Nandanvan
Deedo IDDP-PUN-CEDXIts promised completion date, Dec 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 81% of its units are booked.
Kirkatwadi, Pune 411024 · by Pride Realty
Buying a flat here?
See every deed registered on it.
Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 24 Jan 2022, completion promised 31 Dec 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100032704
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100032704 | 24 Jan 2022 | 31 Dec 2024 | 31 Dec 2024 | Pride Realty | Project page |
Documents202
2 documents held by Deedo, 200 filings listed on MahaRERA's project page
Show all 202 documentsShow fewer documents
Legal
Migrated
- 1 PAN Cardpan card firm.pdf · uploaded 30 Nov 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architech certificate.pdf · uploaded 30 Nov 2021Source
- 1 Copy of the legal title reportSARCH REPORT.pdf · uploaded 1 Dec 2021Source
- 1 Details of encumbrancesENCOMBERSMENT CERTIFICATE.pdf · uploaded 1 Dec 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERT.pdf · uploaded 1 Dec 2021Source
- 1 Declaration about Commencement CertificateFORMAT D.pdf · uploaded 1 Dec 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 1 Dec 2021Source
- 1 Proforma of Allotment letterRera Agreement Drift.pdf · uploaded 1 Dec 2021Source
- 2 Copy of the legal title reportSEARCH FORM.pdf · uploaded 2 Dec 2021Source
- 3 Copy of the legal title reportSEARCH IN FORMAT A.pdf · uploaded 3 Jan 2022Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 3 Jan 2022Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 3 Jan 2022Source
- 2 Proforma of Allotment letterPOSSESSION LETTER FINAL.pdf · uploaded 3 Jan 2022Source
- 1 OtherFORM B.pdf · uploaded 3 Jan 2022Source
- 2 OtherCERSAI.pdf · uploaded 3 Jan 2022Source
- 3 OtherSEARCH IN FORMAT A.pdf · uploaded 3 Jan 2022Source
- 4 OtherPOSSESSION LETTER FINAL.pdf · uploaded 3 Jan 2022Source
- 1 Copy of Layout Approval (in case of layout)NA ORDER.pdf · uploaded 17 Jan 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentplan.pdf · uploaded 17 Jan 2022Source
- 3 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 17 Jan 2022Source
- 5 OtherALLOTMENT LETTER.pdf · uploaded 17 Jan 2022Source
- 1 Disclosure of sold/ booked inventoryBOOK INVERTORY.pdf · uploaded 21 Oct 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentPLAN 1.pdf · uploaded 4 Nov 2023Source
- 3 Building Plan Approval / NA Order for plotted developmentPLAN 2.pdf · uploaded 4 Nov 2023Source
- 4 Building Plan Approval / NA Order for plotted developmentPLAN 3.pdf · uploaded 4 Nov 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 4 Nov 2023Source
- 2 Declaration about Commencement Certificatecc declaration.pdf · uploaded 4 Nov 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect form 1.pdf · uploaded 23 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Annual Report 22-23.pdf · uploaded 23 Nov 2023Source
- 5 Building Plan Approval / NA Order for plotted development1-3 - converted.pdf · uploaded 1 Aug 2024Source
- 6 Building Plan Approval / NA Order for plotted development2-3 - converted.pdf · uploaded 1 Aug 2024Source
- 7 Building Plan Approval / NA Order for plotted development3-3 - converted.pdf · uploaded 1 Aug 2024Source
- 3 Commencement Certificates / NA Order for plotted developmentCC - converted.pdf · uploaded 1 Aug 2024Source
- 3 Declaration about Commencement CertificateCC DEC - converted.pdf · uploaded 1 Aug 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)arch - converted.pdf · uploaded 1 Aug 2024Source
- 2 Disclosure of sold/ booked inventorySOLD.pdf · uploaded 1 Aug 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 1.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 2.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 3.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 4.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 5.pdf · uploaded 7 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Chartered Accountant Certificate - converted.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 1.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 2.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 3.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 4.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 5.pdf · uploaded 7 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Chartered Accountant Certificate - converted.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 1.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 2.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 3.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 4.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 5.pdf · uploaded 7 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Chartered Accountant Certificate - converted.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 1.pdf · uploaded 7 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 2.pdf · uploaded 7 Oct 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 3.pdf · uploaded 7 Oct 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 4.pdf · uploaded 7 Oct 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 5.pdf · uploaded 7 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Chartered Accountant Certificate - converted.pdf · uploaded 7 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 3-22.pdf · uploaded 21 Jun 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)2 6-22.pdf · uploaded 21 Jun 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 9-22.pdf · uploaded 21 Jun 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)4 12-22.pdf · uploaded 21 Jun 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)5 3-23.pdf · uploaded 21 Jun 2025Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)6 6-23.pdf · uploaded 21 Jun 2025Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)7 9-23.pdf · uploaded 21 Jun 2025Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)8 12-23.pdf · uploaded 21 Jun 2025Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)9 3-24.pdf · uploaded 21 Jun 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Pride reality - Certificate 22-23.pdf · uploaded 26 Jun 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)Pride reality - Certificate 23-24.pdf · uploaded 26 Jun 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG 3-22.pdf · uploaded 1 Jul 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG 6-22.pdf · uploaded 1 Jul 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG 9 -22.pdf · uploaded 1 Jul 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG 12-22.pdf · uploaded 1 Jul 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG 3-23.pdf · uploaded 1 Jul 2025Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG 6-23.pdf · uploaded 1 Jul 2025Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG 9-23.pdf · uploaded 1 Jul 2025Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG 12-23.pdf · uploaded 1 Jul 2025Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG 3-24.pdf · uploaded 1 Jul 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A -21-22.pdf · uploaded 1 Jul 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2A-22-23.pdf · uploaded 1 Jul 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A- 23-24.pdf · uploaded 1 Jul 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 APR 25 TO 30 JUNE 25.pdf · uploaded 21 Jul 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)10 6-24.pdf · uploaded 21 Jul 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)11 9-24.pdf · uploaded 21 Jul 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)12 12-24.pdf · uploaded 21 Jul 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)13 3-25.pdf · uploaded 21 Jul 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)6-24.pdf · uploaded 21 Jul 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)9-24.pdf · uploaded 21 Jul 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)12-24.pdf · uploaded 21 Jul 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)3-25.pdf · uploaded 21 Jul 2025Source
- 1 Disclosure of sold/ booked inventorySOLD 5-25.pdf · uploaded 22 Jul 2025Source
- Form 1arch 1 JAN 22 TO 31 MARCH 22.pdf · uploaded 29 Sep 2025Source
- Form 1arch 1 APR 22 TO 30 JUNE 22.pdf · uploaded 29 Sep 2025Source
- Form 1arch 1 JULY 22 TO 30 SEP 22.pdf · uploaded 29 Sep 2025Source
- Form 1ARCH 3.pdf · uploaded 29 Sep 2025Source
- Form 1ARCH 2.pdf · uploaded 29 Sep 2025Source
- Form 1ARCH 1.pdf · uploaded 29 Sep 2025Source
- Form 1ARCH 5.pdf · uploaded 29 Sep 2025Source
- Form 1ARCH 4.pdf · uploaded 29 Sep 2025Source
- Form 1arch 1 APR 24 TO 30 JUN 24.pdf · uploaded 29 Sep 2025Source
- Form 1arch 1 JULY 24 TO 30 SEP 24.pdf · uploaded 29 Sep 2025Source
- Form 1arch 1 OCT 24 TO 31 DEC 24.pdf · uploaded 29 Sep 2025Source
- Form 1ARCH 5.pdf · uploaded 29 Sep 2025Source
- Form 2ENG 3-22.pdf · uploaded 29 Sep 2025Source
- Form 2ENG 6-22.pdf · uploaded 29 Sep 2025Source
- Form 2ENG 9 -22.pdf · uploaded 29 Sep 2025Source
- Form 2ENG 12-22.pdf · uploaded 29 Sep 2025Source
- Form 2ENG 3-23.pdf · uploaded 29 Sep 2025Source
- Form 2ENG 6-23.pdf · uploaded 29 Sep 2025Source
- Form 2ENG 12-23.pdf · uploaded 29 Sep 2025Source
- Form 2ENG 3-24.pdf · uploaded 29 Sep 2025Source
- Form 2eng 6-24.pdf · uploaded 29 Sep 2025Source
- Form 2eng 9-24.pdf · uploaded 29 Sep 2025Source
- Form 2eng 12-24.pdf · uploaded 29 Sep 2025Source
- Form 2ENG 9-23.pdf · uploaded 29 Sep 2025Source
- Form 3ca 3-22.pdf · uploaded 29 Sep 2025Source
- Form 3ca 2 6-22.pdf · uploaded 29 Sep 2025Source
- Form 3ca 3 9-22.pdf · uploaded 29 Sep 2025Source
- Form 3ca 4 12-22.pdf · uploaded 29 Sep 2025Source
- Form 3ca 5 3-23.pdf · uploaded 29 Sep 2025Source
- Form 3ca 6 6-23.pdf · uploaded 29 Sep 2025Source
- Form 3ca 8 12-23.pdf · uploaded 29 Sep 2025Source
- Form 3ca 9 3-24.pdf · uploaded 29 Sep 2025Source
- Form 3ca 10 6-24.pdf · uploaded 29 Sep 2025Source
- Form 3ca 11 9-24.pdf · uploaded 29 Sep 2025Source
- Form 3ca 12 12-24.pdf · uploaded 29 Sep 2025Source
- Form 3ca 7 9-23.pdf · uploaded 29 Sep 2025Source
- Disclosure of Sold and Booked Inventorysold.pdf · uploaded 29 Sep 2025View
- Disclosure of Sold and Booked Inventorysold.pdf · uploaded 29 Sep 2025View
- Disclosure of Sold and Booked InventoryNandanvan Sold 2.pdf · uploaded 29 Sep 2025View
- Disclosure of Sold and Booked InventoryNandanvan Sold 3.pdf · uploaded 29 Sep 2025View
- Disclosure of Sold and Booked InventoryNandanvan Sold 4.pdf · uploaded 29 Sep 2025View
- Disclosure of Sold and Booked InventoryNandanvan Sold 5.pdf · uploaded 29 Sep 2025View
- Disclosure of Sold and Booked InventoryNandanvan Sold 7.pdf · uploaded 29 Sep 2025View
- Disclosure of Sold and Booked InventoryNandanvan Sold 8.pdf · uploaded 29 Sep 2025View
- Disclosure of Sold and Booked InventoryNandanvan Sold 9.pdf · uploaded 29 Sep 2025View
- Disclosure of Sold and Booked InventoryNandanvan Sold 10.pdf · uploaded 29 Sep 2025View
- Disclosure of Sold and Booked InventoryNandanvan Sold 11.pdf · uploaded 29 Sep 2025View
- Disclosure of Sold and Booked InventoryNandanvan Sold 6.pdf · uploaded 29 Sep 2025View
- Form 2A (FY 2021-2022)Form 2A -1.pdf · uploaded 29 Sep 2025Source
- Form 2A (FY 2022-2023)Form 2A -2.pdf · uploaded 29 Sep 2025Source
- Form 2A (FY 2023-2024)Form 2A - 3.pdf · uploaded 29 Sep 2025Source
- Form 2A (FY 2024-2025)Form 2A -4.pdf · uploaded 29 Sep 2025Source
- Form 5 (FY 2022-2023)Pride reality - Certificate 22-23.pdf · uploaded 26 Oct 2025Source
- Form 5 (FY 2023-2024)Pride reality - Certificate 23-24.pdf · uploaded 26 Oct 2025Source
Technical
- DocumentNA ORDER.pdf · uploaded 17 Jan 2022Source
- Documentplan.pdf · uploaded 17 Jan 2022Source
- DocumentPLAN 1.pdf · uploaded 4 Nov 2023Source
- DocumentPLAN 2.pdf · uploaded 4 Nov 2023Source
- DocumentPLAN 3.pdf · uploaded 4 Nov 2023Source
- Document1-3 - converted.pdf · uploaded 1 Aug 2024Source
- Document2-3 - converted.pdf · uploaded 1 Aug 2024Source
- Document3-3 - converted.pdf · uploaded 1 Aug 2024Source
Technical (Architect)
- Documentarch - converted.pdf · uploaded 1 Aug 2024Source
- DocumentARCH 1.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 2.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 3.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 4.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 5.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 1.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 2.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 3.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 4.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 5.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 1.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 2.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 3.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 4.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 5.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 1.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 2.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 3.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 4.pdf · uploaded 7 Oct 2024Source
- DocumentARCH 5.pdf · uploaded 7 Oct 2024Source
- Document1 APR 25 TO 30 JUNE 25.pdf · uploaded 21 Jul 2025Source
Technical (Engineer)
- DocumentENG 3-22.pdf · uploaded 1 Jul 2025Source
- DocumentENG 6-22.pdf · uploaded 1 Jul 2025Source
- DocumentENG 9 -22.pdf · uploaded 1 Jul 2025Source
- DocumentENG 12-22.pdf · uploaded 1 Jul 2025Source
- DocumentENG 3-23.pdf · uploaded 1 Jul 2025Source
- DocumentENG 6-23.pdf · uploaded 1 Jul 2025Source
- DocumentENG 9-23.pdf · uploaded 1 Jul 2025Source
- DocumentENG 12-23.pdf · uploaded 1 Jul 2025Source
- DocumentENG 3-24.pdf · uploaded 1 Jul 2025Source
- Document6-24.pdf · uploaded 21 Jul 2025Source
- Document9-24.pdf · uploaded 21 Jul 2025Source
- Document12-24.pdf · uploaded 21 Jul 2025Source
- Document3-25.pdf · uploaded 21 Jul 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel GAT NO.116
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK63 units in all
- Address
- Gat No.116, Gat No 116, KirkatwadiPIN 411024
- Village
- Kirkatwadi, Haveli taluka
- Location
- 18.44100, 73.79341
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- 9 M Wide Road
- South
- Gat No 120
- East
- Gat No 117
- West
- Gat No 115
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking63 units
51 of 63 units booked (81%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 37.9 sq m · 408 sq ft | 6 | 4 |
| 1BHK | 38 sq m · 409 sq ft | 7 | 6 |
| 1BHK | 40 sq m · 431 sq ft | 16 | 13 |
| 1BHK | 40.25 sq m · 433 sq ft | 12 | 11 |
| 2BHK | 57.5 sq m · 619 sq ft | 3 | 2 |
| 2BHK | 58 sq m · 624 sq ft | 2 | 2 |
| 2BHK | 59.05 sq m · 636 sq ft | 3 | 2 |
| 2BHK | 60 sq m · 646 sq ft | 5 | 4 |
Show all 11 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 62.35 sq m · 671 sq ft | 3 | 3 |
| 2BHK | 62.52 sq m · 673 sq ft | 3 | 2 |
| 2BHK | 62.85 sq m · 677 sq ft | 3 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | S D Walhekar . . | — |
| Chartered accountant | Kishor Mandhare . . | — |
| Chartered accountant | V G Naikawadi | — |
| Engineer | Shubham Paygude | — |
Source: MahaRERA project page. Contact details are not shown.