Deedo IDDP-PUN-TB24Completion was pushed back 4 months, to Aug 2027; no MahaRERA orders on record; 27% of its units are booked.
Hinjavadi (Ct), Pune 411057 · Property rates in Hinjavadi (Ct) · by Anand Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Aug 2027
- This projectRegistered 2 May 2024, completion promised 5 Apr 2027, revised to 5 Aug 2027.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100055957
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100055957 | 2 May 2024 | 5 Apr 2027 | 5 Aug 2027 | Anand Developers | Project page |
Documents78
2 documents held by Deedo, 76 filings listed on MahaRERA's project page
Finance
- PAN CardPAN Firm.pdf · uploaded 18 Apr 2024Source
Legal
- Other – Legal7'12 Hinjawadi 1_3_2.pdf · uploaded 18 Apr 2024Source
- Other – Legal7'12 Hinjawadi 1_4_1.pdf · uploaded 18 Apr 2024Source
- Other – Legal7'12 Hinjawai 1_4_2.pdf · uploaded 18 Apr 2024Source
- Other – Legal1-4-2.pdf · uploaded 18 Apr 2024Source
- Other – LegalHinjawadi 1 4 1_compressed.pdf · uploaded 18 Apr 2024Source
Show all 78 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardPAN Firm.pdf · uploaded 18 Apr 2024Source
- 1 a Details of encumbrances concerned to FinanceNo Financial Enc.pdf · uploaded 18 Apr 2024Source
- 2 a Details of encumbrances concerned to FinanceNo Legal Encb.pdf · uploaded 18 Apr 2024Source
- 1 b Details of encumbrances concerned to LegalNo Financial Enc.pdf · uploaded 18 Apr 2024Source
- 2 b Details of encumbrances concerned to LegalNo Legal Encb.pdf · uploaded 18 Apr 2024Source
- 1 Copy of Layout Approval (in case of layout)Layout Highlighted_compressed.pdf · uploaded 18 Apr 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan 2'3_compressed.pdf · uploaded 18 Apr 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentBuilding Plan 3'3_compressed.pdf · uploaded 18 Apr 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement.pdf · uploaded 18 Apr 2024Source
- 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 18 Apr 2024Source
- 1 Declaration in FORM BDeclaration Form B.pdf · uploaded 18 Apr 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsVijaykumar.pdf · uploaded 18 Apr 2024Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsPramod.pdf · uploaded 18 Apr 2024Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsSunita.pdf · uploaded 18 Apr 2024Source
- 1 Proforma of Allotment letterAllottment letter.pdf · uploaded 18 Apr 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Declaration.pdf · uploaded 18 Apr 2024Source
- 1 Deviation Report with respect to Allotment letterNo Deviation Allotment Ltr.pdf · uploaded 18 Apr 2024Source
- 1 Deviation Report with respect to model copy of AgreementNo Deviation Agreement.pdf · uploaded 18 Apr 2024Source
- 1 Other – Legal7'12 Hinjawadi 1_3_2.pdf · uploaded 18 Apr 2024Source
- 2 Other – Legal7'12 Hinjawadi 1_4_1.pdf · uploaded 18 Apr 2024Source
- 3 Other – Legal7'12 Hinjawai 1_4_2.pdf · uploaded 18 Apr 2024Source
- 4 Other – Legal1-4-2.pdf · uploaded 18 Apr 2024Source
- 5 Other – LegalHinjawadi 1 4 1_compressed.pdf · uploaded 18 Apr 2024Source
- 6 Other – LegalHinjawadi 1 3 2_compressed.pdf · uploaded 18 Apr 2024Source
- 1 Copy of the legal title reportLegal Title Final Uploaded.pdf · uploaded 19 Apr 2024Source
- 1 CERSAI detailsFINAL CERSAI.pdf · uploaded 19 Apr 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Uploaded.pdf · uploaded 19 Apr 2024Source
- 1 Proforma of Agreement for saleAgreement to sale draft Model pgmj.pdf · uploaded 19 Apr 2024Source
