Deedo IDDP-PUN-RJH5Its promised completion date, May 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 72% of its units are booked.
Devale, Pune 410502 · by Devki Housing Pvt Ltd · 50% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Its promised completion date, May 2023, has passed and MahaRERA does not show it completed
- This projectRegistered 20 Sep 2021, completion promised 31 May 2023, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
4 buildings
Open a building to see every flat, floor by floor.
- A Wing6 floors · 12 units83% booked
- Building (P52100030864)Size not on record69% booked
- B Wing6 floors · 12 units50% booked
- C Wing5 floors · 8 units88% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100030864
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100030864 | 20 Sep 2021 | 31 May 2023 | 31 May 2023 | Devki Housing Pvt Ltd | Project page |
Documents41
2 documents held by Deedo, 39 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN CardPAN NO - DHPL.pdf · uploaded 24 Jun 2021Source
Legal
Migrated
- 1 PAN CardPAN NO - DHPL.pdf · uploaded 24 Jun 2021Source
Show all 41 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportLegal title report.pdf · uploaded 24 Jun 2021Source
- 1 Details of encumbrancesEncumbrance Certificate - Aahana.pdf · uploaded 24 Jun 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentAAHANA COMMENCEMENT.pdf · uploaded 24 Jun 2021Source
- 1 Declaration about Commencement CertificateDeclaration for commencement.pdf · uploaded 24 Jun 2021Source
- 1 Declaration in FORM BForm B - Aahana.pdf · uploaded 24 Jun 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate (Form 3).pdf · uploaded 24 Jun 2021Source
- 1 Proforma of Allotment letterAgreement for sale - Aahana.pdf · uploaded 24 Jun 2021Source
- 1 OtherResolution - DHPL.pdf · uploaded 24 Jun 2021Source
- 2 OtherSale deed - NFPV to DHPL.pdf · uploaded 24 Jun 2021Source
- 1 Copy of Layout Approval (in case of layout)SHEET 01.pdf · uploaded 15 Sep 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentSHEET 01.pdf · uploaded 15 Sep 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentSHEET 02.pdf · uploaded 15 Sep 2021Source
- 3 Building Plan Approval / NA Order for plotted developmentSHEET 03.pdf · uploaded 15 Sep 2021Source
- 2 Details of encumbrancesaahana - encumbrance certificate.pdf · uploaded 12 Sep 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 01 March 2024.pdf · uploaded 17 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A FY 2021-22.pdf · uploaded 17 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A FY 2022-23.pdf · uploaded 17 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A FY 2023-24.pdf · uploaded 17 Jun 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 - Aahana( 2021-22).pdf · uploaded 17 Jun 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 - Aahana (22-23).pdf · uploaded 17 Jun 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - 2021-22.pdf · uploaded 22 Jun 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - 2022-23.pdf · uploaded 22 Jun 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 -31-03-2024.pdf · uploaded 22 Jun 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 2022.pdf · uploaded 22 Jun 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 2023.pdf · uploaded 22 Jun 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 2024.pdf · uploaded 22 Jun 2024Source
- 1 Disclosure of sold/ booked inventorySold Unsold Inventory.pdf · uploaded 25 Jun 2024View
Technical
Technical (Architect)
- DocumentForm 01 March 2024.pdf · uploaded 17 Jun 2024Source
Technical (Engineer)
- DocumentForm 2 -31-03-2024.pdf · uploaded 22 Jun 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 308 PART
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK32 units in all
- Address
- 308 Part, Sadapur Road, DevalePIN 410502
- Village
- Devale, Mawal taluka
- Location
- 18.74454, 73.46259
- Land area for this project
- 3,536 sq m (38,058 sq ft)
- Permissible built-up area
- 1,410 sq m (15,178 sq ft)
- Sanctioned built-up area
- 1,410 sq m (15,178 sq ft)
- Recreational open space
- 684 sq m (7,359 sq ft)
- Designated bank account
- 85
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
308 PART
Boundaries
- North
- By Adjacent Village Road
- South
- By Adjacent Gat No 259
- East
- By Amenity Space And Adj Village Road
- West
- By Remaining Part Of Gat No 308
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking32 units
23 of 32 units booked (72%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A Wing | 1BHK | 42 sq m · 452 sq ft | 9 | 7 |
| A Wing | 1BHK | 45 sq m · 484 sq ft | 3 | 3 |
| B Wing | 1BHK | 42 sq m · 452 sq ft | 9 | 5 |
| B Wing | 1BHK | 45 sq m · 484 sq ft | 3 | 1 |
| C Wing | 1BHK | 43 sq m · 463 sq ft | 8 | 7 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals7
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ar Milind Saraf | — |
| Chartered accountant | CA Rushabh Dugad | — |
| Chartered accountant | D G Kango | — |
| Chartered accountant | V A Dudhedia And Associates | — |
| Engineer | Er Makrand Shinganwade | — |
| Engineer | Rupali Phanse | — |
| Other | Mr Raju Patil | — |
Source: MahaRERA project page. Contact details are not shown.