Deedo IDDP-PUN-VQAPCompletion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 38% of its units are booked.
Bavadhan Bk, Pune 411021 · Property rates in Bavadhan Bk · by Mont Vert Needs
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 2 Feb 2022, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100032943
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100032943 | 2 Feb 2022 | 31 Dec 2028 | 30 Apr 2029 | Mont Vert Needs | Project page |
Documents157
1 document held by Deedo, 156 filings listed on MahaRERA's project page
Finance
- PAN CardMont Vert Needs PAN.pdf · uploaded 6 Dec 2021Source
Legal
- Legal Title reportFormat A Legal title uploaded RERA AXIS.pdf · uploaded 3 Jan 2022Source
- Legal Title reporttitle Axis Bavdhan Search Report 5-8-21.pdf · uploaded 3 Jan 2022Source
- Declaration Form BForm B declaration revised Axis.pdf · uploaded 3 Jan 2022Source
- OtherFInal Declaration Others MahaRERA.pdf · uploaded 5 Jan 2022Source
- OtherDeclaration of CC validity Maharera Axis.pdf · uploaded 5 Jan 2022Source
- OtherBAVDHAN LETTER.PDF · uploaded 11 Jan 2022Source
Show all 157 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardMont Vert Needs PAN.pdf · uploaded 6 Dec 2021Source
- 1 Details of encumbrancesLegal encumbrances.pdf · uploaded 18 Dec 2021Source
- 2 Details of encumbrancesFinancial loan.pdf · uploaded 18 Dec 2021Source
- 1 Proforma of Allotment letterAllotment letter- Mont Vert Axis.pdf · uploaded 18 Dec 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 compressed.pdf · uploaded 28 Dec 2021Source
- 2 Proforma of Allotment letterBavdhan unit agreement compressed version 1.pdf · uploaded 28 Dec 2021Source
- 1 Copy of the legal title reportFormat A Legal title uploaded RERA AXIS.pdf · uploaded 3 Jan 2022Source
- 2 Copy of the legal title reporttitle Axis Bavdhan Search Report 5-8-21.pdf · uploaded 3 Jan 2022Source
- 1 Declaration in FORM BForm B declaration revised Axis.pdf · uploaded 3 Jan 2022Source
- 1 Copy of Layout Approval (in case of layout)01 BP layout_compressed.pdf · uploaded 5 Jan 2022Source
- 1 Building Plan Approval / NA Order for plotted development05 shops_compressed.pdf · uploaded 5 Jan 2022Source
- 2 Building Plan Approval / NA Order for plotted development06 shops_compressed.pdf · uploaded 5 Jan 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 5 Jan 2022Source
- 1 OtherFInal Declaration Others MahaRERA.pdf · uploaded 5 Jan 2022Source
- 2 OtherDeclaration of CC validity Maharera Axis.pdf · uploaded 5 Jan 2022Source
- 1 Declaration about Commencement CertificateFormat D declaration Axis coomencement.pdf · uploaded 6 Jan 2022Source
- 1 CERSAI detailsCERSAI_Search_Report Axis Bavdhan.pdf · uploaded 10 Jan 2022Source
- 3 OtherBAVDHAN LETTER.PDF · uploaded 11 Jan 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 M V Axis.pdf · uploaded 13 Jan 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 M V Axis.pdf · uploaded 13 Jan 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A M V Axis.pdf · uploaded 13 Jan 2022Source
- 3 Copy of the legal title reportAXIS MAHARERA LEGAL TITLE REPORT -1.pdf · uploaded 1 Aug 2022Source
- 3 Building Plan Approval / NA Order for plotted developmentscan751_resize.pdf · uploaded 8 Aug 2022Source
- 4 Building Plan Approval / NA Order for plotted developmentscan752_resize.pdf · uploaded 8 Aug 2022Source
- 5 Building Plan Approval / NA Order for plotted developmentscan753_resize.pdf · uploaded 8 Aug 2022Source
- 6 Building Plan Approval / NA Order for plotted developmentscan754_resize.pdf · uploaded 8 Aug 2022Source
- 7 Building Plan Approval / NA Order for plotted developmentscan755_resize.pdf · uploaded 8 Aug 2022Source
- 8 Building Plan Approval / NA Order for plotted developmentscan756_resize.pdf · uploaded 8 Aug 2022Source
- 9 Building Plan Approval / NA Order for plotted developmentscan757_resize.pdf · uploaded 8 Aug 2022Source
- 10 Building Plan Approval / NA Order for plotted developmentscan758_resize.pdf · uploaded 8 Aug 2022Source
- 11 Building Plan Approval / NA Order for plotted developmentscan760_resize.pdf · uploaded 8 Aug 2022Source
- 12 Building Plan Approval / NA Order for plotted developmentscan761_resize.pdf · uploaded 8 Aug 2022Source
- 13 Building Plan Approval / NA Order for plotted developmentscan762_resize.pdf · uploaded 8 Aug 2022Source
- 14 Building Plan Approval / NA Order for plotted developmentscan763_resize.pdf · uploaded 8 Aug 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentCommencement certificate June 30 2022_compressed.pdf · uploaded 8 Aug 2022Source
- 2 Declaration about Commencement Certificatecommencement declaration Axis RERA AUg 2022.pdf · uploaded 8 Aug 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 M V Axis Mar 22.pdf · uploaded 16 Feb 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 M V Axis Mar 22.pdf · uploaded 16 Feb 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 March 2022 mont vert axis Both Sign.pdf · uploaded 17 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Mont Vert Needs certificate Form 5 2022.pdf · uploaded 17 Feb 2023Source
- 1 Proforma of Agreement for saleAxis agreement draft.pdf · uploaded 18 Feb 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 M V Axis Mar 23.pdf · uploaded 8 Apr 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A M V Axis Mar 23.pdf · uploaded 8 Apr 2023Source
- 1 Disclosure of sold/ booked inventorySold Unsold Inventory M V Axis Mar 23.pdf · uploaded 8 Apr 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 M V Axis Mar 23 Qtr.pdf · uploaded 18 Apr 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Mont Vert Axis Dec 2022 Both sign.pdf · uploaded 24 May 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Mont Vert Axis March 2023 Both sign.pdf · uploaded 24 May 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 AXIS 30-06-23.pdf · uploaded 9 Aug 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 AXIS 8-07-23.pdf · uploaded 9 Aug 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A AXIS 8-07-23.pdf · uploaded 9 Aug 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-Mont Vert Needs-Mont Vert Axis-both sign compressed.pdf · uploaded 9 Aug 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Annexure F MONT VERT NEEDS.pdf · uploaded 6 Sep 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Axis Form 1 Oct 2023.pdf · uploaded 6 Nov 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Mont Vert Axis Sep 2023.pdf · uploaded 10 Nov 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Axis Spt 2023_compressed.pdf · uploaded 10 Nov 2023Source
- 2 Disclosure of sold/ booked inventorySold Unsold Axis 30-9-23 AXIS.pdf · uploaded 6 Dec 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 Mont Vet Axis 31122023 both signed_compressed.pdf · uploaded 26 Feb 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Mont Vert Axis 31032024.pdf · uploaded 17 May 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 AXIS.pdf · uploaded 17 May 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 Mont Vert Axis 31-03-2024-both sign-compress.pdf · uploaded 17 May 2024Source
- 3 Disclosure of sold/ booked inventorySold Unsold 31032024 AXIS.pdf · uploaded 20 May 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 Most vert Axis 30-06-2024_compressed.pdf · uploaded 13 Nov 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Mont Vert Axis 30092024.pdf · uploaded 13 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Mont Vert Axis June 2024 ANNEXURE B.pdf · uploaded 13 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 AXIS000.pdf · uploaded 13 Nov 2024Source
- 2 Disclosure of sold/ booked inventorySold Unsold M V NEEDS AXIS 30-6-2024.pdf · uploaded 15 Nov 2024Source
- 3 Disclosure of sold/ booked inventorySold Unsold M V NEEDS AXIS 30-9-2024.pdf · uploaded 15 Nov 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Axis Dec 2023.pdf · uploaded 21 Nov 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Axis March 2024.pdf · uploaded 21 Nov 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Axis June 2024.pdf · uploaded 21 Nov 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Axis Sept 2024.pdf · uploaded 21 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A AXIS 2022-2023.pdf · uploaded 21 Nov 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Axis Form 2 Dec 2023.pdf · uploaded 22 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Axis RERA 2023-2024.pdf · uploaded 22 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 RERA Belcreek 2023-2024.pdf · uploaded 22 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Dec 2024 Axis.pdf · uploaded 4 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 Most Vert Axis Dec 2024.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventorySold Unsold Mont Vert Axis Dec 2024.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form_01_Mont_Vert_Axis_March_2025.pdf · uploaded 11 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 NEEDS AXIS MARCH 2025 (1).pdf · uploaded 11 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 AXIS COMMER MARCH 2025.pdf · uploaded 11 Apr 2025Source
- 1 Disclosure of sold/ booked inventorySold and Unsold Mont Vert Axis March 2025.pdf · uploaded 11 Apr 2025Source
- Form 1Form_01_Mont_Vert_Axis_March_2025.pdf · uploaded 5 Sep 2025Source
- Form 2FORM-2 AXIS COMMER MARCH 2025.pdf · uploaded 5 Sep 2025Source
- Form 3FORM 3 NEEDS AXIS MARCH 2025.pdf · uploaded 5 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold and Unsold 31032025.pdf · uploaded 5 Sep 2025Source
- Withdrawal Update Form 1FORM 1 April to June 2025 - 30062025.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 2FORM-2 AXIS COMM 30-6-2025.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 3Mont vert Axis Form 3 30-06-2025 sign_compressed.pdf · uploaded 10 Sep 2025Source
- Form 5 (FY 2024-2025)Form 5 Mont Vert Axis FY 2024-2025 sign.pdf · uploaded 15 Oct 2025Source
- Withdrawal Update Form 1FORM-1 AXIS Arch Sep 2025.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 1FORM-1 AXIS Arch Sep 2025.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 1FORM-1 AXIS Arch Sep 2025.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 2FORM 2 Mont Vert Axis Sep 2025.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 2FORM 2 Mont Vert Axis Sep 2025.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 2RERA FORM-2 Mont Vert Axis Sep 2025.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 3Form 3 Axis Sept 2025 sign.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 3Form 3 Axis Sept 2025 sign.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 3Mont vert Axis Form 3 30-09-2025 sign_compressed.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 1FORM 1 NEEDS Dec 205 sign.pdf · uploaded 25 Feb 2026Source
- Withdrawal Update Form 2FORM 2 NEEDS AXIS 31122025.pdf · uploaded 25 Feb 2026Source
- Withdrawal Update Form 3Mont vert Axis Form 3 31122025 sign_compressed.pdf · uploaded 25 Feb 2026Source
- Withdrawal Update Form 1FORM-1 AXIS 31032026.pdf · uploaded 4 May 2026Source
- Withdrawal Update Form 2FORM-2 AXIS 31032026.pdf · uploaded 4 May 2026Source
- Withdrawal Update Form 3Mont vert Axis Form 3 31032026 sign.pdf · uploaded 4 May 2026Source
- Form 2A (FY 2025-2026)Form 2A Maharera Mont Vert Axis 2025 2026.pdf · uploaded 13 May 2026Source
- Withdrawal Update Form 1FORM 1 AXIS June 2026.pdf · uploaded 21 Jul 2026Source
- Withdrawal Update Form 2FORM 2 AXIS June 2026.pdf · uploaded 21 Jul 2026Source
- Withdrawal Update Form 3Mont vert Axis Form 3 30 06 2026 sign.pdf · uploaded 21 Jul 2026Source
- Form 5 (FY 2021-2022)form 5 202122.pdf · uploaded 3 Aug 2026Source
- Form 5 (FY 2022-2023)Form 5 fy 22-23 (MONT VERT NEEDS) both sign.pdf · uploaded 3 Aug 2026Source
- Form 5 (FY 2023-2024)form 5 Mont Vert Axis 31-03-2024.pdf · uploaded 3 Aug 2026Source
- Form 2A (FY 2022-2023)Form 2 A 2022-23.pdf · uploaded 6 Aug 2026Source
- Form 2A (FY 2023-2024)Form 2 A 2023-24.pdf · uploaded 6 Aug 2026Source
- Form 2A (FY 2024-2025)Form 2A 2024-2025.pdf · uploaded 6 Aug 2026Source
- Withdrawal Update Form 1Axis Form 1 Q1 2026.pdf · uploaded 10 Aug 2026Source
- Withdrawal Update Form 2FORM 2 AXIS June 2026.pdf · uploaded 10 Aug 2026Source
- Withdrawal Update Form 3Mont vert Axis Form 3 30 06 2026 sign.pdf · uploaded 10 Aug 2026Source
- Form 5 (FY 2025-2026)Form 5 Mont Vert Axis FY 2025-2026 sign.pdf · uploaded 28 Sep 2026Source
Technical
- Document01 BP layout_compressed.pdf · uploaded 5 Jan 2022Source
- Document05 shops_compressed.pdf · uploaded 5 Jan 2022Source
- Document06 shops_compressed.pdf · uploaded 5 Jan 2022Source
- Documentscan751_resize.pdf · uploaded 8 Aug 2022Source
- Documentscan752_resize.pdf · uploaded 8 Aug 2022Source
- Documentscan753_resize.pdf · uploaded 8 Aug 2022Source
- Documentscan754_resize.pdf · uploaded 8 Aug 2022Source
- Documentscan755_resize.pdf · uploaded 8 Aug 2022Source
- Documentscan756_resize.pdf · uploaded 8 Aug 2022Source
- Documentscan757_resize.pdf · uploaded 8 Aug 2022Source
- Documentscan758_resize.pdf · uploaded 8 Aug 2022Source
- Documentscan760_resize.pdf · uploaded 8 Aug 2022Source
- Documentscan761_resize.pdf · uploaded 8 Aug 2022Source
- Documentscan762_resize.pdf · uploaded 8 Aug 2022Source
- Documentscan763_resize.pdf · uploaded 8 Aug 2022Source
Technical (Architect)
- DocumentForm 1 Axis Dec 2023.pdf · uploaded 21 Nov 2024Source
- DocumentForm 1 Axis March 2024.pdf · uploaded 21 Nov 2024Source
- DocumentForm 1 Axis June 2024.pdf · uploaded 21 Nov 2024Source
- DocumentForm 1 Axis Sept 2024.pdf · uploaded 21 Nov 2024Source
- DocumentForm 1 Dec 2024 Axis.pdf · uploaded 4 Jan 2025Source
- DocumentForm_01_Mont_Vert_Axis_March_2025.pdf · uploaded 11 Apr 2025Source
- DocumentAxis Form 1 Q1 2026.pdf · uploaded 10 Aug 2026Source
Technical (Engineer)
- DocumentFORM 2 Mont Vert Axis June 2024 ANNEXURE B.pdf · uploaded 13 Nov 2024Source
- DocumentFORM 2 AXIS000.pdf · uploaded 13 Nov 2024Source
- DocumentAxis Form 2 Dec 2023.pdf · uploaded 22 Nov 2024Source
- DocumentFORM-2 AXIS COMMER MARCH 2025.pdf · uploaded 11 Apr 2025Source
- DocumentFORM 2 AXIS June 2026.pdf · uploaded 21 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel SN 53 Hissa 13/B/2 3 5 6 7p
As registered with MahaRERA and published on its project page
- Project type
- Commercial
- Status on MahaRERA
- Certificate Signed
- Unit types
- Office space, Shop146 units in all
- Address
- SN 53 Hissa 13/B/2 3 5 6 7p, Sr. No. 53, Hissa No. 13/B/2, 3, 5, 6, 7(P), BavdhanPIN 411021
- Village
- Bavadhan BK, Mulshi taluka
- Location
- 18.50761, 73.77304
- Land area for this project
- 7,308 sq m (78,663 sq ft)
- Permissible built-up area
- 26,460 sq m (2,84,813 sq ft)
- Sanctioned built-up area
- 2,049 sq m (22,055 sq ft)
- Recreational open space
- 460 sq m (4,951 sq ft)
- Designated bank account
- 43
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SN 53 Hissa 13/B/2 3 5 6 7p
Boundaries
- North
- SN 53 p
- South
- 53 p and Paud Road
- East
- SN 67 p
- West
- Sn 52
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking146 units
56 of 146 units booked (38%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Office space | 32.39 sq m · 349 sq ft | 1 | 0 |
| Office space | 35.87 sq m · 386 sq ft | 1 | 1 |
| Office space | 39.18 sq m · 422 sq ft | 7 | 6 |
| Office space | 41.33 sq m · 445 sq ft | 8 | 0 |
| Office space | 43.77 sq m · 471 sq ft | 16 | 7 |
| Office space | 44.21 sq m · 476 sq ft | 8 | 1 |
| Office space | 47.75 sq m · 514 sq ft | 23 | 8 |
| Office space | 61 sq m · 657 sq ft | 24 | 10 |
Show all 25 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Office space | 64.18 sq m · 691 sq ft | 8 | 1 |
| Office space | 66.56 sq m · 716 sq ft | 24 | 9 |
| Office space | 68.19 sq m · 734 sq ft | 1 | 0 |
| Office space | 68.34 sq m · 736 sq ft | 1 | 1 |
| Office space | 69.19 sq m · 745 sq ft | 1 | 1 |
| Office space | 79.22 sq m · 853 sq ft | 8 | 2 |
| Office space | 92.96 sq m · 1,001 sq ft | 1 | 1 |
| Office space | 96.42 sq m · 1,038 sq ft | 1 | 0 |
| Office space | 104.18 sq m · 1,121 sq ft | 3 | 2 |
| Shop | 41.74 sq m · 449 sq ft | 1 | 0 |
| Shop | 46.17 sq m · 497 sq ft | 1 | 1 |
| Shop | 71.48 sq m · 769 sq ft | 1 | 0 |
| Shop | 78.19 sq m · 842 sq ft | 1 | 1 |
| Shop | 79.04 sq m · 851 sq ft | 1 | 1 |
| Shop | 102.45 sq m · 1,103 sq ft | 1 | 1 |
| Shop | 106.27 sq m · 1,144 sq ft | 1 | 0 |
| Shop | 114.93 sq m · 1,237 sq ft | 3 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Shrinivas V Kadkol | — |
| Architect | Vikas Achalkar AT consultants | — |
| Chartered accountant | Ganesh Gundecha | — |
| Engineer | G V Khasnis | — |
| Engineer | Rameshwar Bamodkar | — |
| Other | JW Consultant | — |
Source: MahaRERA project page. Contact details are not shown.