Skip to content
Mixed · 1 building · 12 unitsRERA PM1240002502766

Mamle Heights

Deedo IDDP-PAL-01J9

Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 0% of its units are booked.

Virar, Palghar 401305 · by Mamle Developers Pvt Ltd

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 12 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 12 Mar 2026, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPM1240002502766
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM124000250276612 Mar 202631 Dec 202830 Apr 2029Mamle Developers Pvt LtdProject page
Documents20

1 document held by Deedo, 19 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardMamle Developers PAN Card 1.pdf · uploaded 3 Feb 2026Source
  • OthersLandowners bank declaration.pdf · uploaded 24 Feb 2026Source

Legal

  • OthersMAMLEDEV-ANNX-A-TRUPTI-DECLARATION.pdf · uploaded 22 Jan 2026Source
  • OthersMAMLEDEV-ANNX-A-DISCLOSURE-INTERETST-OTHER-RE.pdf · uploaded 22 Jan 2026Source
  • Declaration Form BMAMLEDEV-AFFDCUMDECL.pdf · uploaded 22 Jan 2026Source
  • Declaration Form BMAMLEDEV-FORMAT-A.pdf · uploaded 22 Jan 2026Source
  • Declaration Form Bmamle_compressed.pdf · uploaded 22 Jan 2026Source
Show all 20 documentsShow fewer documents

Legal

  • Declaration Form B7 12 (2).pdf · uploaded 19 Feb 2026Source
  • Others7 12 mamle heights-1.pdf · uploaded 24 Feb 2026Source

Migrated

  • Withdrawal Update Form 1Form 1 Mamle Developers.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 2Form 2 Eng Certificate-1-2.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 3FORM 3 FINAL-1.pdf · uploaded 9 Jun 2026Source

Technical

  • DocumentMAMLE HEIGHTS APPROVAL PLAN.pdf · uploaded 22 Jan 2026Source
  • DocumentMAMLE HEIGHTS APPROVAL PLAN.pdf · uploaded 22 Jan 2026Source
  • DocumentMAMLEDEV order 50.pdf · uploaded 22 Jan 2026Source
  • OthersArchitect Form 1 Mamle (2).pdf · uploaded 24 Feb 2026Source
  • OthersEnginner Certificate 2_compressed.pdf · uploaded 24 Feb 2026Source

Technical (Architect)

  • DocumentForm 1 Mamle Developers.pdf · uploaded 4 Jun 2026Source

Technical (Engineer)

  • DocumentForm 2 Eng Certificate-1-2.pdf · uploaded 9 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 275/7/C

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
—12 units in all
Address
Road, RoadPIN 401305
Village
Virar, Vasai taluka
Land area for this project
576 sq m (6,201 sq ft)
Permissible built-up area
1,425 sq m (15,344 sq ft)
Sanctioned built-up area
1,425 sq m (15,344 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
82
Developed in phases
No

Survey, CTS, gat or plot numbers

275/7/C

Land as published on MahaRERA's project page

275/7/C

Boundaries

North
West
South
West
East
West
West
West

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking12 units

12 units registered

— · 12 units
TypeCarpet areaUnits
——12

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
EngineerSwapnil Jadhav—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Virar

All 60 projects in Virar · Compare Mamle Heights with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology