Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 22% of its units are booked.

Balewadi, Pune 411045 · Property rates in Balewadi · by Hubtown Limited

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales22% booked4 of 18 units · as the promoter reported to MahaRERAPrice₹11,900 /sq ft9.1% above Balewadi · 36 registered sales

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 6 Feb 2024, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

All 36 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Nov 2026Main building · 505Primary sale2,474 sq ftView Primary sale, Nov 2026
Oct 2026It & Ites BuildingPrimary sale6,113 sq ftView Primary sale, Oct 2026
Oct 2026It & Ites BuildingPrimary sale1,696 sq ftView Primary sale, Oct 2026
Oct 2026It & Ites BuildingPrimary sale2,098 sq ftView Primary sale, Oct 2026
Oct 2026It & Ites BuildingPrimary sale2,025 sq ftView Primary sale, Oct 2026
Oct 2026It & Ites BuildingPrimary sale3,517 sq ftView Primary sale, Oct 2026
Oct 2026It & Ites BuildingPrimary sale3,718 sq ftView Primary sale, Oct 2026
Oct 2026It & Ites BuildingPrimary sale2,146 sq ftView Primary sale, Oct 2026
Oct 2026It & Ites BuildingPrimary sale2,699 sq ftView Primary sale, Oct 2026
Sep 2026It & Ites Building · 1102Primary sale6,113 sq ftView Primary sale, Sep 2026

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100054731
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000547316 Feb 202431 Dec 202830 Apr 2029Hubtown LimitedProject page
Documents147

1 document held by Deedo, 146 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardHUBTOWN PAN CARD.pdf · uploaded 6 Jan 2024Source
  • Other – FinanceResolution_Jasmin Balewadi (1).pdf · uploaded 10 Jan 2024Source
  • PAN CardResolution_Jasmin Balewadi (2).pdf · uploaded 11 Jan 2024Source
  • Other – FinanceResolution Hubtown 20092022 (1).pdf · uploaded 12 Jan 2024Source

Legal

  • Other – LegalResolution_Jasmin Balewadi (1).pdf · uploaded 10 Jan 2024Source
  • Legal Title reportSearch and Title Report_Adv Amruta_11zon.pdf · uploaded 10 Jan 2024Source
  • Other – LegalResolution Hubtown 20092022 (1).pdf · uploaded 12 Jan 2024Source
Show all 147 documentsShow fewer documents

Legal

  • Legal Title report27WEST search and title report (1) (1).pdf · uploaded 12 Jan 2024Source
  • Declaration Form BDeclaration Promoter.pdf · uploaded 15 Jan 2024Source
  • Other – LegalDeed of Dissolution H-1-45.pdf · uploaded 25 Jan 2024Source
  • Other – LegalDeed of Dissolution H-46-92_11zon.pdf · uploaded 25 Jan 2024Source
  • Other – LegalDeed of Dissolution H-93-140_11zon.pdf · uploaded 25 Jan 2024Source
  • Other – LegalDeed of Dissolution H-141-185.pdf · uploaded 25 Jan 2024Source
  • Other – LegalDeed of Dissolution H-186-230.pdf · uploaded 25 Jan 2024Source
  • Other – LegalDeed of Dissolution H-231-280_11zon.pdf · uploaded 25 Jan 2024Source
  • Other – LegalDeed of Dissolution H-281-325_11zon.pdf · uploaded 25 Jan 2024Source
  • Other – LegalDeed of Dissolution H-326-356.pdf · uploaded 25 Jan 2024Source
  • Legal Title reportTSR (1).pdf · uploaded 5 Dec 2024Source

Migrated

  • 1 PAN CardHUBTOWN PAN CARD.pdf · uploaded 6 Jan 2024Source
  • 1 a Details of encumbrances concerned to FinanceNo Encumbrance.pdf · uploaded 6 Jan 2024Source
  • 2 a Details of encumbrances concerned to FinanceLegal encumbrance.pdf · uploaded 6 Jan 2024Source
  • 1 b Details of encumbrances concerned to LegalNo Encumbrance.pdf · uploaded 6 Jan 2024Source
  • 2 b Details of encumbrances concerned to LegalLegal encumbrance.pdf · uploaded 6 Jan 2024Source
  • 1 Copy of Layout Approval (in case of layout)Sanction Plan_compressed.pdf · uploaded 6 Jan 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentSanction Plan_2.pdf · uploaded 6 Jan 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 6 Jan 2024Source
  • 1 Declaration about Commencement Certificatecommencement declaration.pdf · uploaded 6 Jan 2024Source
  • 1 CERSAI detailsCERSAI Declaration.pdf · uploaded 6 Jan 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 6 Jan 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A 1.pdf · uploaded 6 Jan 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDisclosure_Bhakti Kothare.pdf · uploaded 6 Jan 2024Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsDisclosure_Jignesh Gala .pdf · uploaded 6 Jan 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A_BAnk details.pdf · uploaded 6 Jan 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-03 27 WEST.pdf · uploaded 9 Jan 2024Source
  • 1 Copy of the legal title reportSearch and Title Report_Adv Amruta_11zon.pdf · uploaded 10 Jan 2024Source
  • 5 Disclosure of Interest in Other Real Estate OrganizationsDirector Kartik Ruparel_Annexure A.pdf · uploaded 10 Jan 2024Source
  • 6 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A - Milind Ramani.pdf · uploaded 10 Jan 2024Source
  • 1 Other – LegalResolution_Jasmin Balewadi (1).pdf · uploaded 10 Jan 2024Source
  • 1 Other – FinanceResolution_Jasmin Balewadi (1).pdf · uploaded 10 Jan 2024Source
  • 1 Other – TechnicalResolution_Jasmin Balewadi (1).pdf · uploaded 10 Jan 2024Source
  • 2 PAN CardResolution_Jasmin Balewadi (2).pdf · uploaded 11 Jan 2024Source
  • 1 Proforma of Allotment letter1 Proforma of Allotment letter (2) (1).pdf · uploaded 11 Jan 2024Source
  • 1 Proforma of Agreement for sale1 Proforma of Agreement for sale (1) (1).pdf · uploaded 11 Jan 2024Source
  • 1 Deviation Report with respect to Allotment letter1 Deviation Report with respect to Allotment letter (1).pdf · uploaded 11 Jan 2024Source
  • 1 Deviation Report with respect to model copy of Agreement1 Deviation Report with respect to model copy of Agreement (1).pdf · uploaded 11 Jan 2024Source
  • 2 Other – TechnicalResolution_Jasmin Balewadi (2).pdf · uploaded 11 Jan 2024Source
  • 2 Copy of the legal title report27WEST search and title report (1) (1).pdf · uploaded 12 Jan 2024Source
  • 2 Other – LegalResolution Hubtown 20092022 (1).pdf · uploaded 12 Jan 2024Source
  • 2 Other – FinanceResolution Hubtown 20092022 (1).pdf · uploaded 12 Jan 2024Source
  • 3 Other – TechnicalResolution Hubtown 20092022 (1).pdf · uploaded 12 Jan 2024Source
  • 1 Declaration in FORM BDeclaration Promoter.pdf · uploaded 15 Jan 2024Source
  • 3 Other – LegalDeed of Dissolution H-1-45.pdf · uploaded 25 Jan 2024Source
  • 4 Other – LegalDeed of Dissolution H-46-92_11zon.pdf · uploaded 25 Jan 2024Source
  • 5 Other – LegalDeed of Dissolution H-93-140_11zon.pdf · uploaded 25 Jan 2024Source
  • 6 Other – LegalDeed of Dissolution H-141-185.pdf · uploaded 25 Jan 2024Source
  • 7 Other – LegalDeed of Dissolution H-186-230.pdf · uploaded 25 Jan 2024Source
  • 8 Other – LegalDeed of Dissolution H-231-280_11zon.pdf · uploaded 25 Jan 2024Source
  • 9 Other – LegalDeed of Dissolution H-281-325_11zon.pdf · uploaded 25 Jan 2024Source
  • 10 Other – LegalDeed of Dissolution H-326-356.pdf · uploaded 25 Jan 2024Source
  • 3 a Details of encumbrances concerned to FinanceEncum Certificate.pdf · uploaded 30 Jan 2024Source
  • 3 b Details of encumbrances concerned to LegalEncum Certificate.pdf · uploaded 30 Jan 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)SIGNED FORM 3 - HUBTOWN_compressed.pdf · uploaded 22 Jul 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Certificate_West27_30-06-2024.pdf · uploaded 23 Jul 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)HUBTOWN FORM 3_organized_compressed.pdf · uploaded 23 Jul 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 June 2024.pdf · uploaded 31 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 2A March 2024_removed.pdf · uploaded 31 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 March 2024.pdf · uploaded 6 Aug 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 June 2024.pdf · uploaded 6 Aug 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)QA Certificate-FY 23-24.pdf · uploaded 10 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 27West.pdf · uploaded 10 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Cert 27WEST.pdf · uploaded 19 Oct 2024Source
  • 2 Disclosure of sold/ booked inventorySold Unsold Inventory 27West.pdf · uploaded 19 Oct 2024Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Qty Assurance Cert 27WEST.pdf · uploaded 19 Oct 2024Source
  • 1 Copy of the legal title reportTSR (1).pdf · uploaded 5 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)27WEST form 1.pdf · uploaded 18 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)SIGNED FROM 27 west final.pdf · uploaded 18 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 27 west.pdf · uploaded 18 Jan 2025Source
  • 1 Disclosure of sold/ booked inventory27WEST sold unsold.pdf · uploaded 18 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A.pdf · uploaded 18 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (2).pdf · uploaded 20 Jan 2025Source
  • Form 1Form 1 31-03-20.pdf · uploaded 30 May 2025Source
  • Form 2Form 2 31-03-25.pdf · uploaded 30 May 2025Source
  • Form 3Form 3_27West.pdf · uploaded 30 May 2025Source
  • Disclosure of Sold and Booked InventorySold-Unsold 31-03-25.pdf · uploaded 30 May 2025Source
  • Form 1Form 1 Architect Certificate.pdf · uploaded 18 Aug 2025Source
  • Form 2FORM 2 - ENGINEER'S CERTIFICATE.pdf · uploaded 18 Aug 2025Source
  • Form 3Form 3 CA CERTIFICATE.pdf · uploaded 18 Aug 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD INVENTORY.pdf · uploaded 18 Aug 2025Source
  • Withdrawal Update Form 1Form 1_Architect Certifcate_30-09-2025.pdf · uploaded 14 Oct 2025Source
  • Withdrawal Update Form 2Form 2 Engineers Certifcate_30-09-2025.pdf · uploaded 14 Oct 2025Source
  • Withdrawal Update Form 3FORM-3_30-09-2025.pdf · uploaded 14 Oct 2025Source
  • Form 2A (FY 2024-2025)Form 2A Engineers Certifcate_30-09-2025.pdf · uploaded 14 Oct 2025Source
  • Form 5 (FY 2024-2025)27west-Signed.pdf · uploaded 15 Oct 2025Source
  • Withdrawal Update Form 1Form 1_Architect Certifcate_31-12-2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3Form 3_CA_Certificate_31-12-2025.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 1fORM 1_HUBTOWN.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 2FORM 2 HUBTOWN (1).pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 3Form 3 (CA Certificate).pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 1fORM 1_HUBTOWN.pdf · uploaded 6 May 2026Source
  • Withdrawal Update Form 2FORM 2 HUBTOWN (1).pdf · uploaded 6 May 2026Source
  • Withdrawal Update Form 3Form 3 (CA Certificate).pdf · uploaded 6 May 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 22 Sep 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 22 Sep 2026Source
  • Withdrawal Update Form 3Form 3 (1).pdf · uploaded 22 Sep 2026Source

