Its promised completion date, Mar 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 84% of its units are booked.

Baner, Pune 411021 · Property rates in Baner · Promoter: Anand Realtors

Delivery2 yrs 7 mo past duePromised Mar 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales84% booked252 of 301 units · as the promoter reported to MahaRERA
Mount Unique project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Mar 2024, has passed and MahaRERA does not show it completed

  • P52100009362Registered 22 Aug 2017, completion promised 30 Jun 2018, and still not shown completed today.
  • P52100019240Registered 14 Jan 2019, completion promised 30 Mar 2024, and still not shown completed today.

No extension certificate on record.

2 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations2
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210000936222 Aug 201730 Jun 201830 Jun 2018Anand RealtorsProject page
P5210001924014 Jan 201930 Mar 202430 Mar 2024Anand RealtorsProject page
Documents106

2 documents held by Deedo, 104 filings listed on MahaRERA's project page

Registration certificate (2)

  • Registration certificateP52100009362 · 22 Aug 2017ViewSource
  • Registration certificateP52100019240 · 9 Sep 2021ViewSource

Legal

  • Declaration Form BP52100009362 · Form B Affidavit.pdf · uploaded 31 Jul 2017Source
  • Legal Title reportP52100009362 · Title Report.pdf · uploaded 31 Jul 2017Source
  • OtherP52100009362 · COMPLETION CERTIFICATE.pdf · uploaded 10 Nov 2017Source
  • Legal Title reportP52100019240 · Title Search Report.pdf · uploaded 9 Jan 2019Source
  • Declaration Form BP52100019240 · Form B.pdf · uploaded 9 Jan 2019Source

Migrated

  • 1 Copy of the legal title reportP52100009362 · Title Report.pdf · uploaded 31 Jul 2017Source
Show all 106 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesP52100009362 · Encumbrance Certificate MU.pdf · uploaded 31 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)P52100009362 · Sacn - 3.pdf · uploaded 31 Jul 2017Source
  • 1 Building Plan Approval (IOD)P52100009362 · Plan.pdf · uploaded 31 Jul 2017Source
  • 1 Declaration in FORM BP52100009362 · Form B Affidavit.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100009362 · Architect Mount Unique.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100009362 · Engineer Mount Unique.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of CA (Form 3)P52100009362 · CA Certificate-UNIQUE.pdf · uploaded 31 Jul 2017Source
  • 1 Proforma of Allotment letterP52100009362 · Agreement.pdf · uploaded 31 Jul 2017Source
  • 2 Proforma of Allotment letterP52100009362 · Mount Unique Agreement.pdf · uploaded 6 Oct 2017Source
  • 1 OtherP52100009362 · COMPLETION CERTIFICATE.pdf · uploaded 10 Nov 2017Source
  • 1 Certificates of Architect (Form 4)P52100009362 · Architect Certificate (MU) - RERA.pdf · uploaded 14 Nov 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100009362 · Anand Realtors CC.pdf · uploaded 9 Mar 2018Source
  • 1 Copy of the legal title reportP52100019240 · Title Search Report.pdf · uploaded 9 Jan 2019Source
  • 1 Details of encumbrancesP52100019240 · Encumbrance Certificate.pdf · uploaded 9 Jan 2019Source
  • 1 Copy of Layout Approval (in case of layout)P52100019240 · Layout.pdf · uploaded 9 Jan 2019Source
  • 1 Building Plan Approval (IOD)P52100019240 · Plan 1.pdf · uploaded 9 Jan 2019Source
  • 2 Building Plan Approval (IOD)P52100019240 · Plan 2.pdf · uploaded 9 Jan 2019Source
  • 3 Building Plan Approval (IOD)P52100019240 · Plan 3.pdf · uploaded 9 Jan 2019Source
  • 4 Building Plan Approval (IOD)P52100019240 · Plan 4.pdf · uploaded 9 Jan 2019Source
  • 5 Building Plan Approval (IOD)P52100019240 · Plan 5.pdf · uploaded 9 Jan 2019Source
  • 6 Building Plan Approval (IOD)P52100019240 · Plan 6.pdf · uploaded 9 Jan 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100019240 · Commencement Certificate.pdf · uploaded 9 Jan 2019Source
  • 1 Declaration in FORM BP52100019240 · Form B.pdf · uploaded 9 Jan 2019Source
  • 1 Certificates of CA (Form 3)P52100019240 · CA Certificate.pdf · uploaded 10 Jan 2019Source
  • 1 Proforma of Allotment letterP52100019240 · Agreement Format.pdf · uploaded 10 Jan 2019Source
  • 1 Form 2AP52100019240 · Form 2A.pdf · uploaded 15 Jun 2019Source
  • 2 Form 2AP52100019240 · Form 2A (September 2019).pdf · uploaded 26 Sep 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5)P52100019240 · Form 5 (2018-19).pdf · uploaded 26 Sep 2019Source
  • 2 Copy of Layout Approval (in case of layout)P52100019240 · 1-12.pdf · uploaded 28 Jan 2020Source
  • 7 Building Plan Approval (IOD)P52100019240 · 2-12.pdf · uploaded 28 Jan 2020Source
  • 8 Building Plan Approval (IOD)P52100019240 · 3-12.pdf · uploaded 28 Jan 2020Source
  • 9 Building Plan Approval (IOD)P52100019240 · 4-12.pdf · uploaded 28 Jan 2020Source
  • 10 Building Plan Approval (IOD)P52100019240 · 5-12.pdf · uploaded 28 Jan 2020Source
  • 11 Building Plan Approval (IOD)P52100019240 · 6-12.pdf · uploaded 28 Jan 2020Source
  • 12 Building Plan Approval (IOD)P52100019240 · 7-12.pdf · uploaded 28 Jan 2020Source
  • 13 Building Plan Approval (IOD)P52100019240 · 8-12.pdf · uploaded 28 Jan 2020Source
  • 14 Building Plan Approval (IOD)P52100019240 · 9-12.pdf · uploaded 28 Jan 2020Source
  • 15 Building Plan Approval (IOD)P52100019240 · 10-12.pdf · uploaded 28 Jan 2020Source
  • 16 Building Plan Approval (IOD)P52100019240 · 11-12.pdf · uploaded 28 Jan 2020Source
  • 17 Building Plan Approval (IOD)P52100019240 · 12-12.pdf · uploaded 28 Jan 2020Source
  • 2 Commencement Certificates / NA Order for plotted developmentP52100019240 · Commencement Certificate.pdf · uploaded 28 Jan 2020Source
  • 3 Form 2AP52100019240 · Form 2A (December 2019).pdf · uploaded 3 Feb 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)P52100019240 · Form 5 (2018-19).pdf · uploaded 3 Feb 2020Source
  • 3 Copy of Layout Approval (in case of layout)P52100019240 · Revised Layout.pdf · uploaded 28 Oct 2020Source
  • 18 Building Plan Approval (IOD)P52100019240 · Plan 1.pdf · uploaded 28 Oct 2020Source
  • 19 Building Plan Approval (IOD)P52100019240 · Plan 2.pdf · uploaded 28 Oct 2020Source
  • 20 Building Plan Approval (IOD)P52100019240 · Plan 3.pdf · uploaded 28 Oct 2020Source
  • 21 Building Plan Approval (IOD)P52100019240 · Plan 4.pdf · uploaded 28 Oct 2020Source
  • 22 Building Plan Approval (IOD)P52100019240 · Plan 5.pdf · uploaded 28 Oct 2020Source
  • 23 Building Plan Approval (IOD)P52100019240 · Plan 6.pdf · uploaded 28 Oct 2020Source
  • 24 Building Plan Approval (IOD)P52100019240 · Plan 7.pdf · uploaded 28 Oct 2020Source
  • 25 Building Plan Approval (IOD)P52100019240 · Plan 8.pdf · uploaded 28 Oct 2020Source
  • 26 Building Plan Approval (IOD)P52100019240 · Plan 9.pdf · uploaded 28 Oct 2020Source
  • 27 Building Plan Approval (IOD)P52100019240 · Plan 10.pdf · uploaded 28 Oct 2020Source
  • 28 Building Plan Approval (IOD)P52100019240 · Plan 11.pdf · uploaded 28 Oct 2020Source
  • 29 Building Plan Approval (IOD)P52100019240 · Plan 12.pdf · uploaded 28 Oct 2020Source
  • 3 Commencement Certificates / NA Order for plotted developmentP52100019240 · Revised Commencement Certificate.pdf · uploaded 28 Oct 2020Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100009362 · COMPLETION CERTIFICATE (A) Mount Unique.pdf · uploaded 6 Mar 2023Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100019240 · FULL COMPLETION CERTIFICATE (WING - B).pdf · uploaded 6 Mar 2023Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100019240 · COMPLETION CERTIFICATE WING C and SHOP.pdf · uploaded 6 Mar 2023Source
  • 2 Certificates of Architect (Form 4)P52100009362 · Form 4 MU Wing A.pdf · uploaded 28 Mar 2023Source
  • 5 Architect’s Certificate on Completion of Project (Form 4)P52100019240 · Form 4 Anand Realtors.pdf · uploaded 6 Oct 2023Source

Technical

  • DocumentP52100009362 · Sacn - 3.pdf · uploaded 31 Jul 2017Source
  • DocumentP52100009362 · Plan.pdf · uploaded 31 Jul 2017Source
  • DocumentP52100019240 · Layout.pdf · uploaded 9 Jan 2019Source
  • DocumentP52100019240 · Plan 1.pdf · uploaded 9 Jan 2019Source
  • DocumentP52100019240 · Plan 2.pdf · uploaded 9 Jan 2019Source
  • DocumentP52100019240 · Plan 3.pdf · uploaded 9 Jan 2019Source
  • DocumentP52100019240 · Plan 4.pdf · uploaded 9 Jan 2019Source
  • DocumentP52100019240 · Plan 5.pdf · uploaded 9 Jan 2019Source
  • DocumentP52100019240 · Plan 6.pdf · uploaded 9 Jan 2019Source
  • DocumentP52100019240 · 1-12.pdf · uploaded 28 Jan 2020Source
  • DocumentP52100019240 · 2-12.pdf · uploaded 28 Jan 2020Source
  • DocumentP52100019240 · 3-12.pdf · uploaded 28 Jan 2020Source
  • DocumentP52100019240 · 4-12.pdf · uploaded 28 Jan 2020Source
  • DocumentP52100019240 · 5-12.pdf · uploaded 28 Jan 2020Source
  • DocumentP52100019240 · 6-12.pdf · uploaded 28 Jan 2020Source
  • DocumentP52100019240 · 7-12.pdf · uploaded 28 Jan 2020Source
  • DocumentP52100019240 · 8-12.pdf · uploaded 28 Jan 2020Source
  • DocumentP52100019240 · 9-12.pdf · uploaded 28 Jan 2020Source
  • DocumentP52100019240 · 10-12.pdf · uploaded 28 Jan 2020Source
  • DocumentP52100019240 · 11-12.pdf · uploaded 28 Jan 2020Source
  • DocumentP52100019240 · 12-12.pdf · uploaded 28 Jan 2020Source
  • DocumentP52100019240 · Revised Layout.pdf · uploaded 28 Oct 2020Source
  • DocumentP52100019240 · Plan 1.pdf · uploaded 28 Oct 2020Source
  • DocumentP52100019240 · Plan 2.pdf · uploaded 28 Oct 2020Source
  • DocumentP52100019240 · Plan 3.pdf · uploaded 28 Oct 2020Source
  • DocumentP52100019240 · Plan 4.pdf · uploaded 28 Oct 2020Source
  • DocumentP52100019240 · Plan 5.pdf · uploaded 28 Oct 2020Source
  • DocumentP52100019240 · Plan 6.pdf · uploaded 28 Oct 2020Source
  • DocumentP52100019240 · Plan 7.pdf · uploaded 28 Oct 2020Source
  • DocumentP52100019240 · Plan 8.pdf · uploaded 28 Oct 2020Source
  • DocumentP52100019240 · Plan 9.pdf · uploaded 28 Oct 2020Source
  • DocumentP52100019240 · Plan 10.pdf · uploaded 28 Oct 2020Source
  • DocumentP52100019240 · Plan 11.pdf · uploaded 28 Oct 2020Source
  • DocumentP52100019240 · Plan 12.pdf · uploaded 28 Oct 2020Source

Technical (Architect)

  • DocumentP52100009362 · Architect Mount Unique.pdf · uploaded 31 Jul 2017Source

Technical (Engineer)

  • DocumentP52100009362 · Engineer Mount Unique.pdf · uploaded 31 Jul 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsS No 52/4/1

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Phases
2
Unit types
1 BHK, 2 BHK, 3 BHK, 1BHK, 2BHK, 3BHK, Shop 11, Shop 12, Shop 13, Shop 14, Shop 15, Shop 16, Shop 17, Shop 18, Shop 19301 units in all
Address
S No 52/4/1, Sus-Pashan Road, BanerPIN 411021
Village
Baner, Haveli taluka
Designated bank account
171
Developed in phases
No
Also registered as
Mount Unique A Wing, Mount Unique B and C Wing

Survey, CTS, gat or plot numbers

S No 52/4/1

Boundaries

North
Amenity Space
South
30 Mtr Wide Road
East
Internal Road
West
Remaining Land of S No 52

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking301 units

252 of 301 units booked (84%), as the promoter reported to MahaRERA

1 BHK · 2 units2 BHK · 82 units3 BHK · 28 units1BHK · 39 units2BHK · 109 units3BHK · 32 unitsShop 11 · 1 unitShop 12 · 1 unitShop 13 · 1 unitShop 14 · 1 unitShop 15 · 1 unitShop 16 · 1 unitShop 17 · 1 unitShop 18 · 1 unitShop 19 · 1 unit
RERABuildingTypeCarpet areaUnitsBooked
P52100009362A Wing1 BHK37.54 sq m · 404 sq ft21
P52100009362A Wing2 BHK49.61 sq m · 534 sq ft2620
P52100009362A Wing2 BHK49.91 sq m · 537 sq ft146
P52100009362A Wing2 BHK51.62 sq m · 556 sq ft1410
P52100009362A Wing2 BHK54.37 sq m · 585 sq ft147
P52100009362A Wing2 BHK56.09 sq m · 604 sq ft1411
P52100009362A Wing3 BHK64.54 sq m · 695 sq ft142
P52100009362A Wing3 BHK67.16 sq m · 723 sq ft147
Show all 30 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P52100019240B Wing1BHK39.12 sq m · 421 sq ft33
P52100019240B Wing2BHK59.53 sq m · 641 sq ft1616
P52100019240B Wing2BHK63.55 sq m · 684 sq ft1313
P52100019240B Wing2BHK63.97 sq m · 689 sq ft1616
P52100019240B Wing2BHK64.86 sq m · 698 sq ft1615
P52100019240B Wing2BHK68.25 sq m · 735 sq ft1616
P52100019240B Wing2BHK68.58 sq m · 738 sq ft1616
P52100019240B Wing2BHK69 sq m · 743 sq ft1616
P52100019240B Wing3BHK81.01 sq m · 872 sq ft1616
P52100019240B Wing3BHK91.81 sq m · 988 sq ft1616
P52100019240B WingShop 1130.44 sq m · 328 sq ft11
P52100019240B WingShop 1229.37 sq m · 316 sq ft11
P52100019240B WingShop 1347.06 sq m · 507 sq ft11
P52100019240B WingShop 1444.3 sq m · 477 sq ft11
P52100019240B WingShop 1547.12 sq m · 507 sq ft11
P52100019240B WingShop 1625.21 sq m · 271 sq ft11
P52100019240B WingShop 1723.28 sq m · 251 sq ft11
P52100019240B WingShop 1834.33 sq m · 370 sq ft11
P52100019240B WingShop 1925.53 sq m · 275 sq ft11
P52100019240C Wing1BHK30.34 sq m · 327 sq ft66
P52100019240C Wing1BHK30.97 sq m · 333 sq ft66
P52100019240C Wing1BHK36.12 sq m · 389 sq ft2424

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectPrakash Chandak—P52100009362
ArchitectPrakash Chandak—P52100019240
Registered real estate agentPriyanka Nautiyal—P52100009362

Source: MahaRERA project page. Contact details are not shown.