Skip to content
Others · 1 building · 16 unitsRERA P52100047716

Gautam

Deedo IDDP-PUN-A1XM

MahaRERA shows it completed; no MahaRERA orders on record; 94% of its units are booked.

Gultekadi, Pune 411037 · by Shri Laxmi Narayan Properties Llp · 50% of its projects kept the RERA date

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales94% booked15 of 16 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 21 Nov 2022, completion promised 23 Dec 2023.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100047716
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210004771621 Nov 202223 Dec 202323 Dec 2023Shri Laxmi Narayan Properties LLPProject page
Documents50

1 document held by Deedo, 49 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardSLNP LLP_ PAN.pdf · uploaded 2 Nov 2022Source

Legal

  • Legal Title reportLegal Title Report- Gautam Apartment CHS.pdf · uploaded 2 Nov 2022Source
  • Declaration Form BFORM -B (Promoter).pdf · uploaded 2 Nov 2022Source

Migrated

  • 1 PAN CardSLNP LLP_ PAN.pdf · uploaded 2 Nov 2022Source
  • 1 Copy of the legal title reportLegal Title Report- Gautam Apartment CHS.pdf · uploaded 2 Nov 2022Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Letter -Dues_Scan.pdf · uploaded 2 Nov 2022Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Letter - Legal_Scan.pdf · uploaded 2 Nov 2022Source
Show all 50 documentsShow fewer documents

Migrated

  • 1 b Details of encumbrances concerned to LegalEncumbrance Letter -Dues_Scan.pdf · uploaded 2 Nov 2022Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Letter - Legal_Scan.pdf · uploaded 2 Nov 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 2 Nov 2022Source
  • 1 Declaration about Commencement CertificateCC Declaration -Format D_Scan.pdf · uploaded 2 Nov 2022Source
  • 1 Declaration in FORM BFORM -B (Promoter).pdf · uploaded 2 Nov 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200251027555_For_Asset_Based_Search_31_10_2022_19_31_36_261.pdf · uploaded 2 Nov 2022Source
  • 1 Proforma of Allotment letterNew Allotment Letter_Deviation 31102022.pdf · uploaded 2 Nov 2022Source
  • 1 Proforma of Agreement for saleAFS GAUTAM _31102022.pdf · uploaded 2 Nov 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A - Seperate Bank Account Details_Scan.pdf · uploaded 2 Nov 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report of Alloment 31102022.pdf · uploaded 3 Nov 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report of Model AFS 31102022.pdf · uploaded 3 Nov 2022Source
  • 1 Copy of Layout Approval (in case of layout)plan gautamn.pdf · uploaded 5 Nov 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentplan gautamn.pdf · uploaded 5 Nov 2022Source
  • 2 Building Plan Approval / NA Order for plotted development1 Building Plan Approval _ NA Order for plotted development (6).pdf · uploaded 5 Nov 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Certificate 376 SCAN_compressed.pdf · uploaded 5 Nov 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Gautam_ Date 30-06-2023_compressed.pdf · uploaded 3 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Gautam form 3_compressed (1).pdf · uploaded 3 Oct 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Gautam June-23.pdf · uploaded 22 Nov 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A- Gautam as on June 2023.pdf · uploaded 22 Nov 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Gautam as on Dec 2022.pdf · uploaded 2 Jan 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - Gautam as on June 2023.pdf · uploaded 2 Jan 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Gautam as on Sep 2023.pdf · uploaded 2 Jan 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Gautam as on Dec 2023.pdf · uploaded 2 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Gautam as on Dec 2022.pdf · uploaded 2 Jan 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Gautam as on June 2023.pdf · uploaded 2 Jan 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Gautam as on March 2023.pdf · uploaded 17 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gautam as on Dec 2022_compressed.pdf · uploaded 17 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gautam as on March 2023_compressed.pdf · uploaded 17 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 17 Jan 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gautam as on Sep 2023_compressed.pdf · uploaded 17 Jan 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Gautam as on Dec 2023_compressed.pdf · uploaded 17 Jan 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - Gautam as on June 2023.pdf · uploaded 8 Feb 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Gautam as on March 2023.pdf · uploaded 8 Feb 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Gautam as on June 2023.pdf · uploaded 8 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 - Gautam FY 22-23.pdf · uploaded 11 Mar 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFull OC - Gautam.pdf · uploaded 19 Mar 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 1 Apr 2024Source

Technical

  • Documentplan gautamn.pdf · uploaded 5 Nov 2022Source
  • Documentplan gautamn.pdf · uploaded 5 Nov 2022Source
  • Document1 Building Plan Approval _ NA Order for plotted development (6).pdf · uploaded 5 Nov 2022Source

Technical (Architect)

  • DocumentForm 1 - Gautam as on March 2023.pdf · uploaded 17 Jan 2024Source

Technical (Engineer)

  • DocumentFORM 2 - Gautam as on June 2023.pdf · uploaded 8 Feb 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel C.T.S. No.3277, Plot No. 33

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK, Office space16 units in all
Address
Survey No.585, C.T.S. No.3277, Plot No. 33, Bibwewadi, Bibwewadi, PunePIN 411037
Village
Gultekadi, Haveli taluka
Land area for this project
527 sq m (5,667 sq ft)
Permissible built-up area
1,684 sq m (18,127 sq ft)
Sanctioned built-up area
1,684 sq m (18,127 sq ft)
Designated bank account
119
Developed in phases
No

Survey, CTS, gat or plot numbers

C.T.S. No.3277Plot No. 33Survey No.585

Land as published on MahaRERA's project page

Survey No.585, C.T.S. No.3277, Plot No. 33

Boundaries

North
Plot No - 32
South
9 M Wide Road
East
Plot No - 34
West
6 M Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking16 units

15 of 16 units booked (94%), as the promoter reported to MahaRERA

2BHK · 2 units3BHK · 12 unitsOffice space · 2 units
TypeCarpet areaUnitsBooked
2BHK51.6 sq m · 555 sq ft22
3BHK71 sq m · 764 sq ft22
3BHK93.37 sq m · 1,005 sq ft33
3BHK93.46 sq m · 1,006 sq ft11
3BHK94.12 sq m · 1,013 sq ft32
3BHK111.99 sq m · 1,205 sq ft33
Office space22.49 sq m · 242 sq ft22

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectStudio 55—
Chartered accountantSTP & Associates—
EngineerMr Subash Joshi—
OtherRERA Easy—

Source: MahaRERA project page. Contact details are not shown.