Univis
Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.
Baner, Pune 411045 · Property rates in Baner · Promoter: Elegant Ioc
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 25 Jan 2024, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
4 buildings
Open a building to see every flat, floor by floor.
- A1 floor · 1 unit0% booked
- B5 floors · 8 units0% booked
- C5 floors · 8 units0% booked
- D5 floors · 8 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100054531
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100054531 | 25 Jan 2024 | 31 Dec 2026 | 30 Apr 2027 | Elegant Ioc | Project page |
Documents72
1 document held by Deedo, 71 filings listed on MahaRERA's project page
Finance
- PAN CardElegant IOC Pan.pdf · uploaded 20 Oct 2023Source
Legal
Show all 72 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentUNIVIS Commencement Certificate.pdf · uploaded 20 Oct 2023Source
- 1 Declaration about Commencement Certificaterera commencement declaration.pdf · uploaded 20 Oct 2023Source
- 1 Declaration in FORM Bform b reupload.pdf · uploaded 20 Oct 2023Source
- 1 Proforma of Allotment letter1- Allottment letter by rera flat.pdf · uploaded 20 Oct 2023Source
- 1 Proforma of Agreement for saleDraft - Rera - Elegant IOC- UNIVIS-Baner - Flat -As per RERA Act -Agreement for Sale -SN 124-saykar.pdf · uploaded 20 Oct 2023Source
- 1 Copy of Layout Approval (in case of layout)NA.pdf · uploaded 27 Oct 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)rera certi_ A.pdf · uploaded 27 Oct 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)rera certi_ B.pdf · uploaded 27 Oct 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)rera certi_ C.pdf · uploaded 27 Oct 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)rera certi_ D.pdf · uploaded 27 Oct 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)a wing.pdf · uploaded 27 Oct 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)B Wing.pdf · uploaded 27 Oct 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)C Wing.pdf · uploaded 27 Oct 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)D Wing.pdf · uploaded 27 Oct 2023Source
- 1 a Details of encumbrances concerned to FinanceFINANCIAL ENC.pdf · uploaded 27 Nov 2023Source
- 2 a Details of encumbrances concerned to FinanceLEGAL.pdf · uploaded 27 Nov 2023Source
- 1 b Details of encumbrances concerned to LegalFINANCIAL ENC.pdf · uploaded 27 Nov 2023Source
- 2 b Details of encumbrances concerned to LegalLEGAL.pdf · uploaded 27 Nov 2023Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 27 Nov 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsMIC INTEREST.pdf · uploaded 27 Nov 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsAM INTEREST.pdf · uploaded 27 Nov 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsNP INTEREST.pdf · uploaded 27 Nov 2023Source
- 1 Deviation Report with respect to Allotment letterNO DEVIATION AL LETTER.pdf · uploaded 27 Nov 2023Source
- 1 Deviation Report with respect to model copy of AgreementNO DEVIATION AFS.pdf · uploaded 27 Nov 2023Source
- 1 Copy of the legal title reportTitle report with annexure.pdf · uploaded 28 Nov 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 accepted.pdf · uploaded 28 Nov 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameElegant .pdf · uploaded 28 Nov 2023Source
- 1 Other – LegalLandowner Form B.pdf · uploaded 11 Jan 2024Source
- Form 2A (FY 2023-2024)2A24.pdf · uploaded 20 Dec 2025Source
- Form 2A (FY 2024-2025)2A25.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 1Withdrawal Application Form1.pdf · uploaded 25 Dec 2025Source
- Withdrawal Update Form 2D Wing.pdf · uploaded 25 Dec 2025Source
- Withdrawal Update Form 3d8ac7aac-e4c3-4102-b763-f64decca9efd.pdf · uploaded 25 Dec 2025Source
- Form 1Form 1 2324 Q4.pdf · uploaded 30 Dec 2025Source
- Form 2FORM 2 2324 Q4.pdf · uploaded 30 Dec 2025Source
- Form 3Form 3 2324 Q4.pdf · uploaded 30 Dec 2025Source
- Disclosure of Sold and Booked Inventory2324 Q4.pdf · uploaded 30 Dec 2025Source
- Form 1Form 1 2425 Q1.pdf · uploaded 30 Dec 2025Source
- Form 2FORM 2 2425 Q1.pdf · uploaded 30 Dec 2025Source
- Form 3Form 3 2425 Q1.pdf · uploaded 30 Dec 2025Source
- Disclosure of Sold and Booked Inventory2425 Q1.pdf · uploaded 30 Dec 2025Source
- Form 1Form 1 2425 Q2.pdf · uploaded 30 Dec 2025Source
- Form 2Form 2 2425 Q2.pdf · uploaded 30 Dec 2025Source
- Form 3Form 3 2425 Q2.pdf · uploaded 30 Dec 2025Source
- Disclosure of Sold and Booked Inventory2425 Q2.pdf · uploaded 30 Dec 2025Source
- Form 1Form 1 2425 Q3.pdf · uploaded 30 Dec 2025Source
- Form 2FORM 2 2425 Q3.pdf · uploaded 30 Dec 2025Source
- Form 3Form 3 2425 Q3.pdf · uploaded 30 Dec 2025Source
- Disclosure of Sold and Booked Inventory2425 Q3.pdf · uploaded 30 Dec 2025Source
- Form 1Form 1 2425 Q4.pdf · uploaded 30 Dec 2025Source
- Form 2Form 2 2425 Q4.pdf · uploaded 30 Dec 2025Source
- Form 3Form 3 2425 Q4.pdf · uploaded 30 Dec 2025Source
- Disclosure of Sold and Booked Inventory2425 Q4.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 1Withdrawal Application Form1.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 2D Wing.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 3d8ac7aac-e4c3-4102-b763-f64decca9efd.pdf · uploaded 30 Dec 2025Source
- Withdrawal Update Form 1F1 - June 25.pdf · uploaded 13 Jan 2026Source
- Withdrawal Update Form 2F1 - June 25.pdf · uploaded 13 Jan 2026Source
- Withdrawal Update Form 3F3 - June 25.pdf · uploaded 13 Jan 2026Source
Technical
Technical (Architect)
- DocumentF1 - June 25.pdf · uploaded 13 Jan 2026Source
Technical (Engineer)
- DocumentF1 - June 25.pdf · uploaded 13 Jan 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals124/3/2/1 PLOT A, 124/3/2/5/OPEN SPACE
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK25 units in all
- Address
- 124/3/2/1 Plot A And 124/3/2/5/Open Space, Baner, BanerPIN 411045
- Village
- Baner, Haveli taluka
- Location
- 18.56439, 73.77860
- Designated bank account
- 212
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- S No 124 B Open Space
- South
- 30 Meter Baner Road
- East
- Plot Under Survey No 124 4
- West
- Tambe Construction Row House Project
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking25 units
0 of 25 units booked (0%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A | 2BHK | 74.18 sq m · 798 sq ft | 1 | 0 |
| B | 2BHK | 71.62 sq m · 771 sq ft | 8 | 0 |
| C | 2BHK | 71.62 sq m · 771 sq ft | 8 | 0 |
| D | 2BHK | 71.62 sq m · 771 sq ft | 8 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Nilesh Saswade | — |
| Chartered accountant | Pranav Gandhi | — |
| Chartered accountant | Pratik Gandhi | — |
| Engineer | Ajinkya Raut | — |
| Engineer | Balaji Waghmare | — |
Source: MahaRERA project page. Contact details are not shown.