Deedo IDDP-PAL-ZQ4MCompletion was pushed back 4 months, to Feb 2029; no MahaRERA orders on record; 0% of its units are booked.
Tivari, Palghar 401208 · by Savera Reality
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Feb 2029
- This projectRegistered 14 Nov 2024, completion promised 31 Oct 2028, revised to 28 Feb 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP99000077972
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000077972 | 14 Nov 2024 | 31 Oct 2028 | 28 Feb 2029 | Savera Reality | Project page |
Documents51
1 document held by Deedo, 50 filings listed on MahaRERA's project page
Finance
Legal
Show all 51 documentsShow fewer documents
Migrated
- 2 a Details of encumbrances concerned to FinanceEncumbrance- legal.pdf · uploaded 24 Oct 2024Source
- 1 Copy of Layout Approval (in case of layout)Plan1.pdf · uploaded 24 Oct 2024Source
- 1 Proforma of Allotment letterAL_ Savera Heights_ Savera Realty_23102024 (1).pdf · uploaded 24 Oct 2024Source
- 1 Declaration in FORM BFOrm B (Promoter).pdf · uploaded 24 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)ilovepdf_merged.pdf · uploaded 24 Oct 2024Source
- 1 Commencement Certificates / NA Order for plotted development1 Commencement Certificates _ NA Order for plotted development.pdf · uploaded 24 Oct 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan1 (1).pdf · uploaded 24 Oct 2024Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 24 Oct 2024Source
- 1 CERSAI detailsCersai Declaration.pdf · uploaded 24 Oct 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A.pdf · uploaded 24 Oct 2024Source
- 1 Deviation Report with respect to Allotment letter1 Deviation Report with respect to Allotment letter.pdf · uploaded 24 Oct 2024Source
- 1 b Details of encumbrances concerned to LegalEncumbrance- Finance.pdf · uploaded 24 Oct 2024Source
- 2 b Details of encumbrances concerned to LegalEncumbrance- legal.pdf · uploaded 24 Oct 2024Source
- 1 Other – FinanceDeclaration on landowner.pdf · uploaded 24 Oct 2024Source
- 1 Other – TechnicalORDER NO50.pdf · uploaded 24 Oct 2024Source
- 1 Deviation Report with respect to model copy of Agreement1 Deviation Report with respect to model copy of Agreement.pdf · uploaded 24 Oct 2024Source
- 1 Proforma of Agreement for saleAFS_ Savera Heights_ Savera Realty_23102024 (1).pdf · uploaded 24 Oct 2024Source
- 1 Disclosure of Interest in Other Real Estate Organizationsoutput (2).pdf · uploaded 24 Oct 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B.pdf · uploaded 24 Oct 2024Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure.pdf · uploaded 24 Oct 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentCC Verification mail-Savera Heights.pdf · uploaded 8 Nov 2024Source
- Form 1FORM 1.pdf · uploaded 20 Jul 2025Source
- Form 2FORM 2.pdf · uploaded 20 Jul 2025Source
- Form 3FORM 3.pdf · uploaded 20 Jul 2025Source
- Disclosure of Sold and Booked InventorySAVERA SOLD UNSOLD.pdf · uploaded 20 Jul 2025Source
- Self-declaration of Quarterly ProgressSELF DECLARATION.pdf · uploaded 20 Jul 2025Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 2form 2 merged.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 3FORM 3 SIGNED.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 8 Jun 2026Source
- Withdrawal Update Form 2form 2 merged.pdf · uploaded 8 Jun 2026Source
- Withdrawal Update Form 3FORM 3 SIGNED.pdf · uploaded 8 Jun 2026Source
- Withdrawal Update Form 1form 1 q2.pdf · uploaded 15 Jun 2026Source
- Withdrawal Update Form 2RERA_FORM2_MERGED_A_B_WING.pdf · uploaded 15 Jun 2026Source
- Withdrawal Update Form 3FORM 3 CA SIGNED_compressed.pdf · uploaded 15 Jun 2026Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 20 Jun 2026Source
- Withdrawal Update Form 2form 2 merged.pdf · uploaded 20 Jun 2026Source
- Withdrawal Update Form 3FORM 3 Q3.pdf · uploaded 20 Jun 2026Source
Technical
Technical (Architect)
- DocumentFORM 1.pdf · uploaded 20 Jun 2026Source
Technical (Engineer)
- Documentform 2 merged.pdf · uploaded 20 Jun 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Survey No.103 Hissa No.3
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- Landowner 1 BHK, Landowner 2 BHK, Landowner Shop, Sale 1 BHK, Sale 2 BHK, Sale Shop135 units in all
- Address
- Survey No.-103 Hissa No.-3, H No-3, TivariPIN 401208
- Village
- Tivari, Vasai taluka
- Land area for this project
- 2,730 sq m (29,385 sq ft)
- Permissible built-up area
- 8,928 sq m (96,098 sq ft)
- Sanctioned built-up area
- 6,928 sq m (74,570 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 85
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Survey No.-103 Hissa No.-3
Boundaries
- North
- Open Plot
- South
- Open Plot
- East
- Open Plot
- West
- Open Plot
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking135 units
0 of 135 units booked (0%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A Wing | Landowner 1 BHK | 35.88 sq m · 386 sq ft | 1 | 0 |
| A Wing | Landowner 1 BHK | 36.06 sq m · 388 sq ft | 7 | 0 |
| A Wing | Landowner 2 BHK | 43.61 sq m · 469 sq ft | 7 | 0 |
| A Wing | Landowner 2 BHK | 49.4 sq m · 532 sq ft | 7 | 0 |
| A Wing | Landowner Shop | 11.5 sq m · 124 sq ft | 1 | 0 |
| A Wing | Landowner Shop | 13.89 sq m · 150 sq ft | 1 | 0 |
| A Wing | Landowner Shop | 14.71 sq m · 158 sq ft | 1 | 0 |
| A Wing | Sale 1 BHK | 32.99 sq m · 355 sq ft | 1 | 0 |
Show all 29 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A Wing | Sale 1 BHK | 35.29 sq m · 380 sq ft | 7 | 0 |
| A Wing | Sale 1 BHK | 35.88 sq m · 386 sq ft | 14 | 0 |
| A Wing | Sale 2 BHK | 42.35 sq m · 456 sq ft | 7 | 0 |
| A Wing | Sale 2 BHK | 47.47 sq m · 511 sq ft | 14 | 0 |
| A Wing | Sale Shop | 9.76 sq m · 105 sq ft | 1 | 0 |
| A Wing | Sale Shop | 10.6 sq m · 114 sq ft | 1 | 0 |
| A Wing | Sale Shop | 11.87 sq m · 128 sq ft | 1 | 0 |
| A Wing | Sale Shop | 13.08 sq m · 141 sq ft | 1 | 0 |
| A Wing | Sale Shop | 13.11 sq m · 141 sq ft | 1 | 0 |
| A Wing | Sale Shop | 15.51 sq m · 167 sq ft | 1 | 0 |
| B Wing | Landowner 1 BHK | 35.88 sq m · 386 sq ft | 21 | 0 |
| B Wing | Landowner Shop | 16.19 sq m · 174 sq ft | 1 | 0 |
| B Wing | Sale 1 BHK | 34.19 sq m · 368 sq ft | 7 | 0 |
| B Wing | Sale 1 BHK | 35.63 sq m · 384 sq ft | 7 | 0 |
| B Wing | Sale 1 BHK | 35.88 sq m · 386 sq ft | 7 | 0 |
| B Wing | Sale 1 BHK | 42.07 sq m · 453 sq ft | 1 | 0 |
| B Wing | Sale 2 BHK | 47.1 sq m · 507 sq ft | 7 | 0 |
| B Wing | Sale 2 BHK | 48.76 sq m · 525 sq ft | 7 | 0 |
| B Wing | Sale Shop | 8.7 sq m · 94 sq ft | 1 | 0 |
| B Wing | Sale Shop | 9.78 sq m · 105 sq ft | 1 | 0 |
| B Wing | Sale Shop | 11.14 sq m · 120 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Shape Consultants | — |
| Chartered accountant | Chandan Kumar Choudhary | — |
| Chartered accountant | M/s. Pratiksha Tulshyan & Associates | — |
| Chartered accountant | Sanjeev Rajaram Chaudhary | — |
| Engineer | Conar Chindia | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Tivari
- Rajshree ComplexRERA PR1240002500713
- Sunteck OneWorld -Tower 1RERA P99000080341
- Hill Crest ResidencyRERA P99000078975
- ShivneriRERA P99000077793
- Global Arena - Phase IIRERA P99000053168
- Sai Enclave Building No.2RERA P99000035122
- Sunteck ONEWorld 3, Tivri, Naigaon EastRERA P99000033099
- Sunteck ONEWorldRERA P99000032834
All 23 projects in Tivari · Compare Savera Heights with another project