- 1 Other – TechnicalOrder 50.pdf · uploaded 19 Apr 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Final.pdf · uploaded 30 Jan 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 30 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 30 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 30 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Final.pdf · uploaded 30 Jan 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 30 Jan 2025Source
- 1 Disclosure of sold/ booked inventorySold Circular.pdf · uploaded 30 Jan 2025Source
- 2 Disclosure of sold/ booked inventorySold Circular.pdf · uploaded 30 Jan 2025Source
- Form 1Form 1.pdf · uploaded 19 Jul 2025Source
- Form 2Form 2 Final.pdf · uploaded 19 Jul 2025Source
- Form 3Form 3 Final.pdf · uploaded 19 Jul 2025Source
- Disclosure of Sold and Booked InventoryRevised Sold Circular.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 19 Oct 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 19 Oct 2025Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 19 Oct 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 20 Apr 2026Source
- Form 5 (FY 2024-2025)Form 5 Final.pdf · uploaded 27 Apr 2026Source
- Form 2A (FY 2024-2025)Form 2A.pdf · uploaded 21 May 2026Source
- Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 22 May 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 24 Jul 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 24 Jul 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 24 Jul 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 1/3/2, 1/4/2
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Shop37 units in all
- Address
- Survey No. 1/4/1, 1/4/2, 1/3/2, Mauje-Hinjewadi, Mauje-HinjewadiPIN 411057
- Village
- Hinjavadi (CT), Mulshi taluka
- Location
- 18.58224, 73.72636
- Land area for this project
- 1,200 sq m (12,917 sq ft)
- Permissible built-up area
- 2,796 sq m (30,094 sq ft)
- Sanctioned built-up area
- 2,793 sq m (30,060 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SURVEY NO. 1/4/1, 1/4/2, 1/3/2
Boundaries
- North
- By S No 1-11
- South
- By S No 1-2
- East
- By S No 2-8
- West
- By Main Chinchwad Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking37 units
10 of 37 units booked (27%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 38.19 sq m · 411 sq ft | 2 | 1 |
| 1BHK | 48.52 sq m · 522 sq ft | 1 | 0 |
| 1BHK | 56.51 sq m · 608 sq ft | 1 | 0 |
| 1BHK | 59.14 sq m · 637 sq ft | 3 | 0 |
| 1BHK | 63.62 sq m · 685 sq ft | 1 | 0 |
| 1BHK | 78.71 sq m · 847 sq ft | 1 | 0 |
| 1BHK | 103.58 sq m · 1,115 sq ft | 1 | 0 |
| 2BHK | 52.38 sq m · 564 sq ft | 5 | 1 |
Show all 21 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 52.84 sq m · 569 sq ft | 5 | 1 |
| 2BHK | 54.77 sq m · 590 sq ft | 3 | 0 |
| 2BHK | 57.13 sq m · 615 sq ft | 1 | 0 |
| 2BHK | 67.86 sq m · 730 sq ft | 1 | 0 |
| 2BHK | 78.55 sq m · 846 sq ft | 3 | 0 |
| Shop | 13.64 sq m · 147 sq ft | 2 | 2 |
| Shop | 15.8 sq m · 170 sq ft | 1 | 1 |
| Shop | 18.2 sq m · 196 sq ft | 1 | 1 |
| Shop | 18.36 sq m · 198 sq ft | 1 | 0 |
| Shop | 18.96 sq m · 204 sq ft | 1 | 1 |
| Shop | 20.93 sq m · 225 sq ft | 1 | 1 |
| Shop | 21.6 sq m · 233 sq ft | 1 | 1 |
| Shop | 23.76 sq m · 256 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | En Visage Architects And Designers | — |
| Chartered accountant | H K Pandya And Company | — |
| Engineer | Rathi's Group | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Hinjavadi (Ct)
- Menlo NestRERA PR1260002601233
- Shankeshwar Kingsland Phase 1RERA PR1261012600728
- Lodha Hinjewadi Phase 3RERA PR1260002502131
- Hinjewadi Premium - Tower 10RERA PR1260002502009
- Geras Joy on the Tree Tops Project BRERA PR1261012501648
- Kohinoor Royale TowersRERA PR1260002501033
- Hinjewadi ProjectRERA PR1260002500741
- Godrej Eden Estate Phase 3RERA PP1260002500516
All 83 projects in Hinjavadi (Ct) · Compare Anand Vrindavan with another project