RERA projects in Vasaivirar City (M Corp)

863 projects under 915 MahaRERA registrations, registered 2017–2026. 60% have a completion date extended beyond the one promised.

Locality
863RERA projects
915Registrationssome projects hold several
370Completion still due545 past their completion date
4 monthsMedian extension beyond promised date60% of registrations extended
16Regulatory caseson 14 projects
1,622Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
2017398
201824
201954
202038
202162
202283
202381
2024113
202557
20265

Projects in Vasaivirar City (M Corp)

863 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Shree Vasant Vihar Nx C WingShree Riddhi Siddhi DevelopersP990000802147 May 202531 Dec 202730 Apr 2028Extended 4 mo0
New Kasturi SadanShiv Shakti EnterprisesP9900008013930 Apr 202531 Dec 203030 Apr 2031Extended 4 mo0
Sky InfiniaUniquepoonam Homes LLPP9900008012229 Apr 202531 Mar 202931 Jul 2029Extended 4 mo0
Laxmi HeightsJanavi Builders & DevelopersP9900008003721 Apr 202531 Dec 202731 Dec 2027Not yet due0
Datta ViharVed SamarthP9900007999111 Apr 202531 Dec 202830 Apr 2029Extended 4 mo0
Chandresh RatnaShree Shakti InfraP9900007987128 Mar 202531 Dec 202830 Apr 2029Extended 4 mo0
Shree Ameya Co-Op Housing Society LtdOrion VenturesP9900007985928 Mar 20251 Apr 20281 Aug 2028Extended 4 mo0
Ocean PearlGargi DevelopersP9900007976526 Mar 202531 Dec 202630 Apr 2027Extended 4 mo0
Rashmi AsthaRashmi Shelter Private LimitedP9900007978626 Mar 202531 Dec 203030 Apr 2031Extended 4 mo0
Shree Gayatri ChslApna Ghar DevelopersP9900007968420 Mar 202531 Mar 202831 Jul 2028Extended 4 mo0
Park View Co Op Housing Society LimitedParkview Co Op Housing Society LimitedP9900007962617 Mar 202531 Dec 202730 Apr 2028Extended 4 mo0
Pearl ResidencyShree Ganesh ConstructionP990000794617 Mar 202531 Dec 202830 Apr 2029Extended 4 mo0
Redevelopment of Chinmay Co-operative Housing Society LtdNeom ConstructionP990000794887 Mar 202515 Jan 202715 May 2027Extended 4 mo0
Estquire Paradise Phase 2Estquire Projects Private LimitedP990000793823 Mar 202531 Dec 202830 Apr 2029Extended 4 mo0
Shree Krishna HeightsSudham Lifespaces LLPP99000079298, P9900007976028 Feb 202530 Jun 202830 Oct 2028Extended 4 mo0
Suraj EmpireOm ConstructionP9900007927725 Feb 202531 Dec 202830 Apr 2029Extended 4 mo0
Agnes PrideAgnes DevelopersP9900007922517 Feb 202531 Dec 202730 Apr 2028Extended 4 mo0
Suraj EmpireS S Builders And DevelopersP9900007918714 Feb 202531 Dec 202831 Dec 2028Not yet due0
Svasa ResidencySvasa DevelopersP990000790623 Feb 202531 Dec 202830 Apr 2029Extended 4 mo0
Mangalam AvenueRamesh Tejabhai ThumarP9900007899731 Jan 202531 Dec 203130 Apr 2032Extended 4 mo0
Parth DevgangaParth Residency And Infra LLPP9900007902531 Jan 202531 Dec 202730 Apr 2028Extended 4 mo0
VanashreeTrimiti Constructions Private LimitedP9900007904131 Jan 202531 Dec 203230 Apr 2033Extended 4 mo0
Redevelopment of Datta Krupa CHS Ltd.Ramkala InfrastructureP9900007898528 Jan 202531 Jul 202730 Nov 2027Extended 4 mo0
Amit Palace CHSLSai Siddhi Builders And DevelopersP9900007891520 Jan 202530 Jul 202930 Nov 2029Extended 4 mo0
Prachiti HeightPrachiti EntereprsiesP9900007891720 Jan 202531 May 202830 Sep 2028Extended 4 mo0

Other localities in Vasai

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Shantee Realty And Life Space6 projects
  2. M/s AMEYA BUILDERS & PROPERTY DEVELOPERS5 projects
  3. Shantee Housing5 projects
  4. Brijesh Satish Dattani4 projects
  5. Jsb Homemakers Private Limited4 projects
  6. Kawali Builders4 projects
  7. Viva Winner Venture Relators LLP4 projects
  8. Ajmera Developers3 projects
  9. Bachraj Developers3 projects
  10. Cosmos Prime Projects Ltd3 projects
Data through17 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology