Vijay Homes
Deedo IDDP-PAL-X76ACompletion was pushed back 3 years, to Mar 2027; no MahaRERA orders on record; 22% of its units are booked.
Vasai, Maharashtra 401209 · by George Elias Gonsalves
Buying a flat here?
See every deed registered on it.
Completion was pushed back 3 years, to Mar 2027
- This projectRegistered 27 Mar 2020, completion promised 30 Mar 2024, revised to 31 Mar 2027.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP99000025250
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000025250 | 27 Mar 2020 | 30 Mar 2024 | 31 Mar 2027 | George Elias Gonsalves | Project page |
Documents80
3 documents held by Deedo, 77 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN CardPAN CARD GEORGE.pdf · uploaded 20 Mar 2020Source
- Other – FinanceSelf Declaration for Nil QPR.pdf · uploaded 12 May 2025Source
- Other – FinanceReason for seeking Extension.pdf · uploaded 16 May 2025Source
- Other – FinanceCPMPERT_STATUS OF WORK.pdf · uploaded 16 May 2025Source
- Other – FinanceDetialed Justification for 2years extension_Vijay Homes_Signed.pdf · uploaded 28 May 2025Source
Show all 80 documentsShow fewer documents
Legal
Migrated
- 1 Copy of the legal title reportTITLE REPORT.pdf · uploaded 4 Mar 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE (1)(1).pdf · uploaded 4 Mar 2020Source
- 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 6 Mar 2020Source
- 1 Details of encumbrancesENCUMBRANCES DECLARAION.pdf · uploaded 19 Mar 2020Source
- 1 Copy of Layout Approval (in case of layout)layout.pdf · uploaded 19 Mar 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentlayout.pdf · uploaded 19 Mar 2020Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 19 Mar 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_CA CERT.pdf · uploaded 19 Mar 2020Source
- 2 Proforma of Allotment letterAGMT FOR SALE_1.pdf · uploaded 19 Mar 2020Source
- 3 Proforma of Allotment letterAGMT FOR SALE_2.pdf · uploaded 19 Mar 2020Source
- 4 Proforma of Allotment letterAGMT FOR SALE_3.pdf · uploaded 19 Mar 2020Source
- 1 PAN CardPAN CARD GEORGE.pdf · uploaded 20 Mar 2020Source
- 2 Commencement Certificates / NA Order for plotted developmentREVISED CC_compressed.pdf · uploaded 19 Jan 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH.pdf · uploaded 19 Jan 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENG.pdf · uploaded 19 Jan 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH.pdf · uploaded 29 Apr 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENG.pdf · uploaded 29 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)1920 rera vijay homes.pdf · uploaded 29 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)vijay homes 2021.pdf · uploaded 29 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)2122 vijay homes.pdf · uploaded 29 Apr 2023Source
- 1 Declaration about Commencement CertificateCC DECL VH.pdf · uploaded 14 Aug 2024Source
- 2 Declaration about Commencement CertificateCC DECL VH.pdf · uploaded 14 Aug 2024Source
- 2 Declaration in FORM BAdobe Scan 8 Jun 2024 (2) (1)1.pdf · uploaded 14 Aug 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH CERT FORM 1 (1).pdf · uploaded 14 Aug 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG CERT1 (1).pdf · uploaded 14 Aug 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A 2122 VH.pdf · uploaded 14 Aug 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM-2A Vijay Homes (1).pdf · uploaded 14 Aug 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2A 2223 VH.pdf · uploaded 14 Aug 2024Source
- 1 Disclosure of sold/ booked inventoryBOOKED INVENTORY.pdf · uploaded 14 Aug 2024View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 VH.pdf · uploaded 14 Aug 2024Source
- 1 Declaration in FORM BAFFIDAVIT IN FORM B_VIJAY HOMES.pdf · uploaded 24 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_Sep 24 duo signed.pdf · uploaded 24 Apr 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_Dec 24 duo signed.pdf · uploaded 24 Apr 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_Mar 25 duo signed.pdf · uploaded 24 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_Sep 2024 duo signed.pdf · uploaded 24 Apr 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_Dec 24 duo signed.pdf · uploaded 24 Apr 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_Mar 2025 duo signed.pdf · uploaded 24 Apr 2025Source
- 1 Other – TechnicalFORM 2A_FY24 25 duo signed.pdf · uploaded 24 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A_FY 23 24 duo signed.pdf · uploaded 24 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_STRA_VIJAY HOMES-SIGNED.pdf · uploaded 28 Apr 2025Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD DECLARATION_VIJAY HOMES_31 03 25.pdf · uploaded 28 Apr 2025View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5_VH_FY23 24(SIGNED).pdf · uploaded 28 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Self Declaration for Nil QPR.pdf · uploaded 12 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Self Declaration for Nil QPR.pdf · uploaded 12 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Self Declaration for Nil QPR.pdf · uploaded 12 May 2025Source
- 1 Other – FinanceSelf Declaration for Nil QPR.pdf · uploaded 12 May 2025Source
- 1 Other – FinanceReason for seeking Extension.pdf · uploaded 16 May 2025Source
- 2 Other – FinanceCPMPERT_STATUS OF WORK.pdf · uploaded 16 May 2025Source
- 1 Other – TechnicalReason for seeking Extension.pdf · uploaded 20 May 2025Source
- 2 Other – TechnicalCPMPERT_STATUS OF WORK.pdf · uploaded 20 May 2025Source
- 1 Other – FinanceDetialed Justification for 2years extension_Vijay Homes_Signed.pdf · uploaded 28 May 2025Source
- 1 Other – TechnicalDetialed Justification for 2years extension_Vijay Homes_Signed.pdf · uploaded 28 May 2025Source
Technical
- Documentlayout.pdf · uploaded 19 Mar 2020Source
- Documentlayout.pdf · uploaded 19 Mar 2020Source
- Other – TechnicalFORM 2A_FY24 25 duo signed.pdf · uploaded 24 Apr 2025Source
- Other – TechnicalReason for seeking Extension.pdf · uploaded 20 May 2025Source
- Other – TechnicalCPMPERT_STATUS OF WORK.pdf · uploaded 20 May 2025Source
- Other – TechnicalDetialed Justification for 2years extension_Vijay Homes_Signed.pdf · uploaded 28 May 2025Source
Technical (Architect)
- DocumentARCH CERT FORM 1 (1).pdf · uploaded 14 Aug 2024Source
- DocumentFORM 1_Sep 24 duo signed.pdf · uploaded 24 Apr 2025Source
- DocumentFORM 1_Dec 24 duo signed.pdf · uploaded 24 Apr 2025Source
- DocumentFORM 1_Mar 25 duo signed.pdf · uploaded 24 Apr 2025Source
- DocumentSelf Declaration for Nil QPR.pdf · uploaded 12 May 2025Source
Technical (Engineer)
- DocumentENG CERT1 (1).pdf · uploaded 14 Aug 2024Source
- DocumentFORM 2_Sep 2024 duo signed.pdf · uploaded 24 Apr 2025Source
- DocumentFORM 2_Dec 24 duo signed.pdf · uploaded 24 Apr 2025Source
- DocumentFORM 2_Mar 2025 duo signed.pdf · uploaded 24 Apr 2025Source
- DocumentSelf Declaration for Nil QPR.pdf · uploaded 12 May 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, Shop32 units in all
- Address
- 219, 220, 0, 0PIN 401209
- Land area for this project
- 820 sq m (8,829 sq ft)
- Permissible built-up area
- 820 sq m (8,829 sq ft)
- Sanctioned built-up area
- 820 sq m (8,829 sq ft)
- Designated bank account
- 19
- Developed in phases
- No
Land as published on MahaRERA's project page
219,220
Boundaries
- North
- 0
- South
- 0
- East
- 0
- West
- 0
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking32 units
7 of 32 units booked (22%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 34.38 sq m · 370 sq ft | 3 | 0 |
| 1BHK | 35.77 sq m · 385 sq ft | 3 | 0 |
| 1BHK | 36.24 sq m · 390 sq ft | 3 | 0 |
| 1RK | 17.93 sq m · 193 sq ft | 3 | 0 |
| 1RK | 20.07 sq m · 216 sq ft | 3 | 0 |
| 1RK | 21.65 sq m · 233 sq ft | 6 | 6 |
| 1RK | 23.69 sq m · 255 sq ft | 3 | 1 |
| 1RK | 27.59 sq m · 297 sq ft | 3 | 0 |
Show all 13 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 8.55 sq m · 92 sq ft | 1 | 0 |
| Shop | 8.64 sq m · 93 sq ft | 1 | 0 |
| Shop | 8.92 sq m · 96 sq ft | 1 | 0 |
| Shop | 9.48 sq m · 102 sq ft | 1 | 0 |
| Shop | 10.87 sq m · 117 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | En Con | — |
| Chartered accountant | Jpm And Associates | — |
| Chartered accountant | Manish Shinde And Associates | — |
| Chartered accountant | S B Jain And Associates | — |
| Engineer | En Con | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Vasai
- Hira Apartment Co Operative Housing SocietyRERA PM1240002602741
- New Gokul Co-Operative Housing Society LtdRERA PR1240002602746
- Yashwant PrideRERA PR1240002602681
- Dixit EnclavesRERA PR1240002602613
- New Raj Palace ChslRERA PR1240002602622
- Jas ApartmentRERA PR1240002602505
- Dhruv TaraRERA PM1240002602470
- Abhinandan TowerRERA PR1240002602389
All 1,568 projects in Vasai · Compare Vijay Homes with another project