7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects29in 10 localities
Registrations29
Completion still due316 past their date
Median extension4 months21% of registrations extended
Regulatory cases1on 1 project

7 in 10 registrations run late here

29 MahaRERA registrations in Parbhani and the places within it

3 extended, not yet due16 past even the latest date10 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Parbhani

29 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Morya HeightsMorya Developers1 yr 5 mo late——
Samarth ResidencySamarth Residency Boi4 mo late——
Smart CityIraj Siddiqui Ifteqaroddin SiddiquiDue Apr 2028, extended 4 mo—27%
Mangalmurti ResidencyMahesh Balkishan SoniDue Mar 2028, extended 4 mo—3%
Godavari NagariGodavari Nagari Developers LLP1 yr 8 mo late——
All 29 projects →
Parbhani market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Localities in Parbhani

Most active promoters

  1. Ganesh Jagannath Farkande2 projects
  2. Akbaroddin Jainulabedin Siddiqui1 project
  3. Dhanlakshmi Construction1 project
  4. Godavari Nagari Developers Llp1 project
  5. Iraj Siddiqui Ifteqaroddin Siddiqui1 project
  6. Jagdish Balasaheb Shinde1 project
  7. Kailash Dayaram Jethwani1 project
  8. Katruwar Manish Vijay Kumar (Huf)1 project
  9. Kishor Sudhakarrao Deshpande1 project
  10. Kuber Builder & Developer1 project

Parbhani, in questions

How many projects in Parbhani run late?

7 in 10 MahaRERA registrations (19 of 29): their completion date was extended or has passed, data through 5 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Parbhani by Deedo. Medians on fewer than 3 deeds are not shown.

Data through5 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology