Residential / Group Housing · 2 buildings · 19 unitsRERA P52100022852

Samruddhi Amber

Deedo IDDP-PUN-C127

Completion was pushed back 5 months to Feb 2024, and that date has passed too; no MahaRERA orders on record; 68% of its units are booked.

Kivale, Pune 412101 · by Samruddhi Group

Delivery3 yrs 2 mo latePromised Sep 2023 · revised Feb 2024 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales68% booked13 of 19 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 5 months to Feb 2024, and that date has passed too

  • This projectRegistered 30 Oct 2019, completion promised 30 Sep 2023, revised to 29 Feb 2024, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100022852
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002285230 Oct 201930 Sep 202329 Feb 2024Samruddhi GroupProject page
Documents38

3 documents held by Deedo, 35 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN CARD.pdf · uploaded 18 Oct 2019Source

Legal

  • Legal Title reportTitle Report_compressed.pdf · uploaded 16 Oct 2019Source
  • Declaration Form BForm B Declaretion_compressed.pdf · uploaded 16 Oct 2019Source

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentBlue Print1_compressed (1).pdf · uploaded 2 Oct 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC_compressed.pdf · uploaded 2 Oct 2019Source
Show all 38 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportTitle Report_compressed.pdf · uploaded 16 Oct 2019Source
  • 1 Details of encumbrancesDeclaaretion Of Encumb.pdf · uploaded 16 Oct 2019Source
  • 1 Copy of Layout Approval (in case of layout)Declaretion Layout Delarretion.pdf · uploaded 16 Oct 2019Source
  • 1 Declaration in FORM BForm B Declaretion_compressed.pdf · uploaded 16 Oct 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A Certificate_compressed.pdf · uploaded 16 Oct 2019Source
  • 1 Proforma of Allotment letterAGREEMENT TO SALE (RERA) FINAL.pdf · uploaded 16 Oct 2019Source
  • 1 PAN CardPAN CARD.pdf · uploaded 18 Oct 2019Source
  • 2 Building Plan Approval / NA Order for plotted developmentDrawing-INWD_WDA_KVL_PRB18_0020_19.pdf · uploaded 13 Feb 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentRevised Commencement Certificate Amber.pdf · uploaded 13 Feb 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Amber-work progress letter.pdf · uploaded 25 Oct 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)SAMRUDDHI engineer certificate.pdf · uploaded 25 Oct 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Quality Asuurance.pdf · uploaded 25 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)SAMRUDDHI engineer certificate_compressed.pdf · uploaded 25 Oct 2023Source
  • 1 Disclosure of sold/ booked inventoryCA certificate 1_compressed.pdf · uploaded 26 Oct 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentPHOTO-2023-06-15-12-47-31.pdf · uploaded 30 Oct 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate_compressed NEW.pdf · uploaded 30 Oct 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)aRCH.pdf · uploaded 6 Nov 2023Source
  • 2 Disclosure of sold/ booked inventorySAMRUDDHI.pdf · uploaded 6 Nov 2023Source
  • 4 Commencement Certificates / NA Order for plotted developmentplinth certificate.pdf · uploaded 7 Nov 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer certificate.pdf · uploaded 16 Nov 2023Source
  • 3 Disclosure of sold/ booked inventorybooked sold.pdf · uploaded 16 Nov 2023View
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SAMRUDDHI AMBAR_compressed.pdf · uploaded 16 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 SAMRUDDHI AMBER.pdf · uploaded 16 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)CA Certificate Form 5 samruddhi Group.pdf · uploaded 16 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 SAMRUDDHI AMBER.pdf · uploaded 16 Nov 2023Source

Technical

  • DocumentBlue Print1_compressed (1).pdf · uploaded 2 Oct 2019Source
  • DocumentDeclaretion Layout Delarretion.pdf · uploaded 16 Oct 2019Source
  • DocumentDrawing-INWD_WDA_KVL_PRB18_0020_19.pdf · uploaded 13 Feb 2022Source

Technical (Architect)

  • DocumentaRCH.pdf · uploaded 6 Nov 2023Source

Technical (Engineer)

  • Documentengineer certificate.pdf · uploaded 16 Nov 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No 8 Survey No 41

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK19 units in all
Address
Plot No 8 Survey No 41, Pendse Colony, VikasnagarPIN 412101
Village
Kivale, Mawal taluka
Land area for this project
490 sq m (5,269 sq ft)
Permissible built-up area
1,132 sq m (12,189 sq ft)
Sanctioned built-up area
976 sq m (10,503 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No 8 Survey No 41

Land as published on MahaRERA's project page

Plot No 8 Survey No 41

Boundaries

North
Colony Road
South
Plot No 15 Sr No 41
East
Colony Road
West
Plot No 9 Sr No 41

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking19 units

13 of 19 units booked (68%), as the promoter reported to MahaRERA

1BHK · 11 units2BHK · 8 units
TypeCarpet areaUnitsBooked
1BHK46.46 sq m · 500 sq ft52
1BHK48.2 sq m · 519 sq ft66
2BHK66.94 sq m · 721 sq ft42
2BHK67.78 sq m · 730 sq ft43

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals13

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKalparachana—
Chartered accountantHanumantrao Lad & Associates—
EngineerNikhil Murchite—
OtherAniket Constructions—
OtherKansingh Contractors—
OtherKumar Kashinath Shahapure—
OtherR P Electrical—
OtherSachin Fabricators—
Show all 13 professionalsShow fewer professionals
RoleNameRegistration no.
OtherShantappa Mulage—
OtherS K Plumbing Contractors—
OtherSneha Arts—
OtherS P Constructions—
OtherSuresh Kumawat—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Kivale

All 41 projects in Kivale · Compare Samruddhi Amber with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology