Extended 4 mo6 floors · 24 flatsRERA PM1260002600666
Main building, Darade Chavan Complex
Deedo IDDP-PUN-80PG-DCC17 of 24 flats are unsold and 0 are booked, per MahaRERA's Oct 2026 disclosure; no sale deed is on record yet.
Median saleNot on recordneeds 3 or more sales
Booked0%0 of 24 · Oct 2026
Completion30 Apr 203031 Dec 2029 · revised
Every flat, floor by floor
Tap a flat to see its record.
- Unsold
- Reserved, rehab or other
Fl 6
Fl 5
Fl 4
Fl 3
Fl 2
Fl 1
Fl G
Fl B1
Sale status from MahaRERA's Oct 2026 disclosure; deeds from IGR Index II, placed on a flat only when the deed names this tower and flat. “Listed by developer” comes from the developer and is labelled as such.
SelectedOther
Flat 24
1 BHK · 520 sq ft · floor 4
- Deeds
- 0
- Last activity
- None on record
- Last sale
- None registered
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Not on record | Not on record | 49 | Not on record |
As registered with MahaRERA
- RERA registration
- PM1260002600666 · registered 4 Jun 2026
- Promised completion
- 31 Dec 2029
- Revised completion
- 30 Apr 2030
- Sanctioned habitable floors
- 6
- Building
- DARADE CHAVAN COMPLEX
- Sanctioned floors (incl. basement, stilt, podium)
- 6
- Units declared
- 49
- Homes
- 24
- Shops and offices
- 25
- Sanctioned FSI area (sq m)
- 6
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-80PG-DCC
Questions about Main building
How many flats in Main building are sold?
0 flats have a sale on record, 0 are booked without a sale deed yet and 17 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
When is Main building due for completion?
The MahaRERA registration promises 31 Dec 2029, revised to 30 Apr 2030.
How many floors does Main building have?
6 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology