Residential / Group Housing · 2 buildings · 50 unitsRERA P99000026369

Ramashray

Deedo IDDP-PAL-WBAX

MahaRERA shows it completed, after its date was pushed back 11 months; no MahaRERA orders on record; 78% of its units are booked.

Palghar 401404 · by Pariksheet Ramkrishna Dandekar

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 11 mo extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales78% booked39 of 50 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 11 months

  • This projectRegistered 11 Sep 2020, completion promised 30 Jun 2022, revised to 31 May 2023.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000026369
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900002636911 Sep 202030 Jun 202231 May 2023Pariksheet Ramkrishna DandekarProject page
Documents56

3 documents held by Deedo, 53 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPRD Pan Card.pdf · uploaded 4 Sep 2020Source

Legal

  • Declaration Form BAffidavit RERA_compressed.pdf · uploaded 4 Sep 2020Source
  • Legal Title reportTitle Investigation Report 1.pdf · uploaded 8 Sep 2020Source
  • Legal Title reportTitle Investigation Report 2.pdf · uploaded 8 Sep 2020Source

Migrated

  • 1 PAN CardPRD Pan Card.pdf · uploaded 4 Sep 2020Source
Show all 56 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesEncumbrance.pdf · uploaded 4 Sep 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC Page 1.pdf · uploaded 4 Sep 2020Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC Page 2.pdf · uploaded 4 Sep 2020Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC Page 3.pdf · uploaded 4 Sep 2020Source
  • 4 Commencement Certificates / NA Order for plotted developmentCC Page 4.pdf · uploaded 4 Sep 2020Source
  • 1 Declaration in FORM BAffidavit RERA_compressed.pdf · uploaded 4 Sep 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects Certificate.pdf · uploaded 4 Sep 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 4 Sep 2020Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 4 Sep 2020Source
  • 2 Proforma of Allotment letterAggrement for Sale.pdf · uploaded 4 Sep 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 5 Sep 2020Source
  • 1 Copy of Layout Approval (in case of layout)Approve Plan 1.pdf · uploaded 7 Sep 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentApprove Plan 1.pdf · uploaded 7 Sep 2020Source
  • 2 Building Plan Approval / NA Order for plotted developmentApprove Plan 2.pdf · uploaded 7 Sep 2020Source
  • 1 Copy of the legal title reportTitle Investigation Report 1.pdf · uploaded 8 Sep 2020Source
  • 2 Copy of the legal title reportTitle Investigation Report 2.pdf · uploaded 8 Sep 2020Source
  • 1 Disclosure of sold/ booked inventorySold Unsold details.pdf · uploaded 27 Oct 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 March .pdf · uploaded 27 Oct 2021Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 8 Jun 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Table A and B.pdf · uploaded 8 Jun 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A Sep 2020.pdf · uploaded 8 Jun 2022Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A April 2021.pdf · uploaded 8 Jun 2022Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A Jan 2021.pdf · uploaded 8 Jun 2022Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A July2021.pdf · uploaded 8 Jun 2022Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A Oct 2021.pdf · uploaded 8 Jun 2022Source
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A Jan 2022.pdf · uploaded 8 Jun 2022Source
  • 7 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A April 2022.pdf · uploaded 8 Jun 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A Sep 2020.pdf · uploaded 8 Jun 2022Source
  • 2 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 8 Jun 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 24 Jan 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 24 Jan 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 24 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineer certificate Form 2A July 2022.pdf · uploaded 2 Feb 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineer certificate Form 2A October 2022.pdf · uploaded 2 Feb 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineer certificate Form 2A January 2023.pdf · uploaded 2 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 2021 2022.pdf · uploaded 2 Feb 2023Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentArcitect Complition1.pdf · uploaded 2 Feb 2023Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Certificate .pdf · uploaded 2 Feb 2023Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupation Certificate.pdf · uploaded 10 Apr 2023Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A March 2023.pdf · uploaded 26 Apr 2023Source
  • 3 Disclosure of sold/ booked inventorySold Unsold inventory.pdf · uploaded 26 Apr 2023View
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 31 March 23.pdf · uploaded 26 Apr 2023Source
  • 5 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 9 May 2023Source

Technical

  • DocumentApprove Plan 1.pdf · uploaded 7 Sep 2020Source
  • DocumentApprove Plan 1.pdf · uploaded 7 Sep 2020Source
  • DocumentApprove Plan 2.pdf · uploaded 7 Sep 2020Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 24 Jan 2023Source

Technical (Engineer)

  • DocumentFORM 2.pdf · uploaded 24 Jan 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 94/A/2/1 95/A/1, 94A21 95A1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, 3BHK, Office space, Shop50 units in all
Address
94A21 95A1, Bhausaheb Dandekar Marg, Near ICICI BankPIN 401404
Village
Palghar, Palghar taluka
Land area for this project
4,160 sq m (44,778 sq ft)
Permissible built-up area
4,324 sq m (46,543 sq ft)
Sanctioned built-up area
4,324 sq m (46,543 sq ft)
Recreational open space
417 sq m (4,486 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

94/A/2/1 95/A/194A21 95A1

Land as published on MahaRERA's project page

94A21 95A1

Boundaries

North
Survey No 95 A Survey No 94 A 2
South
Suvrey No 94 B
East
Survey No 95 A 1
West
S No 94 A 2 S No 93 A 2 S No 94 A 1 S no 94 A 3

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking50 units

39 of 50 units booked (78%), as the promoter reported to MahaRERA

1BHK · 2 units2BHK · 24 units3BHK · 20 unitsOffice space · 2 unitsShop · 2 units
TypeCarpet areaUnitsBooked
1BHK41.17 sq m · 443 sq ft20
2BHK60.89 sq m · 655 sq ft1210
2BHK63.61 sq m · 685 sq ft1210
3BHK82.37 sq m · 887 sq ft108
3BHK82.55 sq m · 889 sq ft109
Office space104.77 sq m · 1,128 sq ft22
Shop103.96 sq m · 1,119 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMahendra Kale—
Chartered accountantCA Sunil Vaidya—
EngineerN M Rege—
OtherShree Sai Contractors and Engineers—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Palghar

All 327 projects in Palghar · Compare Ramashray with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology