Source
  • 15 Building Plan Approval / NA Order for plotted developmentPA BP4 2024.pdf · uploaded 30 Mar 2024Source
  • 3 Commencement Certificates / NA Order for plotted developmentPA CC1 2024.pdf · uploaded 30 Mar 2024Source
  • Form 5 (FY 2023-2024)FORM 5 - PAWANA ASSOCIATES.pdf · uploaded 30 Sep 2024Source
  • Form 1FORM 1 FY 23-24 Q3.pdf · uploaded 3 Jun 2025Source
  • Form 2FORM 2 FY 23-24 Q3.pdf · uploaded 3 Jun 2025Source
  • Form 3FORM 3 FY 23-24 Q3.pdf · uploaded 3 Jun 2025Source
  • Form 1FORM 1 FY 23-24 Q4.pdf · uploaded 3 Jun 2025Source
  • Form 2FORM 2 FY 23-24 Q4.pdf · uploaded 3 Jun 2025Source
  • Form 3FORM 3 FY 23-24 Q4.pdf · uploaded 3 Jun 2025Source
  • Disclosure of Sold and Booked InventoryInv FY 23-24 Q4.pdf · uploaded 3 Jun 2025Source
  • Form 1FORM 1 FY 24-25 Q1.pdf · uploaded 3 Jun 2025Source
  • Form 2FORM 2 FY 24-25 Q1.pdf · uploaded 3 Jun 2025Source
  • Form 3FORM 3 FY 24-25 Q1.pdf · uploaded 3 Jun 2025Source
  • Disclosure of Sold and Booked InventoryInv FY 24-25 Q1.pdf · uploaded 3 Jun 2025Source
  • Form 1FORM 1 FY 24-25 Q2.pdf · uploaded 3 Jun 2025Source
  • Form 2FORM 2 FY 24-25 Q2.pdf · uploaded 3 Jun 2025Source
  • Form 3FORM 3 FY 24-25 Q2.pdf · uploaded 3 Jun 2025Source
  • Disclosure of Sold and Booked InventoryInv FY 24-25 Q2.pdf · uploaded 3 Jun 2025Source
  • Form 1FORM 1 FY 24-25 Q3.pdf · uploaded 3 Jun 2025Source
  • Form 2FORM 2 FY 24-25 Q3.pdf · uploaded 3 Jun 2025Source
  • Form 3FORM 3 FY 24-25 Q3.pdf · uploaded 3 Jun 2025Source
  • Disclosure of Sold and Booked InventoryInv FY 24-25 Q3.pdf · uploaded 3 Jun 2025Source
  • Form 1FORM 1 FY 24-25 Q4.pdf · uploaded 3 Jun 2025Source
  • Form 2FORM 2 FY 24-25 Q4.pdf · uploaded 3 Jun 2025Source
  • Form 3FORM 3 FY 24-25 Q4.pdf · uploaded 3 Jun 2025Source
  • Disclosure of Sold and Booked InventoryInv FY 24-25 Q4.pdf · uploaded 3 Jun 2025Source
  • Form 5 (FY 2019-2020)2019-20.pdf · uploaded 1 Jul 2025Source
  • Form 5 (FY 2020-2021)2020-21.pdf · uploaded 1 Jul 2025Source
  • Form 5 (FY 2021-2022)2021-22.pdf · uploaded 1 Jul 2025Source
  • Form 5 (FY 2022-2023)2022-23.pdf · uploaded 1 Jul 2025Source
  • Withdrawal Update Form 1Form 1 June 25.pdf · uploaded 2 Sep 2025Source
  • Withdrawal Update Form 1Form 1 June 25.pdf · uploaded 2 Sep 2025Source
  • Withdrawal Update Form 2Form 2 June 25.pdf · uploaded 2 Sep 2025Source
  • Withdrawal Update Form 2Form 2 June 25.pdf · uploaded 2 Sep 2025Source
  • Withdrawal Update Form 3Form 3 June 25.pdf · uploaded 2 Sep 2025Source
  • Withdrawal Update Form 3Form 3 June 25.pdf · uploaded 2 Sep 2025Source
  • Form 5 (FY 2024-2025)Form 5 Pawana associated LLP F Y 24-25.pdf · uploaded 3 Oct 2025Source
  • Withdrawal Update Form 1Form 1 June 25.pdf · uploaded 3 Jan 2026Source
  • Withdrawal Update Form 2Form 2 June 25.pdf · uploaded 3 Jan 2026Source
  • Withdrawal Update Form 3Form 3 June 25.pdf · uploaded 3 Jan 2026Source
  • Form 2A (FY 2019-2020)Form 2A FY 2019-20.pdf · uploaded 7 Jan 2026Source
  • Form 2A (FY 2020-2021)Form 2A FY 2020-21.pdf · uploaded 7 Jan 2026Source
  • Form 2A (FY 2021-2022)Form 2A FY 2021-22.pdf · uploaded 7 Jan 2026Source
  • Form 2A (FY 2022-2023)Form 2A FY 2022-23.pdf · uploaded 7 Jan 2026Source
  • Form 2A (FY 2023-2024)Form 2A Fy 2023-24.pdf · uploaded 7 Jan 2026Source
  • Form 2A (FY 2024-2025)Form 2A FY 2024-25.pdf · uploaded 7 Jan 2026Source

