Residential / Group Housing · 2 buildings · 159 unitsRERA P52100034801

Global Spaces

Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 45% of its units are booked.

Charholi, Pune 412105 · Promoter: Mdd Realty

Delivery10 mo past duePromised Dec 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales45% booked71 of 159 units · as the promoter reported to MahaRERA
Global Spaces project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 28 Apr 2022, completion promised 31 Dec 2025, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100034801
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210003480128 Apr 202231 Dec 202531 Dec 2025Mdd RealtyProject page
Documents101

1 document held by Deedo, 100 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card.pdf · uploaded 6 Apr 2022Source

Legal

  • Legal Title reportLegal Title Report.pdf · uploaded 14 Apr 2022Source
  • Declaration Form BForm B.pdf · uploaded 26 Apr 2022Source

Migrated

  • 1 PAN CardPAN Card.pdf · uploaded 6 Apr 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 6 Apr 2022Source
  • 1 Proforma of Allotment letterProforma Allotment Letter.pdf · uploaded 11 Apr 2022Source
  • 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 14 Apr 2022Source
Show all 101 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesDetails of Encrumbances.pdf · uploaded 14 Apr 2022Source
  • 1 Copy of Layout Approval (in case of layout)Copy of Layout Approval (in case of layout)_Approval.pdf · uploaded 17 Apr 2022Source
  • 2 Copy of Layout Approval (in case of layout)Copy of Layout Approval (in case of layout)_Layout.pdf · uploaded 17 Apr 2022Source
  • 1 Building Plan Approval / NA Order for plotted development1 Building Plan Approval_Building A.pdf · uploaded 17 Apr 2022Source
  • 2 Building Plan Approval / NA Order for plotted development2 Building Plan Approval _Building A.pdf · uploaded 17 Apr 2022Source
  • 3 Building Plan Approval / NA Order for plotted development3 Building Plan Approval_Building B.pdf · uploaded 17 Apr 2022Source
  • 4 Building Plan Approval / NA Order for plotted development4 NA Order.pdf · uploaded 17 Apr 2022Source
  • 1 Commencement Certificates / NA Order for plotted development1 Commencement Certificates.pdf · uploaded 17 Apr 2022Source
  • 2 Commencement Certificates / NA Order for plotted development4 NA Order.pdf · uploaded 17 Apr 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 17 Apr 2022Source
  • 1 CERSAI detailsCERSAI Undertaking.pdf · uploaded 18 Apr 2022Source
  • 2 Details of encumbrancesNon Encrumbance Certificate.pdf · uploaded 26 Apr 2022Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 26 Apr 2022Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 26 Apr 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 26 Apr 2022Source
  • 2 Proforma of Allotment letterProforma Agreement to Sale.pdf · uploaded 26 Apr 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)annexure A.pdf · uploaded 21 Feb 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate MDD Realty_A AND B Building-31-12-2022.pdf · uploaded 21 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)4th Quality Assurance Certificate MDD Realty A AND B Building _31-12-2022.pdf · uploaded 21 Feb 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 21 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5_Signed.pdf · uploaded 21 Feb 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Dec 2022.pdf · uploaded 18 Apr 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_31-03-2023.pdf · uploaded 26 Jun 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_30-09-2023.pdf · uploaded 24 Nov 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_30-12-2023.pdf · uploaded 8 Feb 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_10-08-2023.pdf · uploaded 8 Feb 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_30-09-2023.pdf · uploaded 8 Feb 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_30-06-2023.pdf · uploaded 8 Feb 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A_31-03-2022.pdf · uploaded 8 Feb 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A_30-06-2022_2nd Quality Assurance Certificate MDD Realty (A Building).pdf · uploaded 8 Feb 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A_31-12-2022.pdf · uploaded 8 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5_FY 2022-23_Signed.pdf · uploaded 13 Feb 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 13-04-2024_compressed (1).pdf · uploaded 20 May 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.pdf · uploaded 15 Oct 2024Source
  • 2 Copy of Layout Approval (in case of layout)fjj001 (3)_compressed.pdf · uploaded 22 Oct 2024Source
  • 1 Copy of Layout Approval (in case of layout)S041000113_2407041153000.pdf · uploaded 22 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar Certificate.pdf · uploaded 22 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_30-06-2024.pdf · uploaded 22 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_30-06-2024.pdf · uploaded 22 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_31-03-2024.pdf · uploaded 22 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 22 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentfjj002 (3)_compressed.pdf · uploaded 22 Oct 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentvhhh004 (2)_compressed.pdf · uploaded 22 Oct 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentvhhh006 (1)_compressed.pdf · uploaded 22 Oct 2024Source
  • 4 Building Plan Approval / NA Order for plotted developmentvhhh003 (1)_compressed.pdf · uploaded 22 Oct 2024Source
  • 3 Copy of Layout Approval (in case of layout)Layout Approval.pdf · uploaded 19 Nov 2024Source
  • 4 Copy of Layout Approval (in case of layout)Copy of Layout.pdf · uploaded 19 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 19 Nov 2024Source
  • 5 Building Plan Approval / NA Order for plotted developmentPlan Approval.pdf · uploaded 19 Nov 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval.pdf · uploaded 19 Nov 2024Source
  • 7 Building Plan Approval / NA Order for plotted developmentPlan Approval 3.pdf · uploaded 19 Nov 2024Source
  • 8 Building Plan Approval / NA Order for plotted development4 Plan Approval .pdf · uploaded 19 Nov 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)8 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 29 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate .pdf · uploaded 26 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate .pdf · uploaded 26 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate .pdf · uploaded 26 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Final.pdf · uploaded 7 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 25 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3__.pdf · uploaded 25 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 25 May 2025Source
  • Form 2A (FY 2025-2026)FORM 2A (12).pdf · uploaded 5 Aug 2026Source
  • Form 5 (FY 2025-2026)form 5 (3).pdf · uploaded 8 Aug 2026Source

Technical

  • DocumentCopy of Layout Approval (in case of layout)_Approval.pdf · uploaded 17 Apr 2022Source
  • DocumentCopy of Layout Approval (in case of layout)_Layout.pdf · uploaded 17 Apr 2022Source
  • Document1 Building Plan Approval_Building A.pdf · uploaded 17 Apr 2022Source
  • Document2 Building Plan Approval _Building A.pdf · uploaded 17 Apr 2022Source
  • Document3 Building Plan Approval_Building B.pdf · uploaded 17 Apr 2022Source
  • Document4 NA Order.pdf · uploaded 17 Apr 2022Source
  • DocumentS041000113_2407041153000.pdf · uploaded 22 Oct 2024Source
  • Documentfjj001 (3)_compressed.pdf · uploaded 22 Oct 2024Source
  • Documentfjj002 (3)_compressed.pdf · uploaded 22 Oct 2024Source
  • Documentvhhh004 (2)_compressed.pdf · uploaded 22 Oct 2024Source
  • Documentvhhh006 (1)_compressed.pdf · uploaded 22 Oct 2024Source
  • Documentvhhh003 (1)_compressed.pdf · uploaded 22 Oct 2024Source
  • DocumentLayout Approval.pdf · uploaded 19 Nov 2024Source
  • DocumentCopy of Layout.pdf · uploaded 19 Nov 2024Source
  • DocumentPlan Approval.pdf · uploaded 19 Nov 2024Source
  • DocumentBuilding Plan Approval.pdf · uploaded 19 Nov 2024Source
  • DocumentPlan Approval 3.pdf · uploaded 19 Nov 2024Source
  • Document4 Plan Approval .pdf · uploaded 19 Nov 2024Source

Technical (Architect)

  • DocumentForm 1_10-08-2023.pdf · uploaded 8 Feb 2024Source
  • DocumentAr Certificate.pdf · uploaded 22 Oct 2024Source
  • DocumentForm 1_30-06-2024.pdf · uploaded 22 Oct 2024Source
  • DocumentArchitect Certificate .pdf · uploaded 26 Feb 2025Source
  • DocumentArchitect Certificate .pdf · uploaded 26 Feb 2025Source
  • DocumentForm 1.pdf · uploaded 25 May 2025Source

Technical (Engineer)

  • DocumentForm 2_30-06-2023.pdf · uploaded 8 Feb 2024Source
  • DocumentForm 2.pdf · uploaded 22 Oct 2024Source
  • DocumentForm 2_31-03-2024.pdf · uploaded 22 Oct 2024Source
  • DocumentForm 2_30-06-2024.pdf · uploaded 22 Oct 2024Source
  • Document8 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 29 Nov 2024Source
  • DocumentEngineer Certificate .pdf · uploaded 26 Feb 2025Source
  • DocumentForm 2.pdf · uploaded 25 May 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsSR. NO. 495/3

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, 1RK, Driver room, Office space, Restaurant, Shop159 units in all
Address
Sr. No. 495/3, Gat No. 495/3, CharholiPIN 412105
Village
Charholi, Haveli taluka
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

SR. NO. 495/3

Boundaries

North
Survey No 499 Dp Road 18 Meters
South
Survey No 494
East
Survey No 495
West
Survey No 495-2

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking159 units

71 of 159 units booked (45%), as the promoter reported to MahaRERA

1BHK · 52 units2BHK · 101 units1RK · 2 unitsDriver room · 1 unitOffice space · 1 unitRestaurant · 1 unitShop · 1 unit
BuildingTypeCarpet areaUnitsBooked
Global Spaces A1BHK34.26 sq m · 369 sq ft5227
Global Spaces A2BHK43.32 sq m · 466 sq ft2613
Global Spaces A2BHK46.19 sq m · 497 sq ft135
Global Spaces A2BHK46.2 sq m · 497 sq ft135
Global Spaces A2BHK46.58 sq m · 501 sq ft136
Global Spaces A2BHK46.69 sq m · 503 sq ft134
Global Spaces A2BHK51.6 sq m · 555 sq ft2311
Global Spaces B1RK57.46 sq m · 618 sq ft10
Show all 13 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Global Spaces B1RK72.69 sq m · 782 sq ft10
Global Spaces BDriver room36.72 sq m · 395 sq ft10
Global Spaces BOffice space102.57 sq m · 1,104 sq ft10
Global Spaces BRestaurant397.34 sq m · 4,277 sq ft10
Global Spaces BShop25.16 sq m · 271 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMahendra Thakur & Associates—
Chartered accountantkhandelwal associates—
Chartered accountantParakh Shah & Associates—
EngineerKishorkumar Dasud—
EngineerRathi's Group—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology