Others · 1 building · 32 unitsRERA P99000079433

Parth Plaza

Deedo IDDP-PAL-4R0Y

Completion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 0% of its units are booked.

Makane, Palghar 401102 · by Zinal Builders And Developers

DeliveryExtended 4 moPromised Dec 2027 · now due Apr 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 32 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2028

  • This projectRegistered 6 Mar 2025, completion promised 31 Dec 2027, revised to 30 Apr 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000079433
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P990000794336 Mar 202531 Dec 202730 Apr 2028Zinal Builders And DevelopersProject page
Documents65

1 document held by Deedo, 64 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardcompany pan card.pdf · uploaded 23 Jan 2025Source

Legal

  • Other – LegalGmail - CC Issued by collector Palghar at village Makne ser no 178-4plot no 2and 4 Order date 17Dec2024.pdf · uploaded 4 Feb 2025Source
  • Other – LegalPARTH PLAZA CLARIFICATION OF CC.pdf · uploaded 4 Feb 2025Source
  • Other – Legalpartnership deed_compressed.pdf · uploaded 4 Feb 2025Source
  • Legal Title reportPARTH PLAZA LEGAL TITLE REPORT.pdf · uploaded 4 Feb 2025Source
  • Other – LegalConveyance parth plaza_compressed_compressed.pdf · uploaded 14 Feb 2025Source
  • Other – Legal7 12 EXTRAC PARTH PLAZA.pdf · uploaded 14 Feb 2025Source
Show all 65 documentsShow fewer documents

Legal

  • Declaration Form BPARTH PLAZA FORM B PROMOTER REVISED.pdf · uploaded 3 Mar 2025Source

Migrated

  • 1 PAN Cardcompany pan card.pdf · uploaded 23 Jan 2025Source
  • 1 Copy of Layout Approval (in case of layout)PARTH PLAZA BLUE PRINT AND LAYOUT PLAN.PDF · uploaded 23 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 23 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 23 Jan 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentPARTH PLAZA BLUE PRINT AND LAYOUT PLAN.PDF · uploaded 23 Jan 2025Source
  • 1 Copy of the legal title reportPARTH PLAZA LEGAL TITLE REPORT.pdf · uploaded 4 Feb 2025Source
  • 1 a Details of encumbrances concerned to FinancePARTH PLAZA NO ENCUMBRANCE TO FINANCE.pdf · uploaded 4 Feb 2025Source
  • 2 a Details of encumbrances concerned to FinancePARTH PLAZA NO ENCUMBRANCE TO LEGAL.pdf · uploaded 4 Feb 2025Source
  • 1 Proforma of Allotment letterPARTH PLAZA ALLOTEMENT LETTER_compressed.pdf · uploaded 4 Feb 2025Source
  • 2 Other – LegalPARTH PLAZA CLARIFICATION OF CC.pdf · uploaded 4 Feb 2025Source
  • 1 Other – LegalGmail - CC Issued by collector Palghar at village Makne ser no 178-4plot no 2and 4 Order date 17Dec2024.pdf · uploaded 4 Feb 2025Source
  • 3 Other – Legalpartnership deed_compressed.pdf · uploaded 4 Feb 2025Source
  • 1 CERSAI detailsPARTH PLAZA CERSAI REPORT.pdf · uploaded 4 Feb 2025Source
  • 1 Deviation Report with respect to Allotment letterPARTH PLAZA NO DEVIATION FOR ALLOTEMENT.pdf · uploaded 4 Feb 2025Source
  • 1 b Details of encumbrances concerned to LegalPARTH PLAZA NO ENCUMBRANCE TO FINANCE.pdf · uploaded 4 Feb 2025Source
  • 2 b Details of encumbrances concerned to LegalPARTH PLAZA NO ENCUMBRANCE TO LEGAL.pdf · uploaded 4 Feb 2025Source
  • 1 Deviation Report with respect to model copy of AgreementPARTH PLAZA NO DEVIATION FOR AGREEMENT FOR SALE.pdf · uploaded 4 Feb 2025Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsdisclosure of interest - aparna kawli.pdf · uploaded 4 Feb 2025Source
  • 2 Disclosure of Interest in Other Real Estate Organizationsdisclosure of interest - dhanesh thakur.pdf · uploaded 4 Feb 2025Source
  • 3 Disclosure of Interest in Other Real Estate Organizationsdisclosure of interest - Nilesh thumar.pdf · uploaded 4 Feb 2025Source
  • 4 Disclosure of Interest in Other Real Estate Organizationsdisclosure of interest pradnya thumar.pdf · uploaded 4 Feb 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)format b bank.pdf · uploaded 4 Feb 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectPARTH PLAZA SECURE N UNSECURED AVAILED.pdf · uploaded 4 Feb 2025Source
  • 1 Declaration about Commencement CertificatePARTH PLAZA DECLARTAION ABOUT CC.pdf · uploaded 5 Feb 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC Issued by collector Palghar at village Makne ser no 178-4plot no 2and 4 Order date 17Dec2024.pdf · uploaded 6 Feb 2025Source
  • 1 Other – TechnicalDECLARATION CUM UNDERTAKING.pdf · uploaded 6 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)PARTH PLAZA FORM 3.pdf · uploaded 14 Feb 2025Source
  • 5 Other – Legal7 12 EXTRAC PARTH PLAZA.pdf · uploaded 14 Feb 2025Source
  • 4 Other – LegalConveyance parth plaza_compressed_compressed.pdf · uploaded 14 Feb 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)PARTH PLAZA FORMAT A BANK.pdf · uploaded 14 Feb 2025Source
  • 1 Proforma of Agreement for saleagreement for sale.pdf · uploaded 14 Feb 2025Source
  • 1 Declaration in FORM BPARTH PLAZA FORM B PROMOTER REVISED.pdf · uploaded 3 Mar 2025Source
  • Form 1FORM 1.pdf · uploaded 29 Dec 2025Source
  • Form 2FORM 2.pdf · uploaded 29 Dec 2025Source
  • Form 3FORM 3.pdf · uploaded 29 Dec 2025Source
  • Disclosure of Sold and Booked Inventoryparth plaza sold unsold 31032025.pdf · uploaded 29 Dec 2025Source
  • Withdrawal Update Form 1parth form 1 300625.pdf · uploaded 29 Dec 2025Source
  • Withdrawal Update Form 1parth form 1 300625.pdf · uploaded 29 Dec 2025Source
  • Withdrawal Update Form 1parth plaza form 1 300925.pdf · uploaded 29 Dec 2025Source
  • Withdrawal Update Form 2parth plaza form 2.pdf · uploaded 29 Dec 2025Source
  • Withdrawal Update Form 2parth plaza form 2.pdf · uploaded 29 Dec 2025Source
  • Withdrawal Update Form 2parth plaza form 2 30092025.pdf · uploaded 29 Dec 2025Source
  • Withdrawal Update Form 3PARTH PLAZA FORM 3.pdf · uploaded 29 Dec 2025Source
  • Withdrawal Update Form 3parth plaza form 3 300625.pdf · uploaded 29 Dec 2025Source
  • Withdrawal Update Form 3parthplazaform 3 300925.pdf · uploaded 29 Dec 2025Source
  • Withdrawal Update Form 1parthplaza form 1 31122025.pdf · uploaded 11 Mar 2026Source
  • Withdrawal Update Form 220260311-WA0010__merged.pdf · uploaded 11 Mar 2026Source
  • Withdrawal Update Form 3parthplaza form 3 311225.pdf · uploaded 11 Mar 2026Source
  • Withdrawal Update Form 1parth plaza form 1.pdf · uploaded 5 Jun 2026Source
  • Withdrawal Update Form 2form 2 parth plaza march.pdf · uploaded 5 Jun 2026Source
  • Withdrawal Update Form 3Parth Plaza Form3 31-3-2026.pdf · uploaded 5 Jun 2026Source

Technical

  • DocumentPARTH PLAZA BLUE PRINT AND LAYOUT PLAN.PDF · uploaded 23 Jan 2025Source
  • DocumentPARTH PLAZA BLUE PRINT AND LAYOUT PLAN.PDF · uploaded 23 Jan 2025Source
  • Other – TechnicalDECLARATION CUM UNDERTAKING.pdf · uploaded 6 Feb 2025Source

Technical (Architect)

  • Documentparth plaza form 1.pdf · uploaded 5 Jun 2026Source

Technical (Engineer)

  • Documentform 2 parth plaza march.pdf · uploaded 5 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 4, NEW GUT NO 178/4

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop32 units in all
Address
Old Survey No 550, New Gut No 178/4, Plot No 2 & 4, Tembhikhodave, Saphale WestPIN 401102
Village
Makane, Palghar taluka
Land area for this project
766 sq m (8,244 sq ft)
Permissible built-up area
1,719 sq m (18,501 sq ft)
Sanctioned built-up area
1,719 sq m (18,501 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
19
Developed in phases
No

Survey, CTS, gat or plot numbers

4NEW GUT NO 178/4OLD SURVEY NO 550PLOT NO 2

Land as published on MahaRERA's project page

OLD SURVEY NO 550,NEW GUT NO 178/4,PLOT NO 2 & 4

Boundaries

North
Road
South
Open Plot
East
Chawl
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking32 units

0 of 32 units booked (0%), as the promoter reported to MahaRERA

1BHK · 12 units2BHK · 12 unitsShop · 8 units
TypeCarpet areaUnitsBooked
1BHK24.8 sq m · 267 sq ft60
1BHK26.79 sq m · 288 sq ft60
2BHK33.66 sq m · 362 sq ft60
2BHK34.61 sq m · 373 sq ft60
Shop16.82 sq m · 181 sq ft10
Shop25.01 sq m · 269 sq ft10
Shop25.61 sq m · 276 sq ft10
Shop29.25 sq m · 315 sq ft10
Show all 12 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop36.46 sq m · 392 sq ft10
Shop37.37 sq m · 402 sq ft10
Shop45.64 sq m · 491 sq ft10
Shop46 sq m · 495 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRoshan Patil & Associates—
Chartered accountantP P Barapatre & Co—
EngineerShilplekha Associates—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Makane

All 86 projects in Makane · Compare Parth Plaza with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology