Residential / Group Housing · 1 building · 12 unitsRERA P52100013014

Torna Apartment

Deedo IDDP-PUN-XTMY

Its promised completion date, Mar 2019, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 83% of its units are booked.

Boripardhi, Pune 412203 · by Shree Ganesh Devlopers

Delivery7 yrs 8 mo past duePromised Mar 2019 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales83% booked10 of 12 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Mar 2019, has passed and MahaRERA does not show it completed

  • This projectRegistered 12 Sep 2017, completion promised 31 Mar 2019, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100013014
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001301412 Sep 201731 Mar 201931 Mar 2019Shree Ganesh DevlopersProject page
Documents30

1 document held by Deedo, 29 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD PARTNERSHIPFIRM.pdf · uploaded 9 Sep 2017Source

Legal

  • OtherAFFIDAVIT FORM B.pdf · uploaded 31 Jul 2017Source
  • Declaration Form BAFFIDAVIT FORM B.pdf · uploaded 31 Jul 2017Source
  • OtherAADHAR PAN DINESH AND BHUSHAN NAGARKAR.pdf · uploaded 9 Sep 2017Source
  • OtherSBI LETTER.pdf · uploaded 9 Sep 2017Source
  • OtherLETTERS TO MAHARERE-ilovepdf-compressed(1).pdf · uploaded 9 Sep 2017Source
  • OtherPLINTH.pdf · uploaded 9 Sep 2017Source
Show all 30 documentsShow fewer documents

Legal

  • Legal Title reportTITLE_SEARCH_REPORT_LSR.pdf · uploaded 9 Sep 2017Source

Migrated

  • 1 Details of encumbrancesENCUMBURANCE CERTIFICATE.pdf · uploaded 31 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT AND MOJANI NAKASHA.pdf · uploaded 31 Jul 2017Source
  • 1 Building Plan Approval (IOD)SANCTION PLAN.pdf · uploaded 31 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE-ilovepdf-compressed.pdf · uploaded 31 Jul 2017Source
  • 1 Declaration in FORM BAFFIDAVIT FORM B.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of CA (Form 3)CALETTER-ilovepdf-compressed.pdf · uploaded 31 Jul 2017Source
  • 1 Proforma of Allotment letteralllllllllllllllldoc for upload-ilovepdf-compressed.pdf · uploaded 31 Jul 2017Source
  • 1 OtherAFFIDAVIT FORM B.pdf · uploaded 31 Jul 2017Source
  • 1 PAN CardPAN CARD PARTNERSHIPFIRM.pdf · uploaded 9 Sep 2017Source
  • 1 Copy of the legal title reportTITLE_SEARCH_REPORT_LSR.pdf · uploaded 9 Sep 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE SECOND-ilovepdf-compressed.pdf · uploaded 9 Sep 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE SECOND-ilovepdf-compressed.pdf · uploaded 9 Sep 2017Source
  • 1 Certificates of CA (Form 5)AFFIDAVIT FORM B.pdf · uploaded 9 Sep 2017Source
  • 2 OtherAADHAR PAN DINESH AND BHUSHAN NAGARKAR.pdf · uploaded 9 Sep 2017Source
  • 3 OtherSBI LETTER.pdf · uploaded 9 Sep 2017Source
  • 4 OtherLETTERS TO MAHARERE-ilovepdf-compressed(1).pdf · uploaded 9 Sep 2017Source
  • 5 OtherPLINTH.pdf · uploaded 9 Sep 2017Source

Technical

  • DocumentLAYOUT AND MOJANI NAKASHA.pdf · uploaded 31 Jul 2017Source
  • DocumentSANCTION PLAN.pdf · uploaded 31 Jul 2017Source

Technical (Architect)

  • DocumentARCHITECT CERTIFICATE SECOND-ilovepdf-compressed.pdf · uploaded 9 Sep 2017Source

Technical (Engineer)

  • DocumentENGINEER CERTIFICATE SECOND-ilovepdf-compressed.pdf · uploaded 9 Sep 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1 BHK12 units in all
Address
2PIN 412203
Village
Boripardhi, Daund taluka
Land area for this project
400 sq m (4,306 sq ft)
Permissible built-up area
539 sq m (5,802 sq ft)
Sanctioned built-up area
540 sq m (5,809 sq ft)
Designated bank account
35
Developed in phases
No

Survey, CTS, gat or plot numbers

2

Land as published on MahaRERA's project page

2

Boundaries

North
Lay Out Sanction 9 Meter Wide Road
South
Part Of Gat No Old 248 New Gat 205
East
Road
West
Remaining Land Out Of Plot No 2

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking12 units

10 of 12 units booked (83%), as the promoter reported to MahaRERA

1 BHK · 12 units
TypeCarpet areaUnitsBooked
1 BHK36.25 sq m · 390 sq ft64
1 BHK40.31 sq m · 434 sq ft66

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSameer B Kokre—
EngineerSameer B Kokre—
OtherAslam Shaikh—
OtherKalam Ansari—

Source: MahaRERA project page. Contact details are not shown.