Extended 17 mo13 floorsRERA P52100001732
Main building, Hazel View
Deedo IDDP-PUN-Z319-HVMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked43%32 of 75 · MahaRERA
Completion30 Nov 20201 Jun 2019 · revised
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 37.4 m² (402 sq.ft) | 3 | 1 |
| 1 BHK | 37.4 m² (402 sq.ft) | 4 | 3 |
| 1 BHK | 50.3 m² (542 sq.ft) | 1 | 0 |
| 2 BHK | 45.4 m² (488 sq.ft) | 5 | 1 |
| 2 BHK | 46.9 m² (505 sq.ft) | 1 | 0 |
| 2 BHK | 47.2 m² (508 sq.ft) | 1 | 0 |
| 2 BHK | 47.3 m² (509 sq.ft) | 4 | 0 |
| 2 BHK | 47.3 m² (510 sq.ft) | 4 | 3 |
| 2 BHK | 47.4 m² (510 sq.ft) | 1 | 1 |
| 2 BHK | 47.4 m² (510 sq.ft) | 1 | 0 |
| 2 BHK | 47.4 m² (510 sq.ft) | 4 | 3 |
| 2 BHK | 47.5 m² (511 sq.ft) | 4 | 3 |
| 2 BHK | 47.5 m² (511 sq.ft) | 1 | 0 |
| 2 BHK | 47.6 m² (512 sq.ft) | 1 | 0 |
| 2 BHK | 48.2 m² (519 sq.ft) | 4 | 3 |
| 2 BHK | 48.2 m² (519 sq.ft) | 1 | 0 |
| 2 BHK | 48.4 m² (520 sq.ft) | 3 | 0 |
| 2 BHK | 48.8 m² (525 sq.ft) | 1 | 0 |
| 2 BHK | 48.9 m² (526 sq.ft) | 3 | 1 |
| 2 BHK | 49.3 m² (530 sq.ft) | 3 | 0 |
| 2 BHK | 49.4 m² (531 sq.ft) | 4 | 1 |
| 2 BHK | 50 m² (538 sq.ft) | 4 | 4 |
| 2 BHK | 50.5 m² (543 sq.ft) | 2 | 0 |
| 2 BHK | 52.1 m² (561 sq.ft) | 3 | 3 |
| 2 BHK | 52.1 m² (561 sq.ft) | 1 | 1 |
| 2 BHK | 56.3 m² (606 sq.ft) | 3 | 3 |
| 2 BHK | 65.7 m² (708 sq.ft) | 1 | 1 |
| SHOP 1 | 28.3 m² (304 sq.ft) | 1 | 0 |
| SHOP 2 | 24.9 m² (268 sq.ft) | 1 | 0 |
| SHOP 3 | 18.6 m² (200 sq.ft) | 1 | 0 |
| SHOP 4 | 20.6 m² (222 sq.ft) | 1 | 0 |
| SHOP 5 | 9.6 m² (103 sq.ft) | 1 | 0 |
| SHOP 6 | 14.1 m² (152 sq.ft) | 1 | 0 |
| SHOP 7 | 10 m² (108 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P52100001732 · registered 29 Jul 2017
- Promised completion
- 1 Jun 2019
- Revised completion
- 30 Nov 2020
- Sanctioned habitable floors
- 13
- Building
- HAZEL VIEW
- Sanctioned floors (incl. basement, stilt, podium)
- 13
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-Z319-HV
Questions about Main building
When is Main building due for completion?
The MahaRERA registration promises 1 Jun 2019, revised to 30 Nov 2020.
How many floors does Main building have?
13 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology