Skip to content
Extended 6 mo6 floorsRERA P52100029013

Main building, Soham Galaxy

Deedo IDDP-PUN-CKYS-SG

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

All of Soham Galaxy
Median saleNot on recordneeds 3 or more sales
Booked0%0 of 18 · MahaRERA
Completion1 Jun 202430 Dec 2023 · revised
Units & parking in Main building
TypeCarpet areaUnitsBooked
2BHK69.7 m² (750 sq.ft)60
2BHK71.6 m² (770 sq.ft)60
2BHK74 m² (797 sq.ft)60
As registered with MahaRERA
RERA registration
P52100029013 · registered 23 Apr 2021
Promised completion
30 Dec 2023
Revised completion
1 Jun 2024
Sanctioned habitable floors
6
Building
SOHAM GALAXY
Sanctioned floors (incl. basement, stilt, podium)
6
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
DP-PUN-CKYS-SG
Questions about Main building

When is Main building due for completion?

The MahaRERA registration promises 30 Dec 2023, revised to 1 Jun 2024.

How many floors does Main building have?

6 sanctioned habitable floors, as registered with MahaRERA.

Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology