Devki Housing Pvt Ltd
Deedo IDDD-HFGGOf 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 37 mo late.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| AnnapurnaP52100028613 | Kothrud | Certificate Signed | 30 Nov 2023 | 30 Nov 2023 | On date |
| AahanaP52100030864 | Devale | Certificate Signed | 31 May 2023 | 31 May 2023 | +42 mo* |
| Kanak KunjP52100032319 | Parvati | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| JanakiP52100046138 | Gultekadi | Certificate Signed | 30 Apr 2024 | 30 Apr 2024 | +31 mo* |
Devki Housing Pvt Ltd, in questions
Does Devki Housing Pvt Ltd finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 37 mo late. Across Maharashtra, 73% kept their date.
How many projects has Devki Housing Pvt Ltd registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.
Does Devki Housing Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.