Promised date passed6 floors · 13 flatsRERA P52100052757
Main building, Omkar
Deedo IDDP-PUN-EQ5T-OMKAR6 flats have a sale on record, 0 are booked without a sale deed yet and 0 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
Median saleNot on recordneeds 3 or more sales
Booked46%6 of 13 · Oct 2026
Completion31 Dec 2025as registered
Every flat, floor by floor
Tap a flat to see its record.
- Sale registered
- Reserved, rehab or other
010203
Fl 6
Fl 5
Fl 4
Fl 3
Fl 2
Fl 1
2 BHK1 BHK
Sale status from MahaRERA's Oct 2026 disclosure; deeds from IGR Index II, placed on a flat only when the deed names this tower and flat. “Listed by developer” comes from the developer and is labelled as such.
SelectedSold
Flat 602
2 BHK · 653 sq ft · floor 6
- Deeds
- 0
- Last activity
- None on record
- Last sale
- None registered
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| FLA 503 1BHK | 42.6 m² (459 sq.ft) | 1 | 1 |
| FLAT 101 3BHK | 96.4 m² (1,037 sq.ft) | 1 | 0 |
| FLAT 102 2BHK | 64.2 m² (691 sq.ft) | 1 | 1 |
| FLAT 201 3BHK | 96.4 m² (1,037 sq.ft) | 1 | 1 |
| FLAT 202 2BHK | 64.2 m² (691 sq.ft) | 1 | 1 |
| FLAT 301 3BHK | 96.4 m² (1,037 sq.ft) | 1 | 1 |
| FLAT 302 2BHK | 64.2 m² (691 sq.ft) | 1 | 1 |
| FLAT 401 3BHK | 87.8 m² (945 sq.ft) | 1 | 1 |
| FLAT 402 2BHK | 64.2 m² (691 sq.ft) | 1 | 0 |
| FLAT 501 2BHK | 78.8 m² (848 sq.ft) | 1 | 1 |
| FLAT 502 1RK | 32.4 m² (349 sq.ft) | 1 | 1 |
| FLAT 601 3BHK | 96.4 m² (1,037 sq.ft) | 1 | 1 |
| FLAT 602 2BHK | 64.2 m² (691 sq.ft) | 1 | 1 |
As registered with MahaRERA
- RERA registration
- P52100052757 · registered 22 Sep 2023
- Promised completion
- 31 Dec 2025
- Revised completion
- 31 Dec 2025
- Sanctioned habitable floors
- 6
- Building
- OMKAR
- Sanctioned floors (incl. basement, stilt, podium)
- 6
- Units declared
- 13
- Homes
- 13
- Shops and offices
- 0
- Sanctioned FSI area (sq m)
- 7 (P+6)
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-EQ5T-OMKAR
Questions about Main building
How many flats in Main building are sold?
6 flats have a sale on record, 0 are booked without a sale deed yet and 0 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
When is Main building due for completion?
The MahaRERA registration promises 31 Dec 2025.
How many floors does Main building have?
6 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology