Skip to content
Residential / Group Housing · 1 building · 19 unitsRERA P52100049375

Global Renest Phase 1

Deedo IDDP-PUN-WBBN

It is due for completion in Dec 2027, with no extension on record; no MahaRERA orders on record; 47% of its units are booked.

Bhugaon, Pune 412115 · by Mukund Yashwant Bharekar

DeliveryDue Dec 2027No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales47% booked9 of 19 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

It is due for completion in Dec 2027, with no extension on record

  • This projectRegistered 7 Feb 2023, completion promised 30 Dec 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100049375
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000493757 Feb 202330 Dec 202730 Dec 2027Mukund Yashwant BharekarProject page
Documents86

1 document held by Deedo, 85 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN ADHAR MUKUND BHAREKAR.pdf · uploaded 11 Jan 2023Source

Legal

  • Other – LegalLegal Title Report (Global developers).pdf · uploaded 12 Jan 2023Source
  • Legal Title reportLegal Title Report (Global developers).pdf · uploaded 12 Jan 2023Source
  • Declaration Form BGlobal Developers Form -B Promoter.pdf · uploaded 12 Jan 2023Source
  • Declaration Form BGlobal Developers Form B Land owner .pdf · uploaded 12 Jan 2023Source
  • Declaration Form BGlobal Renest Form B.pdf · uploaded 25 Jan 2025Source

Migrated

  • 1 PAN CardPAN ADHAR MUKUND BHAREKAR.pdf · uploaded 11 Jan 2023Source
Show all 86 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportLegal Title Report (Global developers).pdf · uploaded 12 Jan 2023Source
  • 1 a Details of encumbrances concerned to FinanceLEGAL No Encumbrances concerned to legal for global Developers.pdf · uploaded 12 Jan 2023Source
  • 1 b Details of encumbrances concerned to LegalLEGAL No Encumbrances concerned to legal for global Developers.pdf · uploaded 12 Jan 2023Source
  • 1 Copy of Layout Approval (in case of layout)SANCTIONED PLAN_compressed.pdf · uploaded 12 Jan 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentSANCTIONED PLAN_compressed.pdf · uploaded 12 Jan 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentNA ORDER - GD 10R2.pdf · uploaded 12 Jan 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE GD 10R_compressed.pdf · uploaded 12 Jan 2023Source
  • 1 Declaration about Commencement CertificateFormat D (Declaration about commencement certificate).pdf · uploaded 12 Jan 2023Source
  • 1 Declaration in FORM BGlobal Developers Form -B Promoter.pdf · uploaded 12 Jan 2023Source
  • 2 Declaration in FORM BGlobal Developers Form B Land owner .pdf · uploaded 12 Jan 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate GD 10R.pdf · uploaded 12 Jan 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Global Developers ( Form 2 Engineer certificate).pdf · uploaded 12 Jan 2023Source
  • 1 CERSAI detailsCersai undertaking (2).pdf · uploaded 12 Jan 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexture A (Disclosure of intrest in other real estate organization).pdf · uploaded 12 Jan 2023Source
  • 1 Proforma of Agreement for saleAGREEMENT TO SALE 10R GLOBAL DEVELOPERS.pdf · uploaded 12 Jan 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report - ALLOTMENT LETTER NEW.pdf · uploaded 12 Jan 2023Source
  • 1 Deviation Report with respect to model copy of AgreementGlobal Developers (Deviation report with respect to a model copy of the agreement of the global renest phase 1 )_compressed.pdf · uploaded 12 Jan 2023Source
  • 1 Other – LegalLegal Title Report (Global developers).pdf · uploaded 12 Jan 2023Source
  • 1 Disclosure of sold/ booked inventoryDeclaration about sold- Booked inventory ( Global developers) (1).pdf · uploaded 13 Jan 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Global Developers Form 3 (CA certificate).pdf · uploaded 13 Jan 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameGlobal Developers ( Format A- Declaration about separate bank account for real estate project) .pdf · uploaded 13 Jan 2023Source
  • 2 a Details of encumbrances concerned to FinanceFINANCE NON ENCUMBRANCE - GLOBAL DEVELOPERS NEW.pdf · uploaded 1 Feb 2023Source
  • 2 b Details of encumbrances concerned to LegalFINANCE NON ENCUMBRANCE - GLOBAL DEVELOPERS NEW.pdf · uploaded 1 Feb 2023Source
  • 1 Proforma of Allotment letterAllotment Letter - Global Developers NEW_compressed.pdf · uploaded 1 Feb 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch.pdf · uploaded 9 Oct 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Arch.pdf · uploaded 9 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA.pdf · uploaded 9 Oct 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch.pdf · uploaded 11 Jan 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Renest.pdf · uploaded 11 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng 1.pdf · uploaded 11 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Quality a.pdf · uploaded 11 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Quality a.pdf · uploaded 11 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA 1.pdf · uploaded 11 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5- Renest.pdf · uploaded 15 Mar 2024Source
  • 1 Declaration in FORM BGlobal Renest Form B.pdf · uploaded 25 Jan 2025Source
  • Form 1Arch Mar 25.pdf · uploaded 31 Dec 2025Source
  • Form 2Engg Mar 25.pdf · uploaded 31 Dec 2025Source
  • Form 3CA Mar 25.pdf · uploaded 31 Dec 2025Source
  • Disclosure of Sold and Booked InventorySold Mar 25.pdf · uploaded 31 Dec 2025Source
  • Form 1Arch Dec 24.pdf · uploaded 31 Dec 2025Source
  • Form 2Engg Dec 24.pdf · uploaded 31 Dec 2025Source
  • Form 3CA Dec 24.pdf · uploaded 31 Dec 2025Source
  • Disclosure of Sold and Booked InventorySold Dec 24.pdf · uploaded 31 Dec 2025Source
  • Form 1Arch Sept 24.pdf · uploaded 31 Dec 2025Source
  • Form 2Engg Sept 24.pdf · uploaded 31 Dec 2025Source
  • Form 3CA Sept 24.pdf · uploaded 31 Dec 2025Source
  • Disclosure of Sold and Booked InventorySold Sept 24.pdf · uploaded 31 Dec 2025Source
  • Form 1Arch cert.pdf · uploaded 31 Dec 2025Source
  • Form 2Global Renest-Engineer Certificate.pdf · uploaded 31 Dec 2025Source
  • Form 3CA Certificate.pdf · uploaded 31 Dec 2025Source
  • Disclosure of Sold and Booked InventorySold Sept 24.pdf · uploaded 31 Dec 2025Source
  • Form 1Arch.pdf · uploaded 31 Dec 2025Source
  • Form 2Eng 1.pdf · uploaded 31 Dec 2025Source
  • Form 3CA 1.pdf · uploaded 31 Dec 2025Source
  • Disclosure of Sold and Booked InventoryQuality a.pdf · uploaded 31 Dec 2025Source
  • Form 1Arch.pdf · uploaded 31 Dec 2025Source
  • Form 2Engg 23.pdf · uploaded 31 Dec 2025Source
  • Form 3CA.pdf · uploaded 31 Dec 2025Source
  • Disclosure of Sold and Booked InventorySold 23.pdf · uploaded 31 Dec 2025Source
  • Form 1Architect certificate.pdf · uploaded 31 Dec 2025Source
  • Form 2Engineer certificate).pdf · uploaded 31 Dec 2025Source
  • Form 3Global Developers Form 3.pdf · uploaded 31 Dec 2025Source
  • Disclosure of Sold and Booked InventorySold 23.pdf · uploaded 31 Dec 2025Source
  • Form 1Arch Mar 24.pdf · uploaded 31 Dec 2025Source
  • Form 2Eng Mar 24.pdf · uploaded 31 Dec 2025Source
  • Form 3CA Mar 24.pdf · uploaded 31 Dec 2025Source
  • Disclosure of Sold and Booked InventorySold Mar 24.pdf · uploaded 31 Dec 2025Source
  • Withdrawal Update Form 1Arch Jun 25.pdf · uploaded 31 Dec 2025Source
  • Withdrawal Update Form 1Arch Sept 25.pdf · uploaded 31 Dec 2025Source
  • Withdrawal Update Form 2Eng 1.pdf · uploaded 31 Dec 2025Source
  • Withdrawal Update Form 2Engg Jun 25.pdf · uploaded 31 Dec 2025Source
  • Withdrawal Update Form 3CA Jun 25.pdf · uploaded 31 Dec 2025Source
  • Withdrawal Update Form 3CA Sep 25.pdf · uploaded 31 Dec 2025Source

Technical

  • DocumentSANCTIONED PLAN_compressed.pdf · uploaded 12 Jan 2023Source
  • DocumentSANCTIONED PLAN_compressed.pdf · uploaded 12 Jan 2023Source
  • DocumentNA ORDER - GD 10R2.pdf · uploaded 12 Jan 2023Source

Technical (Architect)

  • DocumentArch Sept 25.pdf · uploaded 31 Dec 2025Source

Technical (Engineer)

  • DocumentEngg Jun 25.pdf · uploaded 31 Dec 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Survey Number 251/2/1 part

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop19 units in all
Address
Survey Number 251/2/1 part, BHUAGON PAUD ROAD, DAULAT PETROL PUMP SANAS NAGARPIN 412115
Village
Bhugaon, Mulshi taluka
Land area for this project
1,000 sq m (10,764 sq ft)
Permissible built-up area
1,067 sq m (11,482 sq ft)
Sanctioned built-up area
747 sq m (8,037 sq ft)
Designated bank account
82
Developed in phases
No

Survey, CTS, gat or plot numbers

Survey Number 251/2/1 part

Land as published on MahaRERA's project page

Survey Number 251/2/1 part

Boundaries

North
balance land 251-2-1
South
Balance Land 251-2-1
East
Internal Road in 251-2-1
West
Balance Land 251-2-1

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking19 units

9 of 19 units booked (47%), as the promoter reported to MahaRERA

1BHK · 12 units2BHK · 2 unitsShop · 5 units
TypeCarpet areaUnitsBooked
1BHK34.2 sq m · 368 sq ft125
2BHK48.85 sq m · 526 sq ft22
Shop5.49 sq m · 59 sq ft10
Shop6.29 sq m · 68 sq ft10
Shop13.03 sq m · 140 sq ft11
Shop16.32 sq m · 176 sq ft10
Shop19.22 sq m · 207 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectJay Aeram A Aeram—
Chartered accountantCA Dinesh Sudam Kudale Sudam Kudale—
EngineerAditya Keshav Kokhade Keshav Kokhade—
EngineerShrikant Shankar Matre—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology