Devki Housing Pvt Ltd

Deedo IDDD-HFGG

Of 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 37 mo late.

Projects44 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay37 mowhen late
First sales on record2registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
AnnapurnaP52100028613KothrudCertificate Signed30 Nov 202330 Nov 2023On date
AahanaP52100030864DevaleCertificate Signed31 May 202331 May 2023+42 mo*
Kanak KunjP52100032319ParvatiCertificate Signed30 Jun 202430 Jun 2024On date
JanakiP52100046138GultekadiCertificate Signed30 Apr 202430 Apr 2024+31 mo*

Devki Housing Pvt Ltd, in questions

Does Devki Housing Pvt Ltd finish projects on time?

Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 37 mo late. Across Maharashtra, 73% kept their date.

How many projects has Devki Housing Pvt Ltd registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.

Does Devki Housing Pvt Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology