Vrindavan Heights Phase III
Deedo IDDP-PUN-VN4GCompletion was pushed back 1 year, to Mar 2028; no MahaRERA orders on record; 40% of its units are booked.
Hadapsar, Pune 411028 · Property rates in Hadapsar · by Kwality World Developers (Aop)
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year, to Mar 2028
- This projectRegistered 21 Feb 2024, completion promised 31 Mar 2027, revised to 27 Mar 2028.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
- Primary sale · Sep 2026
- Primary sale · Aug 2026
- Primary sale · Aug 2026
- Primary sale · Aug 2026
- Primary sale · Jul 2026
- Primary sale · Jul 2026
- Primary sale · Jul 2026
- Primary sale · Jul 2026
- Primary sale · Jul 2026
- Primary sale · Jul 2026
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Sep 2026 | Vrindavan Heights Wing C · 1503 | Primary sale | 798 sq ft | View Primary sale, Sep 2026 | |
| Aug 2026 | Vrindavan Heights Wing C · 1405 | Primary sale | 919 sq ft | View Primary sale, Aug 2026 | |
| Aug 2026 | Vrindavan Heights Wing C · 1702 | Primary sale | 798 sq ft | View Primary sale, Aug 2026 | |
| Aug 2026 | Vrindavan Heights Wing C · 1408 | Primary sale | 975 sq ft | View Primary sale, Aug 2026 | |
| Jul 2026 | Vrindavan Heights Wing C · 1505 | Primary sale | 919 sq ft | View Primary sale, Jul 2026 | |
| Jul 2026 | Vrindavan Heights Wing C · 1108 | Primary sale | 975 sq ft | View Primary sale, Jul 2026 | |
| Jul 2026 | Vrindavan Heights Wing C · 1001 | Primary sale | 975 sq ft | View Primary sale, Jul 2026 | |
| Jul 2026 | Vrindavan Heights Wing C · 1301 | Primary sale | 975 sq ft | View Primary sale, Jul 2026 | |
| Jul 2026 | Vrindavan Heights Wing C · 1502 | Primary sale | 798 sq ft | View Primary sale, Jul 2026 | |
| Jul 2026 | Vrindavan Heights Wing C · 705 | Primary sale | 919 sq ft | View Primary sale, Jul 2026 |
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100054968
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100054968 | 21 Feb 2024 | 31 Mar 2027 | 27 Mar 2028 | Kwality World Developers (Aop) | Project page |
Documents99
2 documents held by Deedo, 97 filings listed on MahaRERA's project page
Finance
- PAN CardPAN Kwality World Developers.pdf · uploaded 5 Sep 2023Source
Legal
Migrated
- 1 PAN CardPAN Kwality World Developers.pdf · uploaded 5 Sep 2023Source
Show all 99 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCC-Building.pdf · uploaded 5 Sep 2023Source
- 1 Deviation Report with respect to Allotment letterNo deviation respect to model copy of allotment.pdf · uploaded 5 Sep 2023Source
- 1 Proforma of Allotment letterAllotment Letter PDF_11zon.pdf · uploaded 18 Sep 2023Source
- 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 22 Dec 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer certificate.pdf · uploaded 22 Dec 2023Source
- 1 a Details of encumbrances concerned to FinanceNo encumbrance concerned and legal.pdf · uploaded 26 Dec 2023Source
- 1 b Details of encumbrances concerned to LegalNo encumbrance concerned and legal.pdf · uploaded 26 Dec 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_11zon.pdf · uploaded 26 Dec 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest in other real estate organizations 1.pdf · uploaded 26 Dec 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest in other real estate organizations 2.pdf · uploaded 26 Dec 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest in other real estate organizations 3.pdf · uploaded 26 Dec 2023Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest in other real estate organizations 4.pdf · uploaded 26 Dec 2023Source
- 1 Proforma of Agreement for saleFinal Agreement to Sale.pdf · uploaded 26 Dec 2023Source
- 1 Deviation Report with respect to model copy of AgreementNo deviation with respect to model copy of agreement.pdf · uploaded 26 Dec 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 29 Dec 2023Source
- 1 Declaration about Commencement Certificateilovepdf_merged.pdf · uploaded 19 Jan 2024Source
- 1 CERSAI detailsDeclaration about cersai.pdf · uploaded 29 Jan 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about separate bank account.pdf · uploaded 29 Jan 2024Source
- 1 Building Plan Approval / NA Order for plotted development02_11zon.pdf · uploaded 12 Feb 2024Source
- 2 Building Plan Approval / NA Order for plotted development03_11zon.pdf · uploaded 12 Feb 2024Source
- 3 Building Plan Approval / NA Order for plotted development04_11zon.pdf · uploaded 12 Feb 2024Source
- 4 Building Plan Approval / NA Order for plotted development05_11zon.pdf · uploaded 12 Feb 2024Source
- 5 Building Plan Approval / NA Order for plotted development06_11zon.pdf · uploaded 12 Feb 2024Source
- 6 Building Plan Approval / NA Order for plotted development07_11zon.pdf · uploaded 12 Feb 2024Source
- 7 Building Plan Approval / NA Order for plotted development08_11zon.pdf · uploaded 12 Feb 2024Source
- 8 Building Plan Approval / NA Order for plotted development09_11zon.pdf · uploaded 12 Feb 2024Source
- 1 Copy of Layout Approval (in case of layout)1-14 - Highlights new.pdf · uploaded 13 Feb 2024Source
- 1 Declaration in FORM BNotary.pdf · uploaded 17 Feb 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate_11zon.pdf · uploaded 18 Jul 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_11zon.pdf · uploaded 18 Jul 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 18 Jul 2024Source
- 2 Declaration in FORM Bform B_11zon.pdf · uploaded 23 Jul 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 9 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.pdf · uploaded 9 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 10 Dec 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 10 Dec 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 10 Dec 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 23 Dec 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form_3.pdf · uploaded 23 Dec 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 23 Dec 2024Source
- 1 Copy of Layout Approval (in case of layout)Copy of Layout 2_11zon.pdf · uploaded 4 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 2 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 2 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate.pdf · uploaded 2 Apr 2025Source
- 1 Declaration in FORM Bform B.pdf · uploaded 18 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 2 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 2 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_11zon.pdf · uploaded 2 May 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)Form 5.pdf · uploaded 17 May 2025Source
- 1 Disclosure of sold/ booked inventorysold booked inventory.pdf · uploaded 6 Jun 2025Source
- Form 1Form 1.pdf · uploaded 23 Jul 2025Source
- Form 2Form 2 (2).pdf · uploaded 23 Jul 2025Source
- Form 3Form 3.pdf · uploaded 23 Jul 2025Source
- Disclosure of Sold and Booked Inventorysold booked inventory.pdf · uploaded 23 Jul 2025Source
- Withdrawal Update Form 1Architect Certificate Sept 25.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 1Architect Certificate Sept 25.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 2Engineer Certificate Sept 25_11zon.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 2Engineer Certificate Sept 25_11zon.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 1Form 1 Dec 25.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 2Form 2 Dec 25_11zon.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 1Architect Cert Mar 2026.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Form 2_11zon.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 1Form 1 June 26.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 2Engineer Certificate June 26.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 18 Jul 2026Source
Technical
- Document02_11zon.pdf · uploaded 12 Feb 2024Source
- Document03_11zon.pdf · uploaded 12 Feb 2024Source
- Document04_11zon.pdf · uploaded 12 Feb 2024Source
- Document05_11zon.pdf · uploaded 12 Feb 2024Source
- Document06_11zon.pdf · uploaded 12 Feb 2024Source
- Document07_11zon.pdf · uploaded 12 Feb 2024Source
- Document08_11zon.pdf · uploaded 12 Feb 2024Source
- Document09_11zon.pdf · uploaded 12 Feb 2024Source
- Document1-14 - Highlights new.pdf · uploaded 13 Feb 2024Source
- DocumentCopy of Layout 2_11zon.pdf · uploaded 4 Feb 2025Source
- DocumentBuilding permission layout.pdf · uploaded 30 Jul 2025Source
- DocumentCommence certificate 03-01-24.pdf · uploaded 18 Jul 2026Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 183/3P 183/4 183/5A 183/5B 183/7
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —120 units in all
- Address
- 183/3P 183/4 183/5A 183/5B 183/7, Sade Satra Nali Road, HadapsarPIN 411028
- Village
- Hadapsar, Haveli taluka
- Location
- 18.31116, 73.56205
- Land area for this project
- 13,250 sq m (1,42,622 sq ft)
- Permissible built-up area
- 13,719 sq m (1,47,673 sq ft)
- Sanctioned built-up area
- 13,719 sq m (1,47,673 sq ft)
- Recreational open space
- 1,221 sq m (13,148 sq ft)
- Designated bank account
- 154
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
183/3P 183/4 183/5A 183/5B 183/7
Boundaries
- North
- S No 183 Land Owned by Somaji Tupe
- South
- S No 183 Land Owned by Baban Tupe
- East
- S No 191 Land Owned by Patilbua Namdeo Tupe
- West
- S No 181 Land Owned by Chandrashekhar ashtekar
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking120 units
120 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 120 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Hrishikesh Kulkarni | — |
| Chartered accountant | Baban Dangale | — |
| Chartered accountant | CA Aditya Patil | — |
| Engineer | Manish Gade | — |
| Registered real estate agent | Sanjay Kumar Ramteke | — |
Source: MahaRERA project page. Contact details are not shown.
Vrindavan Heights Phase III in numbers
Registered deals, summarised
Deedo has 49 registered documents at Vrindavan Heights Phase III, from Apr 2025 to Sep 2026: 46 sales, 3 mortgages. The median registered sale since Apr 2025 works out to about ₹10,600 per sq ft, at a median of ₹89 L a deal; 0% of sales were resales.
- What is the price per sq ft at Vrindavan Heights Phase III?
- The median registered sale since Apr 2025 works out to about ₹10,600 per sq ft, at a median of ₹89 L a deal; 0% of sales were resales.
- How many properties have been sold at Vrindavan Heights Phase III?
- 46 sales are registered at Vrindavan Heights Phase III.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Vrindavan Heights Phase III by Deedo, last updated with deals registered in Sep 2026.
Latest deal · Primary sale · Sep 2026
₹75 L–1 Cr