Keystone Bliss 1

Deedo IDDP-PUN-GT53

Completion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 16% of its units are booked.

Dhayari (Part), Pune 411041 · by Rucha Associates

DeliveryExtended 4 moPromised Dec 2027 · now due Apr 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales16% booked3 of 19 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2028

  • This projectRegistered 22 Apr 2024, completion promised 31 Dec 2027, revised to 30 Apr 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100055815
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005581522 Apr 202431 Dec 202730 Apr 2028Rucha AssociatesProject page
Documents127

2 documents held by Deedo, 125 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN CARD -RUCHA ASSOCIATES.pdf · uploaded 25 Mar 2024Source
  • Other – Financeland owner declaration keystone bliss 1_removed.pdf · uploaded 29 Mar 2024Source

Legal

  • Declaration Form BFORM B promoter declaration (1).pdf · uploaded 23 Mar 2024Source
  • Legal Title reportlegal title certficate kestone bliss 1.pdf · uploaded 28 Mar 2024Source
  • Other – LegalAgreement_Rucha Associates_Sumeru Buildcon Pvt Ltd_Document No 18224-2022_compressed_compressed.pdf · uploaded 4 Apr 2024Source
  • Other – LegalSALE DEED-128-2-4_compressed (1).pdf · uploaded 4 Apr 2024Source
Show all 127 documentsShow fewer documents

Legal

  • Other – LegalSALE DEED 132-1-3-2-2-_11zon.pdf · uploaded 4 Apr 2024Source
  • Other – LegalRAYKAR -RUCHA.pdf · uploaded 5 Apr 2024Source
  • Other – LegalRAYKAR-RUCHA-29-44.pdf · uploaded 5 Apr 2024Source
  • Other – LegalGAIKWAD-RUCHA.pdf · uploaded 5 Apr 2024Source

Migrated

  • 1 a Details of encumbrances concerned to FinanceENCUMBRACES CERTIFCATE.pdf · uploaded 23 Mar 2024Source
  • 1 b Details of encumbrances concerned to LegalENCUMBRACES CERTIFCATE.pdf · uploaded 23 Mar 2024Source
  • 1 Declaration about Commencement Certificate1 Declaration about Commencement Certificate (1) (1).pdf · uploaded 23 Mar 2024Source
  • 1 Declaration in FORM BFORM B promoter declaration (1).pdf · uploaded 23 Mar 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT CERTIFICATE.pdf · uploaded 23 Mar 2024Source
  • 1 CERSAI detailsCERSAI DECLARATION.pdf · uploaded 23 Mar 2024Source
  • 1 Disclosure of Interest in Other Real Estate Organizations1 Disclosure of Interest in Other Real Estate Organizations (2) (2).pdf · uploaded 23 Mar 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A 1 - Prashant Nilawar.pdf · uploaded 23 Mar 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A 1 - Seema Nilawar.pdf · uploaded 23 Mar 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank account delcaration (1).pdf · uploaded 23 Mar 2024Source
  • 1 PAN CardPAN CARD -RUCHA ASSOCIATES.pdf · uploaded 25 Mar 2024Source
  • 2 a Details of encumbrances concerned to FinanceLEGAL ENCUMBRACES CERTIFICATE.pdf · uploaded 25 Mar 2024Source
  • 2 b Details of encumbrances concerned to LegalLEGAL ENCUMBRACES CERTIFICATE.pdf · uploaded 25 Mar 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentcc-Sub plot 2- layout.pdf · uploaded 25 Mar 2024Source
  • 1 Other – Technicalrevised DECLARATION annex a (1).pdf · uploaded 25 Mar 2024Source
  • 1 Building Plan Approval / NA Order for plotted development1 Copy of Layout Approval (in case of layout) (35).pdf · uploaded 26 Mar 2024Source
  • 1 Copy of the legal title reportlegal title certficate kestone bliss 1.pdf · uploaded 28 Mar 2024Source
  • 1 Copy of Layout Approval (in case of layout)layout bliss 2 (1)_11zon.pdf · uploaded 28 Mar 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 Engineers Certificate.pdf · uploaded 28 Mar 2024Source
  • 1 Proforma of Allotment letterREVISED Allotment Letter.pdf · uploaded 28 Mar 2024Source
  • 1 Proforma of Agreement for saleAgreement To Sell (2).pdf · uploaded 28 Mar 2024Source
  • 1 Deviation Report with respect to Allotment letterdevaition Allotment Letter.pdf · uploaded 28 Mar 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeclaration (6).pdf · uploaded 28 Mar 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC Verification 131.pdf · uploaded 29 Mar 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)KEYSTONE BLISS 1 CA CERTICATE.pdf · uploaded 29 Mar 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 Other – Finance.pdf · uploaded 29 Mar 2024Source
  • 1 Other – Financeland owner declaration keystone bliss 1_removed.pdf · uploaded 29 Mar 2024Source
  • 1 Other – LegalSALE DEED 132-1-3-2-2-_11zon.pdf · uploaded 4 Apr 2024Source
  • 2 Other – LegalAgreement_Rucha Associates_Sumeru Buildcon Pvt Ltd_Document No 18224-2022_compressed_compressed.pdf · uploaded 4 Apr 2024Source
  • 3 Other – LegalSALE DEED-128-2-4_compressed (1).pdf · uploaded 4 Apr 2024Source
  • 4 Other – LegalRAYKAR -RUCHA.pdf · uploaded 5 Apr 2024Source
  • 5 Other – LegalRAYKAR-RUCHA-29-44.pdf · uploaded 5 Apr 2024Source
  • 6 Other – LegalGAIKWAD-RUCHA.pdf · uploaded 5 Apr 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)RE- ARCHITECT CERTFICATE BLISS 1.pdf · uploaded 31 Jul 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE BLISS 1.pdf · uploaded 31 Jul 2024Source
  • 1 Disclosure of sold/ booked inventorySOLD INVENTORY BLISS 1.pdf · uploaded 31 Jul 2024View
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE BLISS 1 .pdf · uploaded 31 Jul 2024Source
  • 1 Proforma of Agreement for saleAGR-bliss 1 (deviation marked).pdf · uploaded 7 Oct 2024Source
  • 1 Proforma of Agreement for saleAGR-bliss 1 (deviation marked).pdf · uploaded 7 Oct 2024Source
  • 1 Proforma of Agreement for saleAGR-bliss 1 (deviation marked).pdf · uploaded 7 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE BLISS 1 SEP DONE.pdf · uploaded 17 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINER CERTIFCATE KEYSTONE BLISS 1 sep done.pdf · uploaded 17 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE KEYSTONE BLISS 1 sep 24 done.pdf · uploaded 17 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryUNSOLD INVENTORY KEYSTONE BLISS 1 sep done.pdf · uploaded 17 Oct 2024View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE BLISS 1 SEP DONE.pdf · uploaded 17 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINER CERTIFCATE KEYSTONE BLISS 1 sep done.pdf · uploaded 17 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE KEYSTONE BLISS 1 sep 24 done.pdf · uploaded 17 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryUNSOLD INVENTORY KEYSTONE BLISS 1 sep done.pdf · uploaded 17 Oct 2024View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE BLISS 1 SEP DONE.pdf · uploaded 17 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE KEYSTONE BLISS 1 sep 24 done.pdf · uploaded 17 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINER CERTIFCATE KEYSTONE BLISS 1 sep done.pdf · uploaded 17 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryUNSOLD INVENTORY KEYSTONE BLISS 1 sep done.pdf · uploaded 17 Oct 2024Source
  • 1 Proforma of Agreement for saleAGREEMENT KEYSTONE BLISS 1_rotated_compressed.pdf · uploaded 23 Dec 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT KEYSTONE BLISS 1.pdf · uploaded 23 Dec 2024Source
  • 1 Proforma of Agreement for saleAGREEMENT KEYSTONE BLISS 1_rotated_compressed.pdf · uploaded 23 Dec 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT KEYSTONE BLISS 1.pdf · uploaded 23 Dec 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT KEYSTONE BLISS 1.pdf · uploaded 23 Dec 2024Source
  • 2 Proforma of Agreement for saleAGREEMENT KEYSTONE BLISS 1_rotated_compressed.pdf · uploaded 23 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Bliss 1.pdf · uploaded 18 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 bliss1.pdf · uploaded 18 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE BLISS 1.pdf · uploaded 18 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Bliss 1.pdf · uploaded 18 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 bliss1.pdf · uploaded 18 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE BLISS 1.pdf · uploaded 18 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Bliss 1.pdf · uploaded 18 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE BLISS 1.pdf · uploaded 18 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 bliss1.pdf · uploaded 18 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryUNSOLD INVENTORY KEYSTONE BLISS 1.pdf · uploaded 20 Jan 2025View
  • 1 Disclosure of sold/ booked inventoryUNSOLD INVENTORY KEYSTONE BLISS 1.pdf · uploaded 20 Jan 2025View
  • 1 Disclosure of sold/ booked inventoryUNSOLD INVENTORY KEYSTONE BLISS 1.pdf · uploaded 20 Jan 2025View
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B-Keystone Bliss 1.pdf · uploaded 21 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 bliss 1.pdf · uploaded 26 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31 MARCH 2025.pdf · uploaded 19 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q4 KEYSTONE - BLISS 1 SIGNED_compressed.pdf · uploaded 19 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ER -keystone Bliss -1.pdf · uploaded 19 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryUNSOLD INVENTORY KEYSTONE BLISS 1 (2).pdf · uploaded 19 Apr 2025View
  • Withdrawal Update Form 1Architectsu0027s Certificate BLISS 1.pdf · uploaded 20 Jul 2025Source
  • Withdrawal Update Form 2Engineers Certificate BLISS 1.pdf · uploaded 20 Jul 2025Source
  • Withdrawal Update Form 3CA CERTIFICATE BLIIS 1.pdf · uploaded 20 Jul 2025Source
  • Withdrawal Update Form 1Architectsu0027s Certificate BLISS 1.pdf · uploaded 8 Oct 2025Source
  • Withdrawal Update Form 2Engineers Certificate BLISS 1.pdf · uploaded 8 Oct 2025Source
  • Withdrawal Update Form 3CA CERTIFICATE BLIIS 1.pdf · uploaded 8 Oct 2025Source
  • Withdrawal Update Form 1keystone Bliss 1 Form 1.pdf · uploaded 10 Nov 2025Source
  • Withdrawal Update Form 2Keystone Bliss 1- Form2(15-10-2025)_compressed.pdf · uploaded 10 Nov 2025Source
  • Withdrawal Update Form 3FORM 3 SEP 2025.pdf · uploaded 10 Nov 2025Source
  • Withdrawal Update Form 1Form 1 Bliss 1 Dec 25.pdf · uploaded 19 Jan 2026Source
  • Withdrawal Update Form 2Form 2 Keystone Bliss 1 31-12-2025.pdf · uploaded 19 Jan 2026Source
  • Withdrawal Update Form 3FORM 3 BLISS -1 31-12-2025.pdf · uploaded 19 Jan 2026Source
  • Form 5 (FY 2024-2025)Form 5 Bliss 1 2024-2025.pdf · uploaded 30 Jan 2026Source
  • Form 2A (FY 2024-2025)Keystone Bliss 1-form 2A(15-10-2025)_compressed.pdf · uploaded 25 Feb 2026Source
  • Withdrawal Update Form 1Form 1 keystone bliss 1.pdf · uploaded 18 Apr 2026Source
  • Withdrawal Update Form 2Form 2 keystone bliss.pdf · uploaded 18 Apr 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 18 Apr 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2keystone Bliss 1(4).pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3form 3 Final.pdf · uploaded 20 Jul 2026Source

Technical

  • Other – Technicalrevised DECLARATION annex a (1).pdf · uploaded 25 Mar 2024Source
  • Document1 Copy of Layout Approval (in case of layout) (35).pdf · uploaded 26 Mar 2024Source
  • Documentlayout bliss 2 (1)_11zon.pdf · uploaded 28 Mar 2024Source

Technical (Architect)

  • DocumentARCHITECT CERTIFICATE BLISS 1 SEP DONE.pdf · uploaded 17 Oct 2024Source
  • DocumentARCHITECT CERTIFICATE BLISS 1 SEP DONE.pdf · uploaded 17 Oct 2024Source
  • DocumentARCHITECT CERTIFICATE BLISS 1 SEP DONE.pdf · uploaded 17 Oct 2024Source
  • DocumentForm 1 Bliss 1.pdf · uploaded 18 Jan 2025Source
  • DocumentForm 1 Bliss 1.pdf · uploaded 18 Jan 2025Source
  • DocumentForm 1 Bliss 1.pdf · uploaded 18 Jan 2025Source
  • DocumentFORM 1 31 MARCH 2025.pdf · uploaded 19 Apr 2025Source
  • DocumentFORM 1.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • DocumentENGINER CERTIFCATE KEYSTONE BLISS 1 sep done.pdf · uploaded 17 Oct 2024Source
  • DocumentENGINER CERTIFCATE KEYSTONE BLISS 1 sep done.pdf · uploaded 17 Oct 2024Source
  • DocumentENGINER CERTIFCATE KEYSTONE BLISS 1 sep done.pdf · uploaded 17 Oct 2024Source
  • DocumentForm 2 bliss1.pdf · uploaded 18 Jan 2025Source
  • DocumentForm 2 bliss1.pdf · uploaded 18 Jan 2025Source
  • DocumentForm 2 bliss1.pdf · uploaded 18 Jan 2025Source
  • DocumentER -keystone Bliss -1.pdf · uploaded 19 Apr 2025Source
  • Documentkeystone Bliss 1(4).pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Certificate Signed
Address
S. No. 133/1/4/2, 132/1/2, 132/1/4/2, 132/1/3/2/1, 132/1/3/2/2, 132/1/1b, 128/2/4, 128/2/5 Sub Plot No 2, DhayariPIN 411041
Village
Dhayari (Part), Haveli taluka
Land area for this project
5,982 sq m (64,386 sq ft)
Permissible built-up area
0 sq m (0 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
171
Developed in phases
No

Land as published on MahaRERA's project page

S. NO. 133/1/4/2, 132/1/2, 132/1/4/2, 132/1/3/2/1, 132/1/3/2/2, 132/1/1B, 128/2/4, 128/2/5 SUB PLOT NO 2

Boundaries

North
By Adj S No 133
South
By 18 Mtr Wide Dp Road
East
By Adj Plot No 1
West
By Adj Plot No 3

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectJaideep Sunil Deshpande—
Chartered accountantChirag Shah—
Chartered accountantYash Paltewar—
EngineerSavan Padmawar—

Source: MahaRERA project page. Contact details are not shown.