Technical

  • DocumentPlan Pass 01.pdf · uploaded 24 Dec 2019Source
  • DocumentPlan Pass 02.pdf · uploaded 24 Dec 2019Source
  • DocumentPlan Pass 03.pdf · uploaded 24 Dec 2019Source
  • DocumentPlan Pass 04.pdf · uploaded 24 Dec 2019Source
  • DocumentPlan Pass 05.pdf · uploaded 24 Dec 2019Source
  • DocumentPlan Pass 01.pdf · uploaded 9 Jan 2020Source
  • DocumentAdobe_Scan_Feb_27,_2022-1-2-1[1].pdf · uploaded 27 Feb 2022Source
  • DocumentAdobe_Scan_Feb_27,_2022-1-2-2[1].pdf · uploaded 27 Feb 2022Source
  • DocumentPLAN 3.pdf · uploaded 27 Feb 2022Source
  • DocumentSanction Plan_30-12-2022_Vitthal Heights_1.pdf · uploaded 3 Feb 2023Source
  • DocumentSanction Plan_30-12-2022_Vitthal Heights_2.pdf · uploaded 3 Feb 2023Source
  • DocumentSanction Plan_30-12-2022_Vitthal Heights_3 (1).pdf · uploaded 3 Feb 2023Source
  • DocumentSanction Plan_30-12-2022_Vitthal Heights_4.pdf · uploaded 3 Feb 2023Source
  • DocumentPA BP1 2024.pdf · uploaded 30 Mar 2024Source
  • DocumentPA BP2 2024.pdf · uploaded 30 Mar 2024Source
  • DocumentPA BP3 2024.pdf · uploaded 30 Mar 2024Source
  • DocumentPA BP4 2024.pdf · uploaded 30 Mar 2024Source

Technical (Architect)

  • DocumentForm 1 June 25.pdf · uploaded 3 Jan 2026Source

Technical (Engineer)

  • DocumentForm 2 June 25.pdf · uploaded 3 Jan 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 73/1/1/2/2

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop127 units in all
Address
73/1/1/2/2, Kiwale, Survey No 73/1/1/2/2, Adarsh Nagar, KiwalePIN 412101
Village
Pimpri Chinchawad (M Corp.), Haveli taluka
Land area for this project
2,874 sq m (30,936 sq ft)
Permissible built-up area
11,763 sq m (1,26,615 sq ft)
Sanctioned built-up area
5,164 sq m (55,585 sq ft)
Recreational open space
269 sq m (2,895 sq ft)
Designated bank account
171
Developed in phases
Yes

Survey, CTS, gat or plot numbers

73/1/1/2/2

Land as published on MahaRERA's project page

73/1/1/2/2, KIWALE

Boundaries

North
18 Meter Wide D P Road
South
Indra Park Society
East
Part Of Survey No 73
West
12 Meter Wide D P Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking127 units

53 of 127 units booked (42%), as the promoter reported to MahaRERA

1BHK · 18 units2BHK · 92 unitsShop · 17 units
BuildingTypeCarpet areaUnitsBooked
A Wing1BHK36.69 sq m · 395 sq ft98
A Wing2BHK51.92 sq m · 559 sq ft120
A Wing2BHK53.21 sq m · 573 sq ft127
A Wing2BHK56.17 sq m · 605 sq ft107
A Wing2BHK57.08 sq m · 614 sq ft111
A Wing2BHK86.59 sq m · 932 sq ft10
A WingShop15.64 sq m · 168 sq ft10
A WingShop16.66 sq m · 179 sq ft10
Show all 24 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A WingShop16.93 sq m · 182 sq ft11
A WingShop21.05 sq m · 227 sq ft43
A WingShop21.37 sq m · 230 sq ft10
A WingShop21.92 sq m · 236 sq ft10
A WingShop23.39 sq m · 252 sq ft11
A WingShop23.4 sq m · 252 sq ft11
A WingShop23.97 sq m · 258 sq ft10
A WingShop26.57 sq m · 286 sq ft22
A WingShop27.76 sq m · 299 sq ft22
A WingShop28.42 sq m · 306 sq ft11
B Wing1BHK36.69 sq m · 395 sq ft98
B Wing2BHK51.92 sq m · 559 sq ft120
B Wing2BHK55.87 sq m · 601 sq ft124
B Wing2BHK56.17 sq m · 605 sq ft103
B Wing2BHK57.08 sq m · 614 sq ft114
B Wing2BHK86.59 sq m · 932 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShekhar Kokane—
Chartered accountantCA Ganesh Kankate—
Chartered accountantCa Manatu Kumbhar—
Chartered accountantKishor Mavkar—
EngineerAjinkya Lahigude—
OtherAnand Gaikwad—
OtherDeltacom Structural Consultants Pvt Ltd—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology