Golden Wings
Deedo IDDP-PUN-325ECompletion was pushed back 4 months, to Jan 2028; no MahaRERA orders on record; 0% of its units are booked.
Karve Nagar, Pune 411052 · by Phoenix Builders & Co
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Jan 2028
- This projectRegistered 14 Nov 2024, completion promised 30 Sep 2027, revised to 30 Jan 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100077969
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100077969 | 14 Nov 2024 | 30 Sep 2027 | 30 Jan 2028 | Phoenix Builders & Co. | Project page |
Documents83
1 document held by Deedo, 82 filings listed on MahaRERA's project page
Finance
- PAN CardPAN Card - Firm.pdf · uploaded 18 Oct 2024Source
Legal
- Other – Legal3_Sale Deed.pdf · uploaded 18 Oct 2024Source
- Other – Legal2_Sale Deed.pdf · uploaded 18 Oct 2024Source
- Other – Legal1_Sale Deed.pdf · uploaded 18 Oct 2024Source
- Legal Title reportLegal Title Report -CTS NO 669-5.pdf · uploaded 18 Oct 2024Source
- Declaration Form BForm B.pdf · uploaded 18 Oct 2024Source
Migrated
- 1 PAN CardPAN Card - Firm.pdf · uploaded 18 Oct 2024Source
Show all 83 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportLegal Title Report -CTS NO 669-5.pdf · uploaded 18 Oct 2024Source
- 1 a Details of encumbrances concerned to FinanceEncumbrance To Finance and Legal.pdf · uploaded 18 Oct 2024Source
- 1 Copy of Layout Approval (in case of layout)Plan_compressed.pdf · uploaded 18 Oct 2024Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 18 Oct 2024Source
- 1 Declaration in FORM BForm B.pdf · uploaded 18 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 18 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form - 2 Enigineer Certificate.pdf · uploaded 18 Oct 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certficate.pdf · uploaded 18 Oct 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentPlan_compressed.pdf · uploaded 18 Oct 2024Source
- 1 Other – Legal1_Sale Deed.pdf · uploaded 18 Oct 2024Source
- 2 Other – Legal2_Sale Deed.pdf · uploaded 18 Oct 2024Source
- 3 Other – Legal3_Sale Deed.pdf · uploaded 18 Oct 2024Source
- 1 Declaration about Commencement CertificateDeclaration about Commencement Certificate.pdf · uploaded 18 Oct 2024Source
- 1 CERSAI detailsCERSAI Declaration.pdf · uploaded 18 Oct 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A Revised.pdf · uploaded 18 Oct 2024Source
- 1 Deviation Report with respect to Allotment letterDeviation - Allotment Letter.pdf · uploaded 18 Oct 2024Source
- 1 b Details of encumbrances concerned to LegalEncumbrance To Finance and Legal.pdf · uploaded 18 Oct 2024Source
- 1 Other – TechnicalAnnexure-A as per order 50-2024.pdf · uploaded 18 Oct 2024Source
- 1 Deviation Report with respect to model copy of AgreementDeviation to model AFS.pdf · uploaded 18 Oct 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclossureof Interest - Aditya Jadhav.pdf · uploaded 18 Oct 2024Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDisclossureof Interest - Akassh Awasare.pdf · uploaded 18 Oct 2024Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsDisclossureof Interest - Akshay Kate.pdf · uploaded 18 Oct 2024Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsDisclossureof Interest - Ashirwadd Jadhav.pdf · uploaded 18 Oct 2024Source
- 5 Disclosure of Interest in Other Real Estate OrganizationsDisclossureof Interest - Kiran Wanjale.pdf · uploaded 18 Oct 2024Source
- 6 Disclosure of Interest in Other Real Estate OrganizationsDisclossureof Interest - Mr Sourabh Barate.pdf · uploaded 18 Oct 2024Source
- 7 Disclosure of Interest in Other Real Estate OrganizationsDisclossureof Interest - Prashant Daswadkar.pdf · uploaded 18 Oct 2024Source
- 8 Disclosure of Interest in Other Real Estate OrganizationsDisclossureof Interest - Satish Wanjale.pdf · uploaded 18 Oct 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B Revised.pdf · uploaded 18 Oct 2024Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure for Secured-Unsecured Finance availed.pdf · uploaded 18 Oct 2024Source
- 1 Proforma of Agreement for saleModel_Agreement For Sale.pdf · uploaded 21 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA.pdf · uploaded 22 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - till Dec 2024.pdf · uploaded 16 Apr 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - till March 2025.pdf · uploaded 16 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 _ 31-12-2024.pdf · uploaded 16 Apr 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_31-03-2025.pdf · uploaded 16 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inv 31-12-2024.pdf · uploaded 16 Apr 2025Source
- 2 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inv 31-03-2025.pdf · uploaded 16 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form I_ 31-12-2024.pdf · uploaded 17 Apr 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form I_ 31-03-2025.pdf · uploaded 17 Apr 2025Source
- Form 1Form 1 FY 2024-25 Q3.pdf · uploaded 7 Jul 2025Source
- Form 2Form 2 FY 2024-25 Q3.pdf · uploaded 7 Jul 2025Source
- Form 3Form 3 FY 2024-25 Q3.pdf · uploaded 7 Jul 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold - Unsold Inv FY 2024-25 Q3.pdf · uploaded 7 Jul 2025Source
- Form 1Form 1 FY 2024-25 Q4.pdf · uploaded 7 Jul 2025Source
- Form 2Form 2 FY 2024-25 Q4.pdf · uploaded 7 Jul 2025Source
- Form 3Form 3 FY 2024-25 Q4.pdf · uploaded 7 Jul 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Unsold Inv FY 2024-25 Q4.pdf · uploaded 7 Jul 2025Source
- Form 2A (FY 2024-2025)FORM-2A.pdf · uploaded 5 Dec 2025Source
- Form 5 (FY 2024-2025)Form 5 (2).pdf · uploaded 5 Dec 2025Source
- Withdrawal Update Form 1Form 1 Architect Certificate.pdf · uploaded 6 Dec 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 6 Dec 2025Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 6 Dec 2025Source
- Withdrawal Update Form 1Architect Certificate(2).pdf · uploaded 5 Feb 2026Source
- Withdrawal Update Form 2Form 2 .pdf · uploaded 5 Feb 2026Source
- Withdrawal Update Form 3Form 3-1.pdf · uploaded 5 Feb 2026Source
- Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 16 Feb 2026Source
- Withdrawal Update Form 1Form 1 .pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 2Form 2 .pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 1Form 1 .pdf · uploaded 24 Jul 2026Source
- Withdrawal Update Form 2Form 2 .pdf · uploaded 24 Jul 2026Source
- Withdrawal Update Form 3Form 3 .pdf · uploaded 24 Jul 2026Source
- Form 5 (FY 2025-2026)Form 5 (2025 2026 ).pdf · uploaded 28 Sep 2026Source
Technical
- DocumentPlan_compressed.pdf · uploaded 18 Oct 2024Source
- DocumentPlan_compressed.pdf · uploaded 18 Oct 2024Source
- Other – TechnicalAnnexure-A as per order 50-2024.pdf · uploaded 18 Oct 2024Source
- DocumentLayout Plan .pdf · uploaded 18 Apr 2026Source
- OthersDeclaretion About Commencement Certificate .pdf · uploaded 18 Apr 2026Source
- DocumentLayout Plan .pdf · uploaded 24 Jul 2026Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel CTS. No. 669/5
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK6 units in all
- Address
- CTS. No. 669/5, Near Vedant Hall, Hingne-BudrukPIN 411052
- Village
- Karve Nagar, Haveli taluka
- Land area for this project
- 326 sq m (3,504 sq ft)
- Permissible built-up area
- 801 sq m (8,625 sq ft)
- Sanctioned built-up area
- 800 sq m (8,609 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 171
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
CTS. No. 669/5
Boundaries
- North
- By the property owned by Mr Vinayak Athawale
- South
- By Nisarg Apartment Building
- East
- By Property of Mr Dharap
- West
- By Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking6 units
0 of 6 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 61.14 sq m · 658 sq ft | 3 | 0 |
| 2BHK | 68.19 sq m · 734 sq ft | 3 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Shankar D Gajage | — |
| Chartered accountant | Jejerao Awale & Associates | — |
| Engineer | Nilesh Sahebra Pawar | — |
| Engineer | Sidhant Pratap Khirid | — |
Source: MahaRERA project page. Contact details are not shown.