Skip to content
Residential / Group Housing · 1 building · 20 unitsRERA P52100013672

Sonigara Pratik

Deedo IDDP-PUN-SAME

MahaRERA shows it completed; no MahaRERA orders on record; 90% of its units are booked.

Kiwale, Pune 412101 · by Shankheshwar Constructions And Developers

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales90% booked18 of 20 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 23 Oct 2017, completion promised 30 Dec 2021.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100013672
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001367223 Oct 201730 Dec 202130 Dec 2021Shankheshwar Constructions And DevelopersProject page
Documents34

1 document held by Deedo, 33 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 16 Sep 2017Source

Legal

  • Declaration Form BAFF CUM DA-ilovepdf-compressed.pdf · uploaded 16 Sep 2017Source
  • Legal Title reportSEARCH REPORT-ilovepdf-compressed.pdf · uploaded 16 Sep 2017Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 16 Sep 2017Source
  • 1 Copy of the legal title reportSEARCH REPORT-ilovepdf-compressed.pdf · uploaded 16 Sep 2017Source
  • 1 Details of encumbrancesDEA.pdf · uploaded 16 Sep 2017Source
  • 1 Copy of Layout Approval (in case of layout)PLAN LAY 1.pdf · uploaded 16 Sep 2017Source
Show all 34 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval (IOD)PLAN LAYOUT -2-ilovepdf-compressed.pdf · uploaded 16 Sep 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMM-ilovepdf-compressed.pdf · uploaded 16 Sep 2017Source
  • 1 Declaration in FORM BAFF CUM DA-ilovepdf-compressed.pdf · uploaded 16 Sep 2017Source
  • 1 Certificates of CA (Form 3)Sonigara Pratik.pdf · uploaded 16 Sep 2017Source
  • 1 Proforma of Allotment letterSONIGARA PRATIK - RERA AGREE.pdf · uploaded 18 Sep 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARC CERTIFICATE 31-03-18.pdf · uploaded 2 May 2018Source
  • 2 Certificates of CA (Form 3)1-1-2018-ilovepdf-compressed.pdf · uploaded 2 May 2018Source
  • 3 Certificates of CA (Form 3)1-4-2018-ilovepdf-compressed.pdf · uploaded 2 May 2018Source
  • 4 Certificates of CA (Form 3)30-6-208.pdf · uploaded 11 Aug 2018Source
  • 1 Certificates of CA (Form 5)sankeshwar (1).pdf · uploaded 30 Sep 2018Source
  • 5 Certificates of CA (Form 3)CA -30-9-2018.pdf · uploaded 27 Nov 2018Source
  • 6 Certificates of CA (Form 3)RERA ANNUAL AUDIT REPORT-2017 TO 2018.pdf · uploaded 19 Dec 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)30-6-2018.pdf · uploaded 14 Jan 2019Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECTS -30-9-2018.pdf · uploaded 14 Jan 2019Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)31-12-2018.pdf · uploaded 14 Jan 2019Source
  • 7 Certificates of CA (Form 3)CA PRATIK.pdf · uploaded 25 Feb 2019Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)31-3-2019.pdf · uploaded 11 Apr 2019Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECTS CERTI FINAL.pdf · uploaded 8 Aug 2019Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECTS CERTI FINAL.pdf · uploaded 8 Aug 2019Source
  • 8 Certificates of CA (Form 3)PRATIK.pdf · uploaded 16 Sep 2019Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 10 Oct 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)12 Shankeshwar Contruction Developers.pdf · uploaded 30 Dec 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Ms Shankheshwar Construction and Developers.pdf · uploaded 15 Mar 2021Source

Technical

  • DocumentPLAN LAY 1.pdf · uploaded 16 Sep 2017Source
  • DocumentPLAN LAYOUT -2-ilovepdf-compressed.pdf · uploaded 16 Sep 2017Source

Technical (Architect)

  • DocumentARCHITECTS CERTI FINAL.pdf · uploaded 8 Aug 2019Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 1608, CTS NO 1607

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1 BHK, 1BHK, 2 BHK, 2BHK20 units in all
Address
S .no -41/1/2, Cts No -1607, 1608, Plot No- 11, Maharashtra, KiwalePIN 412101
Village
Pimpri Chinchawad (M Corp.), Haveli taluka
Land area for this project
454 sq m (4,890 sq ft)
Permissible built-up area
907 sq m (9,767 sq ft)
Sanctioned built-up area
907 sq m (9,767 sq ft)
Designated bank account
229
Developed in phases
No

Survey, CTS, gat or plot numbers

1608CTS NO 1607PLOT NO 11S .NO 41/1/2

Land as published on MahaRERA's project page

S .NO -41/1/2, CTS NO -1607 ,1608, PLOT NO- 11

Boundaries

North
8 M Dp Road
South
6 M Dp Road
East
Plot No 10
West
Plot No 12

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking20 units

18 of 20 units booked (90%), as the promoter reported to MahaRERA

1 BHK · 6 units1BHK · 4 units2 BHK · 4 units2BHK · 6 units
TypeCarpet areaUnitsBooked
1 BHK36.44 sq m · 392 sq ft65
1BHK36.21 sq m · 390 sq ft43
2 BHK47.75 sq m · 514 sq ft44
2BHK48.15 sq m · 518 sq ft33
2BHK48.2 sq m · 519 sq ft33

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSandeep Sakharam Waghchoure—
EngineerRahul Ramesh Kapse—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology