RERA projects in Parbhani

29 projects under 29 MahaRERA registrations across 10 localities, registered 2017–2025. 5% have a completion date extended beyond the one promised.

29RERA projectsin 10 localities
29Registrations
3Completion still due16 past their completion date
69 monthsMedian extension beyond promised date5% of registrations extended
1Regulatory caseson 1 project
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20177
20181
20190
20202
20213
20222
20232
20241
20251

Localities in Parbhani

By number of registered projects. Talukas and localities as MahaRERA names them.

Projects in Parbhani

29 projects registered with MahaRERA in this district and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Morya HeightsMorya DevelopersP5130007884215 Jan 202525 Jun 2025—Promised date passed0
Samarth ResidencySamarth Residency BoiP5130005426310 Jan 202431 Jul 2026—Promised date passed0
Smart CityIraj Siddiqui Ifteqaroddin SiddiquiP5130005391911 Dec 202331 Dec 2027—Not yet due0
Mangalmurti ResidencyMahesh Balkishan SoniP5130004894224 Jan 20232 Nov 2027—Not yet due0
Godavari NagariGodavari Nagari Developers LLPP5130003511210 May 202231 Mar 2025—Promised date passed0
Shree Samarth RealityShri Samarth Reality ParbhaniP5130003356022 Feb 202231 Dec 2025—Promised date passed0
Gokuldham HeightKailash Dayaram JethwaniP513000310885 Oct 202116 Jun 2026—Promised date passed0
Kuber Builder And DeveloperKuber Builder & DeveloperP5130003034717 Aug 202123 Nov 2023—Promised date passed0
Sai NagarJagdish Balasaheb ShindeP513000298044 Jul 202131 Mar 2022—Promised date passed0
Dhanlakshmi ApartmentDhanlakshmi ConstructionP5130002525727 Mar 202030 Dec 2024—Promised date passed0
Shri Ganesh Nagari Na PlotsKatruwar Manish Vijay Kumar (Huf)P5130002443313 Feb 202030 Mar 2022—Promised date passed0
Tapadia Estate - Phase ITapadia InfraprojectsP5130001684720 Jun 201830 Jun 202131 Mar 2027Extended 69 mo0
Gokuldham Row HouseKishor Sudhakarrao DeshpandeP5130001171717 Nov 201731 Dec 2017—Promised date passed0
Bokan HeritageSwapanil Chandrakant BokanP5130001375225 Oct 20179 Jan 2019—Promised date passed0
SmartcitySameer Ramanlal BhandariP513000121071 Sep 201730 Jun 2026—Promised date passed0
Yash NisargaYash Farkande Trading CompanyP5130001058931 Aug 20171 Jan 2026—Promised date passed0
Yash Nisarga Part 1Ganesh Jagannath FarkandeP5130001134731 Aug 20171 Jan 2026—Promised date passed0
Yash Nisarga Part3Ganesh Jagannath FarkandeP5130001076331 Aug 20171 Jan 2026—Promised date passed0
Varad Vinayak ApartmentPrabhawati DevelopersP5130000232831 Jul 201731 Mar 2018—Promised date passed0
Ganesh NagarAkbaroddin Jainulabedin SiddiquiP51300022828————1
Govindraj Row House ParbhaniP51300016168————0
Laxman NagarP51300023953————0
Matoshri NagriP51300028600————0
Mauli NagarP51300026095————0
Om NagarP51300025331————0
P51300048495P51300048495————0
Padmawati TowerP51300008760————0
Sairatan NagariP51300006077————0
SmartcityP51300012606————0

Other districts

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Ganesh Jagannath Farkande2 projects
  2. Akbaroddin Jainulabedin Siddiqui1 project
  3. Dhanlakshmi Construction1 project
  4. Godavari Nagari Developers LLP1 project
  5. Iraj Siddiqui Ifteqaroddin Siddiqui1 project
  6. Jagdish Balasaheb Shinde1 project
  7. Kailash Dayaram Jethwani1 project
  8. Katruwar Manish Vijay Kumar (Huf)1 project
  9. Kishor Sudhakarrao Deshpande1 project
  10. Kuber Builder & Developer1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology