Residential / Group Housing · 2 buildings · 24 unitsRERA P52100054765

Prime Space

Deedo IDDP-PUN-QHT6

MahaRERA shows it completed; no MahaRERA orders on record; 13% of its units are booked.

Dudulgaon, Pune 412105 · Promoter: Nath Estate

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales13% booked3 of 24 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 12 Feb 2024, completion promised 31 Aug 2026.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100054765
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005476512 Feb 202431 Aug 202631 Aug 2026Nath EstateProject page
Documents122

1 document held by Deedo, 121 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card - Firm.pdf · uploaded 3 Nov 2023Source
  • OthersDeclaration of Revised Estimation.pdf · uploaded 21 Nov 2025Source

Legal

  • Legal Title reportLegal Title Report 193.pdf · uploaded 10 Nov 2023Source
  • Declaration Form BForm B Affidavit cum Declaration.pdf · uploaded 10 Nov 2023Source
  • Other – LegalPOA.pdf · uploaded 30 Jan 2024Source
  • Other – LegalForm B Landowner.pdf · uploaded 7 Feb 2024Source
  • Other – LegalForm B Promoter.pdf · uploaded 7 Feb 2024Source
Show all 122 documentsShow fewer documents

Legal

  • Declaration Form B193 Satbara.pdf · uploaded 13 Jan 2026Source

Migrated

  • 1 PAN CardPAN Card - Firm.pdf · uploaded 3 Nov 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 1.pdf · uploaded 3 Nov 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 3 Nov 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentPlan 3.pdf · uploaded 3 Nov 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 3 Nov 2023Source
  • 1 Copy of the legal title reportLegal Title Report 193.pdf · uploaded 10 Nov 2023Source
  • 1 Copy of Layout Approval (in case of layout)Plan 1.pdf · uploaded 10 Nov 2023Source
  • 1 Declaration in FORM BForm B Affidavit cum Declaration.pdf · uploaded 10 Nov 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 10 Nov 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest -Combined.pdf · uploaded 10 Nov 2023Source
  • 1 Proforma of Allotment letterModel Form of Allotment Letter.pdf · uploaded 10 Nov 2023Source
  • 1 Deviation Report with respect to model copy of AgreementNo Deviation - Agreement for Sale.pdf · uploaded 10 Nov 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 11 Nov 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 -CA Certificate.pdf · uploaded 11 Nov 2023Source
  • 1 Deviation Report with respect to Allotment letterNo Deviation - Allotment Letter.pdf · uploaded 11 Nov 2023Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Letter (Finance).pdf · uploaded 30 Nov 2023Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Letter (Legal).pdf · uploaded 30 Nov 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Letter (Finance).pdf · uploaded 30 Nov 2023Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Letter (Legal).pdf · uploaded 30 Nov 2023Source
  • 1 Declaration about Commencement CertificateDeclaration about Commencement certificate.pdf · uploaded 30 Nov 2023Source
  • 1 CERSAI detailsNo Cresai Report.pdf · uploaded 30 Nov 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration -Seperate Bank Account.pdf · uploaded 2 Dec 2023Source
  • 1 Other – TechnicalMail -Screen shot.pdf · uploaded 11 Dec 2023Source
  • 1 Proforma of Agreement for saleFinal AFS.pdf · uploaded 30 Jan 2024Source
  • 1 Other – LegalPOA.pdf · uploaded 30 Jan 2024Source
  • 2 Other – LegalForm B Landowner.pdf · uploaded 7 Feb 2024Source
  • 3 Other – LegalForm B Promoter.pdf · uploaded 7 Feb 2024Source
  • 4 Building Plan Approval / NA Order for plotted developmentPlan -1.pdf · uploaded 13 Mar 2024Source
  • 5 Building Plan Approval / NA Order for plotted developmentPlan-2.pdf · uploaded 13 Mar 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentPlan-3.pdf · uploaded 13 Mar 2024Source
  • 7 Building Plan Approval / NA Order for plotted developmentPlan-4.pdf · uploaded 13 Mar 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate Dtaed 1130324.pdf · uploaded 13 Mar 2024Source
  • 2 Declaration about Commencement Certificatedeclaration for CC Format D.pdf · uploaded 15 Mar 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY 23-24 Q4 Prime Space.pdf · uploaded 12 Jun 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 23-24 Q4 Prime Space.pdf · uploaded 12 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A FY 23-24 Prime Space.pdf · uploaded 12 Jun 2024Source
  • 1 Disclosure of sold/ booked inventoryPramoter Discloser Prime Space FY 23-24 Q4.pdf · uploaded 12 Jun 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 23-24 Q4 Prime Space.pdf · uploaded 12 Jun 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY 2024-25 Q1.pdf · uploaded 9 Aug 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 7 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 1.pdf · uploaded 7 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 7 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 3.pdf · uploaded 7 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 4.pdf · uploaded 7 Oct 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 7 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 1.pdf · uploaded 7 Oct 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 7 Oct 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentPlan 3.pdf · uploaded 7 Oct 2024Source
  • 4 Building Plan Approval / NA Order for plotted developmentPlan 4.pdf · uploaded 7 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q2 FY 24-25.pdf · uploaded 24 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY 2024-25 Q1.pdf · uploaded 24 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 24-25 Q1 - Prime Space.pdf · uploaded 24 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 24-25 Q2.pdf · uploaded 24 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Form 2 Nath Estate.pdf · uploaded 24 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryPramotar Discloser Q I.pdf · uploaded 24 Jan 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form I FY 2024-25 QIII.pdf · uploaded 22 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2024-25 Q3.pdf · uploaded 22 Feb 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Form 2 Nath FY 2024-25 QIII.pdf · uploaded 22 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Form 2 Nath Estate FY 2024-25 QII.pdf · uploaded 22 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Form 2 Nath Estate FY 2024-25 QI.pdf · uploaded 22 Feb 2025Source
  • 2 Disclosure of sold/ booked inventoryPramoter Disclosure FY 2024-25 Q II.pdf · uploaded 22 Feb 2025Source
  • 3 Disclosure of sold/ booked inventoryPramotar Disclosure FY 2024-25 QIII.pdf · uploaded 22 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.pdf · uploaded 2 Apr 2025Source
  • 1 Declaration about Commencement CertificateDeclaration about Commencement Certificate.pdf · uploaded 3 Apr 2025Source
  • Withdrawal Update Form 1Form 1 QI 2025-2026 Sign.pdf · uploaded 19 Aug 2025Source
  • Withdrawal Update Form 2Form 2 Q1 2025-2026 Sign copy Final.pdf · uploaded 19 Aug 2025Source
  • Withdrawal Update Form 3Form 3 Sign Copy.pdf · uploaded 19 Aug 2025Source
  • Withdrawal Update Form 1FORM 1 FY 25-26.pdf · uploaded 6 Sep 2025Source
  • Withdrawal Update Form 2Form 2 Q1 2025-2026 Sign copy Final.pdf · uploaded 6 Sep 2025Source
  • Withdrawal Update Form 3Form 3 FY 2025-26 Q1.pdf · uploaded 6 Sep 2025Source
  • Withdrawal Update Form 1Form 1 FY 2025-26 for Q2.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 2Form 2 FY 2025-26 for Q2.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 3Form 3 FY 2025-2026 for Q2.pdf · uploaded 8 Nov 2025Source
  • Form 5 (FY 2024-2025)Form 5 for FY 2024-2025.pdf · uploaded 15 Dec 2025Source
  • Form 2A (FY 2024-2025)Form 2A- Nath Estate FY 2024-2025.pdf · uploaded 25 Dec 2025Source
  • Withdrawal Update Form 1Form 1 for FY 2025-26 Q3.pdf · uploaded 13 Jan 2026Source
  • Withdrawal Update Form 1Form 1 for FY 2025-26 Q3.pdf · uploaded 13 Jan 2026Source
  • Withdrawal Update Form 2Form 2 for FY 2025-26 Q3.pdf · uploaded 13 Jan 2026Source
  • Withdrawal Update Form 2Form 2 for FY 2025-26 Q3.pdf · uploaded 13 Jan 2026Source
  • Withdrawal Update Form 3Form 3 for FY 2025-26 Q3.pdf · uploaded 13 Jan 2026Source
  • Withdrawal Update Form 3Form 3 for FY 2025-26 Q3.pdf · uploaded 13 Jan 2026Source
  • Form 2A (FY 2025-2026)Form 2A for FY 2025-2026 final.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 1Form 1 for FY 2025-26 Q4 final.pdf · uploaded 13 May 2026Source
  • Withdrawal Update Form 2Form 2 for FY 2025-2026 Q4 final.pdf · uploaded 13 May 2026Source
  • Withdrawal Update Form 3Form 3 FY 2025-26 Q4 Final.pdf · uploaded 13 May 2026Source
  • Occupational CertificateCompletion Certificate.pdf · uploaded 1 Jun 2026Source
  • Occupational CertificatePCMC Occupany Certificate email.pdf · uploaded 5 Jun 2026Source

Technical

  • DocumentPlan 1.pdf · uploaded 3 Nov 2023Source
  • DocumentPlan 2.pdf · uploaded 3 Nov 2023Source
  • DocumentPlan 3.pdf · uploaded 3 Nov 2023Source
  • DocumentPlan 1.pdf · uploaded 10 Nov 2023Source
  • Other – TechnicalMail -Screen shot.pdf · uploaded 11 Dec 2023Source
  • DocumentPlan -1.pdf · uploaded 13 Mar 2024Source
  • DocumentPlan-2.pdf · uploaded 13 Mar 2024Source
  • DocumentPlan-3.pdf · uploaded 13 Mar 2024Source
  • DocumentPlan-4.pdf · uploaded 13 Mar 2024Source
  • DocumentPlan 1.pdf · uploaded 7 Oct 2024Source
  • DocumentPlan 2.pdf · uploaded 7 Oct 2024Source
  • DocumentPlan 3.pdf · uploaded 7 Oct 2024Source
  • DocumentPlan 4.pdf · uploaded 7 Oct 2024Source
  • DocumentPlan 1.pdf · uploaded 7 Oct 2024Source
  • DocumentPlan 2.pdf · uploaded 7 Oct 2024Source
  • DocumentPlan 3.pdf · uploaded 7 Oct 2024Source
  • DocumentPlan 4.pdf · uploaded 7 Oct 2024Source

Technical (Architect)

  • DocumentForm 1 FY 2024-25 Q1.pdf · uploaded 24 Jan 2025Source
  • DocumentForm 1 Q2 FY 24-25.pdf · uploaded 24 Jan 2025Source
  • DocumentArchitect Certificate Form I FY 2024-25 QIII.pdf · uploaded 22 Feb 2025Source
  • DocumentForm 1 for FY 2025-26 Q4 final.pdf · uploaded 13 May 2026Source

Technical (Engineer)

  • DocumentEngineer Certificate - Form 2 Nath Estate.pdf · uploaded 24 Jan 2025Source
  • DocumentEngineer Certificate - Form 2 Nath Estate FY 2024-25 QI.pdf · uploaded 22 Feb 2025Source
  • DocumentEngineer Certificate - Form 2 Nath Estate FY 2024-25 QII.pdf · uploaded 22 Feb 2025Source
  • DocumentEngineer Certificate - Form 2 Nath FY 2024-25 QIII.pdf · uploaded 22 Feb 2025Source
  • DocumentForm 2 for FY 2025-2026 Q4 final.pdf · uploaded 13 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Gat No. 193(P)

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK24 units in all
Address
Gat No. 193(P), Moshi - Alandi Road, DudulgaonPIN 412105
Village
Dudulgaon, Haveli taluka
Land area for this project
1,616 sq m (17,393 sq ft)
Permissible built-up area
4,835 sq m (52,044 sq ft)
Sanctioned built-up area
4,835 sq m (52,039 sq ft)
Designated bank account
171
Developed in phases
Yes

Survey, CTS, gat or plot numbers

Gat No. 193(P)

Land as published on MahaRERA's project page

Gat No. 193(P)

Boundaries

North
Gat No 193
South
18 mtr DP Road
East
Gat No 192
West
Gat No 194

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking24 units

3 of 24 units booked (13%), as the promoter reported to MahaRERA

2BHK · 12 units3BHK · 12 units
TypeCarpet areaUnitsBooked
2BHK58.16 sq m · 626 sq ft11
2BHK58.23 sq m · 627 sq ft111
3BHK75.93 sq m · 817 sq ft121

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Chartered accountantRatikant Ranganath Pingale—
Chartered accountantSnehal G Patil—
Chartered accountantV S A P & Company—
EngineerKiran Shivaji Patil—
EngineerStrudcom Consultants Pvt Ltd—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology