RERA projects in Bhamboli
1 project under 1 MahaRERA registration, registered 2017–2017. 100% have a completion date extended beyond the one promised.
Locality
1RERA projects
1Registrations
1Completion still due0 past their completion date
48 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
5Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
Projects in Bhamboli
1 project registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Aapla Ghar Chakan Talegaon Phase IMaple Shelters Chakan 1 | P52100012098 | 1 Sep 2017 | 30 Dec 2023 | 31 Dec 2027 | Extended 48 mo | 0 |
Other localities in Khed
Most active promoters
By projects registered here, as named on MahaRERA.
- Maple Shelters Chakan 11 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology