Veer
Completion date passedUmroli, Palghar 401404 |Promoter: Veer Global Infraconstruction Limited
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 2 years
P99000007946The latest completion date on record passed 4 years and 10 months ago.
- Registered
- 18 Aug 2017
- Promised
- 31 Dec 2019
- Revised
- 30 Dec 2021
Completion promised for 30 Jun 2023
P99000028513The latest completion date on record passed 3 years and 4 months ago.
- Registered
- 8 Mar 2021
- Promised
- 30 Jun 2023
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000007946 | 18 Aug 2017 | 31 Dec 2019 | 30 Dec 2021 | Veer Global Infraconstruction Limited | Project page |
| P99000028513 | 8 Mar 2021 | 30 Jun 2023 | — | Veer Global Infraconstruction Limited | Project page |
Documents
3 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Umroli
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.