Omkar Vastu Complex
Deedo IDDP-PAL-3MGRCompletion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.
Makane, Palghar 401102 · by Omkar Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 23 Oct 2021, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
4 buildings
Open a building to see every flat, floor by floor.
- Building No 16 floors · 29 units0% booked
- Building No 26 floors · 44 units0% booked
- Building No 36 floors · 45 units0% booked
- Building No 46 floors · 23 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP99000031421
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000031421 | 23 Oct 2021 | 31 Dec 2026 | 30 Apr 2027 | Omkar Developers | Project page |
Documents106
1 document held by Deedo, 105 filings listed on MahaRERA's project page
Finance
- PAN CardPAN.pdf · uploaded 9 Oct 2021Source
Legal
Show all 106 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)Building layout Plan.pdf · uploaded 9 Oct 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentPlan.pdf · uploaded 9 Oct 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 9 Oct 2021Source
- 2 Commencement Certificates / NA Order for plotted developmentNA order.pdf · uploaded 9 Oct 2021Source
- 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 9 Oct 2021Source
- 1 Declaration in FORM BForm B - promoter.pdf · uploaded 9 Oct 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 9 Oct 2021Source
- 1 Proforma of Allotment letterDRAFT Agreement.pdf · uploaded 9 Oct 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Report.pdf · uploaded 10 Oct 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 CA Certificate- Final 03-10-2021- Print.pdf · uploaded 10 Oct 2021Source
- 1 Other7-12 Extract.pdf · uploaded 10 Oct 2021Source
- Form 1form 1 31032023.pdf · uploaded 7 Aug 2025Source
- Form 2form 2 31032023.pdf · uploaded 7 Aug 2025Source
- Form 3form 3 31032023.pdf · uploaded 7 Aug 2025Source
- Disclosure of Sold and Booked Inventory31032023.pdf · uploaded 7 Aug 2025Source
- Disclosure of Sold and Booked Inventory30062023.pdf · uploaded 7 Aug 2025Source
- Form 1form 1 30062023.pdf · uploaded 7 Aug 2025Source
- Form 2form 2 30062023.pdf · uploaded 7 Aug 2025Source
- Form 3form 3 30062023.pdf · uploaded 7 Aug 2025Source
- Form 3form 3 30092023.pdf · uploaded 7 Aug 2025Source
- Form 1form 1 30092023.pdf · uploaded 7 Aug 2025Source
- Form 2form 1 30092023.pdf · uploaded 7 Aug 2025Source
- Disclosure of Sold and Booked Inventory30092023.pdf · uploaded 7 Aug 2025Source
- Disclosure of Sold and Booked Inventory31122023.pdf · uploaded 7 Aug 2025Source
- Form 1form 1 31122023.pdf · uploaded 7 Aug 2025Source
- Form 2form 2 31122023.pdf · uploaded 7 Aug 2025Source
- Form 3form 3 31122023.pdf · uploaded 7 Aug 2025Source
- Form 3form 3 31032024.pdf · uploaded 7 Aug 2025Source
- Form 1form 1 31032024.pdf · uploaded 7 Aug 2025Source
- Form 2form 2 31032024.pdf · uploaded 7 Aug 2025Source
- Disclosure of Sold and Booked Inventory31032024.pdf · uploaded 7 Aug 2025Source
- Disclosure of Sold and Booked Inventory30062024.pdf · uploaded 7 Aug 2025Source
- Form 1form 1 30062024.pdf · uploaded 7 Aug 2025Source
- Form 2form 2 30062024.pdf · uploaded 7 Aug 2025Source
- Form 3form 3 30062024.pdf · uploaded 7 Aug 2025Source
- Form 1form 1 30092024.pdf · uploaded 7 Aug 2025Source
- Form 2form 2 30092024.pdf · uploaded 7 Aug 2025Source
- Form 3form 3 30092024.pdf · uploaded 7 Aug 2025Source
- Disclosure of Sold and Booked Inventory30092024.pdf · uploaded 7 Aug 2025Source
- Disclosure of Sold and Booked Inventory31122024.pdf · uploaded 7 Aug 2025Source
- Form 1form 1 31122024.pdf · uploaded 7 Aug 2025Source
- Form 2form 2 31122024.pdf · uploaded 7 Aug 2025Source
- Form 3form 3 31122024.pdf · uploaded 7 Aug 2025Source
- Form 1form 1 31032025.pdf · uploaded 7 Aug 2025Source
- Form 2form 2 31032025.pdf · uploaded 7 Aug 2025Source
- Form 3form 3 31032025.pdf · uploaded 7 Aug 2025Source
- Disclosure of Sold and Booked Inventory31032025.pdf · uploaded 7 Aug 2025Source
- Form 5 (FY 2021-2022)form 5 2021 2022.pdf · uploaded 7 Aug 2025Source
- Form 5 (FY 2022-2023)form 5 2022 23.pdf · uploaded 7 Aug 2025Source
- Form 5 (FY 2023-2024)form 5 2023 24.pdf · uploaded 7 Aug 2025Source
- Form 5 (FY 2024-2025)form 5 2024 25.pdf · uploaded 7 Aug 2025Source
- Form 1form 1 31122021.pdf · uploaded 8 Aug 2025Source
- Form 2form 2 31122021.pdf · uploaded 8 Aug 2025Source
- Form 3form 3 31122021.pdf · uploaded 8 Aug 2025Source
- Disclosure of Sold and Booked Inventory31122021.pdf · uploaded 8 Aug 2025Source
- Disclosure of Sold and Booked Inventory31032022.pdf · uploaded 8 Aug 2025Source
- Form 1form 1 31032022.pdf · uploaded 8 Aug 2025Source
- Form 2form 1 31032022.pdf · uploaded 8 Aug 2025Source
- Form 3form 3 31032022.pdf · uploaded 8 Aug 2025Source
- Form 3form 3 30062022.pdf · uploaded 8 Aug 2025Source
- Form 1form 1 30062022.pdf · uploaded 8 Aug 2025Source
- Form 2form 2 30062022.pdf · uploaded 8 Aug 2025Source
- Disclosure of Sold and Booked Inventory30062022.pdf · uploaded 8 Aug 2025Source
- Disclosure of Sold and Booked Inventory30092022.pdf · uploaded 8 Aug 2025Source
- Form 1form 1 30092022.pdf · uploaded 8 Aug 2025Source
- Form 2form 2 30092023.pdf · uploaded 8 Aug 2025Source
- Form 3form 3 30092022.pdf · uploaded 8 Aug 2025Source
- Disclosure of Sold and Booked Inventory31122022.pdf · uploaded 8 Aug 2025Source
- Form 1form 1 31122022.pdf · uploaded 8 Aug 2025Source
- Form 2form 2 31122022.pdf · uploaded 8 Aug 2025Source
- Form 3form 3 31122022.pdf · uploaded 8 Aug 2025Source
- Form 2A (FY 2021-2022)Omkar NEE 2021 2022.pdf · uploaded 8 Aug 2025Source
- Form 2A (FY 2022-2023)form2A 22 23.pdf · uploaded 8 Aug 2025Source
- Form 2A (FY 2023-2024)form 2A 2023 2024.pdf · uploaded 8 Aug 2025Source
- Form 2A (FY 2024-2025)Form 2A 2024 2025.pdf · uploaded 8 Aug 2025Source
- Withdrawal Update Form 1form 1 30062025.pdf · uploaded 28 Feb 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 28 Feb 2026Source
- Withdrawal Update Form 3FORM 3 CA Certificate- Final 03-10-2021- Print.pdf · uploaded 28 Feb 2026Source
- Withdrawal Update Form 1withdrawal form signed 30092025.pdf · uploaded 27 Mar 2026Source
- Withdrawal Update Form 2signedengineer certificate 30092025.pdf · uploaded 27 Mar 2026Source
- Withdrawal Update Form 3form 3 signed 30092025.pdf · uploaded 27 Mar 2026Source
- Withdrawal Update Form 1withdrawal form signed 30092025.pdf · uploaded 31 Mar 2026Source
- Withdrawal Update Form 1form 1 31122025.pdf · uploaded 31 Mar 2026Source
- Withdrawal Update Form 2signedengineer certificate 30092025.pdf · uploaded 31 Mar 2026Source
- Withdrawal Update Form 2signed form2 31122025.pdf · uploaded 31 Mar 2026Source
- Withdrawal Update Form 3new form 3 signed 31122025.pdf · uploaded 31 Mar 2026Source
- Withdrawal Update Form 3new form 3 signed 31122025.pdf · uploaded 31 Mar 2026Source
- Withdrawal Update Form 1form 1 31032026.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 2signed form 2 31032026.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 3form 3 signed 31032026 new.pdf · uploaded 27 May 2026Source
Technical
- DocumentBuilding layout Plan.pdf · uploaded 9 Oct 2021Source
- DocumentPlan.pdf · uploaded 9 Oct 2021Source
- Documentlayout plan.pdf · uploaded 2 Jun 2026Source
- DocumentBuilding no 1 new.pdf · uploaded 2 Jun 2026Source
- DocumentBuilding No 2.pdf · uploaded 2 Jun 2026Source
- DocumentBuilding No 3.pdf · uploaded 2 Jun 2026Source
Technical (Architect)
- Documentform 1 31032026.pdf · uploaded 18 May 2026Source
Technical (Engineer)
- Documentsigned form 2 31032026.pdf · uploaded 18 May 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 256/1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, 2BHK141 units in all
- Address
- 256/1, Makne Saphale Road, SaphalePIN 401102
- Village
- Makane, Palghar taluka
- Location
- 19.57159, 72.80836
- Land area for this project
- 3,000 sq m (32,292 sq ft)
- Permissible built-up area
- 6,657 sq m (71,650 sq ft)
- Sanctioned built-up area
- 6,657 sq m (71,650 sq ft)
- Recreational open space
- 300 sq m (3,229 sq ft)
- Designated bank account
- 227
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
256/1
Boundaries
- North
- Layout Road
- South
- Gut No 256
- East
- Gut No 255
- West
- Gut No 152
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking141 units
0 of 141 units booked (0%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building No 1 | 1BHK | 30.97 sq m · 333 sq ft | 1 | 0 |
| Building No 1 | 1BHK | 31.19 sq m · 336 sq ft | 6 | 0 |
| Building No 1 | 1BHK | 31.21 sq m · 336 sq ft | 16 | 0 |
| Building No 1 | 1RK | 19.19 sq m · 207 sq ft | 6 | 0 |
| Building No 2 | 1BHK | 33.16 sq m · 357 sq ft | 5 | 0 |
| Building No 2 | 1BHK | 34.99 sq m · 377 sq ft | 22 | 0 |
| Building No 2 | 1RK | 19.19 sq m · 207 sq ft | 12 | 0 |
| Building No 2 | 2BHK | 41.57 sq m · 447 sq ft | 5 | 0 |
Show all 19 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building No 3 | 1BHK | 30.66 sq m · 330 sq ft | 5 | 0 |
| Building No 3 | 1BHK | 30.79 sq m · 331 sq ft | 6 | 0 |
| Building No 3 | 1BHK | 31.31 sq m · 337 sq ft | 5 | 0 |
| Building No 3 | 1BHK | 31.64 sq m · 341 sq ft | 5 | 0 |
| Building No 3 | 1BHK | 32.3 sq m · 348 sq ft | 6 | 0 |
| Building No 3 | 1RK | 19.3 sq m · 208 sq ft | 6 | 0 |
| Building No 3 | 2BHK | 39.39 sq m · 424 sq ft | 6 | 0 |
| Building No 3 | 2BHK | 39.87 sq m · 429 sq ft | 6 | 0 |
| Building No 4 | 1BHK | 30.09 sq m · 324 sq ft | 1 | 0 |
| Building No 4 | 1BHK | 30.31 sq m · 326 sq ft | 5 | 0 |
| Building No 4 | 1BHK | 30.65 sq m · 330 sq ft | 17 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals7
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Siddhivinayak Associates | — |
| Chartered accountant | Kiran R Dani | — |
| Chartered accountant | Lalit Kumar Somani | — |
| Chartered accountant | Rinky Khilesh Sharma | — |
| Chartered accountant | Shailendra Kumar Mishra | — |
| Engineer | Farooq Nagori | — |
| Engineer | Vastu Gaurav Associates | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Makane
- Golden HarmonyRERA PR1240002602643
- Fortune HightsRERA PR1240002602290
- Angel ApartmentRERA PR1240002601460
- Nine Star Crown Bldg No. 6 DiamondRERA PR1243032600872
- Angel HomesRERA PR1240002600121
- Om SankulanRERA PM1240002600108
- Nine Star Crown Bldg No. 4 SapphireRERA PR1242022502990
- Aditya ResidencyRERA PR1240002502671
All 86 projects in Makane · Compare Omkar Vastu Complex with another project