Skip to content
Promised date passed13 floorsRERA P52100019341

Main building, The Riverside

Deedo IDDP-PUN-N78M-TR

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

All of The Riverside
Median saleNot on recordneeds 3 or more sales
Booked77%75 of 97 · MahaRERA
Completion30 Dec 2022as registered
Units & parking in Main building
TypeCarpet areaUnitsBooked
1BHK33 m² (356 sq.ft)104
1BHK34.5 m² (372 sq.ft)108
1BHK35.2 m² (379 sq.ft)105
1BHK36 m² (387 sq.ft)97
1BHK37.8 m² (407 sq.ft)3932
2BHK45.9 m² (494 sq.ft)1010
2BHK48 m² (517 sq.ft)99
As registered with MahaRERA
RERA registration
P52100019341 · registered 23 Jan 2019
Promised completion
30 Dec 2022
Revised completion
30 Dec 2022
Sanctioned habitable floors
13
Building
THE RIVERSIDE
Sanctioned floors (incl. basement, stilt, podium)
13
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
DP-PUN-N78M-TR
Questions about Main building

When is Main building due for completion?

The MahaRERA registration promises 30 Dec 2022.

How many floors does Main building have?

13 sanctioned habitable floors, as registered with MahaRERA.