Technical

  • DocumentSanction Plan_compressed.pdf · uploaded 6 Jan 2024Source
  • DocumentSanction Plan_2.pdf · uploaded 6 Jan 2024Source
  • Other – TechnicalResolution_Jasmin Balewadi (1).pdf · uploaded 10 Jan 2024Source
  • Other – TechnicalResolution_Jasmin Balewadi (2).pdf · uploaded 11 Jan 2024Source
  • Other – TechnicalResolution Hubtown 20092022 (1).pdf · uploaded 12 Jan 2024Source
  • DocumentLAYOUT (1) (1).pdf · uploaded 8 Nov 2025Source
  • Document2-compressed.pdf · uploaded 8 Nov 2025Source
  • Document3.pdf · uploaded 8 Nov 2025Source
  • Document4.pdf · uploaded 8 Nov 2025Source
  • Document5.pdf · uploaded 8 Nov 2025Source
  • Document6.pdf · uploaded 8 Nov 2025Source
  • Document7-compressed.pdf · uploaded 8 Nov 2025Source
  • Document8.pdf · uploaded 8 Nov 2025Source
  • Document9.pdf · uploaded 8 Nov 2025Source
  • Document10-rotated.pdf · uploaded 8 Nov 2025Source
  • DocumentLAYOUT (1) (1).pdf · uploaded 8 Nov 2025Source
  • Document2-compressed.pdf · uploaded 8 Nov 2025Source
  • Document3.pdf · uploaded 8 Nov 2025Source
  • Document4.pdf · uploaded 8 Nov 2025Source
  • Document5.pdf · uploaded 8 Nov 2025Source
  • Document6.pdf · uploaded 8 Nov 2025Source
  • Document7-compressed.pdf · uploaded 8 Nov 2025Source
  • Document8.pdf · uploaded 8 Nov 2025Source
  • Document9.pdf · uploaded 8 Nov 2025Source
  • Document10-rotated.pdf · uploaded 8 Nov 2025Source
  • OthersFormat D_Commencement Declaration (1).pdf · uploaded 8 Nov 2025Source
  • DocumentLayout Plan- Highlighted.pdf · uploaded 6 May 2026Source
  • Document2.pdf · uploaded 6 May 2026Source
  • Document3.pdf · uploaded 6 May 2026Source
  • Document4.pdf · uploaded 6 May 2026Source
  • Document5.pdf · uploaded 6 May 2026Source
  • Document6.pdf · uploaded 6 May 2026Source
  • Document7.pdf · uploaded 6 May 2026Source
  • Document8.pdf · uploaded 6 May 2026Source
  • OthersHubtown_Declaration_Commencement.pdf · uploaded 6 May 2026Source

Technical (Architect)

  • Document27WEST form 1.pdf · uploaded 18 Jan 2025Source
  • DocumentFORM 1.pdf · uploaded 22 Sep 2026Source

Technical (Engineer)

  • DocumentEngg Cert 27WEST.pdf · uploaded 19 Oct 2024Source
  • DocumentFORM 2 27 west.pdf · uploaded 18 Jan 2025Source
  • DocumentForm 2 (2).pdf · uploaded 20 Jan 2025Source
  • DocumentFORM 2.pdf · uploaded 22 Sep 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SURVEY NO 27 HISSA NO 1/2/5

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Unit types
office, Shop18 units in all
Address
Survey No 27 Hissa No 1/2/5, S No 27/1/2/5, BalewadiPIN 411045
Village
Balewadi, Haveli taluka
Land area for this project
10,100 sq m (1,08,715 sq ft)
Permissible built-up area
48,551 sq m (5,22,598 sq ft)
Sanctioned built-up area
48,450 sq m (5,21,511 sq ft)
Recreational open space
908 sq m (9,776 sq ft)
Designated bank account
82
Developed in phases
No
Also registered as
27 Vest, 27 वेस्ट

Survey, CTS, gat or plot numbers

SURVEY NO 27 HISSA NO 1/2/5

Land as published on MahaRERA's project page

SURVEY NO 27 HISSA NO 1/2/5

Boundaries

North
By S No 27-1-2-3
South
By S No 27-1-2-6
East
By S No 27-2
West
By Mahalunge-Balewadi Shiv And Part National Highw

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking18 units

4 of 18 units booked (22%), as the promoter reported to MahaRERA

office · 4 unitsShop · 14 units
TypeCarpet areaUnitsBooked
office217.94 sq m · 2,346 sq ft21
office353.67 sq m · 3,807 sq ft21
Shop307.23 sq m · 3,307 sq ft22
Shop322.05 sq m · 3,467 sq ft20
Shop345.56 sq m · 3,720 sq ft40
Shop360.77 sq m · 3,883 sq ft20
Shop426.54 sq m · 4,591 sq ft40

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPavan Govindprasad Dayma—
ArchitectVishal Despande—
Chartered accountantSiddhant Abhay Bora—
EngineerPrasad Nivrutti Kanawade—
OtherVeritas Constructions—

Source: MahaRERA project page. Contact details are not shown.

27west in numbers

Registered deals, summarised

Deedo has 36 registered documents at 27west, from Dec 2024 to Nov 2026: 36 sales. The median registered sale since Dec 2024 works out to about ₹11,900 per sq ft, at a median of ₹3.23 Cr a deal; 0% of sales were resales.

What is the price per sq ft at 27west?
The median registered sale since Dec 2024 works out to about ₹11,900 per sq ft, at a median of ₹3.23 Cr a deal; 0% of sales were resales.
How many properties have been sold at 27west?
36 sales are registered at 27west.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at 27west by Deedo, last updated with deals registered in Nov 2026.

Latest deal · Primary sale · Nov 2026

₹2–3.5 Cr