RERA projects in Parbhani

19 projects under 19 MahaRERA registrations, registered 2017–2025. 20% have a completion date extended beyond the one promised.

Taluka
19RERA projects
19Registrations
3Completion still due12 past their completion date
4 monthsMedian extension beyond promised date20% of registrations extended
0Regulatory casesnone on MahaRERA's lists
205Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20177
20180
20190
20201
20212
20221
20232
20241
20251

Projects in Parbhani

19 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Morya HeightsMorya DevelopersP5130007884215 Jan 202525 Jun 202525 Jun 2025Promised date passed0
Samarth ResidencySamarth Residency BoiP5130005426310 Jan 202431 Jul 202631 Jul 2026Promised date passed0
Smart CityIraj Siddiqui Ifteqaroddin SiddiquiP5130005391911 Dec 202331 Dec 202730 Apr 2028Extended 4 mo0
Mangalmurti ResidencyMahesh Balkishan SoniP5130004894224 Jan 20232 Nov 20272 Mar 2028Extended 4 mo0
Shree Samarth RealityShri Samarth Reality ParbhaniP5130003356022 Feb 202231 Dec 202531 Dec 2025Promised date passed0
Gokuldham HeightKailash Dayaram JethwaniP513000310885 Oct 202116 Jun 202616 Jun 2026Promised date passed0
Kuber Builder And DeveloperKuber Builder & DeveloperP5130003034717 Aug 202123 Nov 202323 Nov 2023Promised date passed0
Dhanlakshmi ApartmentDhanlakshmi ConstructionP5130002525727 Mar 202030 Dec 202430 Dec 2024Promised date passed0
Gokuldham Row HouseKishor Sudhakarrao DeshpandeP5130001171717 Nov 201731 Dec 201731 Dec 2017Promised date passed0
Bokan HeritageSwapanil Chandrakant BokanP5130001375225 Oct 20179 Jan 20199 Jan 2019Promised date passed0
SmartcitySameer Ramanlal BhandariP513000121071 Sep 201730 Jun 202630 Oct 2026Extended 4 mo0
Yash NisargaYash Farkande Trading CompanyP5130001058931 Aug 20171 Jan 20261 Jan 2026Promised date passed0
Yash Nisarga Part 1Ganesh Jagannath FarkandeP5130001134731 Aug 20171 Jan 20261 Jan 2026Promised date passed0
Yash Nisarga Part3Ganesh Jagannath FarkandeP5130001076331 Aug 20171 Jan 20261 Jan 2026Promised date passed0
Varad Vinayak ApartmentPrabhawati DevelopersP5130000232831 Jul 201731 Mar 201831 Mar 2018Promised date passed0
Govindraj Row House ParbhaniP51300016168————0
P51300048495P51300048495————0
Padmawati TowerP51300008760————0
SmartcityP51300012606————0

Other talukas in Parbhani

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Ganesh Jagannath Farkande2 projects
  2. Dhanlakshmi Construction1 project
  3. Iraj Siddiqui Ifteqaroddin Siddiqui1 project
  4. Kailash Dayaram Jethwani1 project
  5. Kishor Sudhakarrao Deshpande1 project
  6. Kuber Builder & Developer1 project
  7. Mahesh Balkishan Soni1 project
  8. Morya Developers1 project
  9. Prabhawati Developers1 project
  10. Samarth Residency Boi1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology