Residential / Group Housing · 2 buildings · 62 unitsRERA P99000046388

Ninestar Crown Bldg No2 Ruby

Deedo IDDP-PAL-M7V4

Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.

Makane, Palghar 401102 · by Nine Homemakers · 57% of its projects kept the RERA date

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 62 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 22 Jun 2022, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000046388
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900004638822 Jun 202231 Dec 202630 Apr 2027Nine HomemakersProject page
Documents66

1 document held by Deedo, 65 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD NHM.pdf · uploaded 9 Apr 2022Source

Legal

  • Declaration Form BCROWN FORM B REVISED.pdf · uploaded 19 Apr 2022Source
  • Legal Title reportTITLE REPORT CROWN.pdf · uploaded 10 Jun 2022Source
  • Declaration Form BCrown Agreement for FSI-1-3.pdf · uploaded 11 Jun 2022Source
  • Declaration Form BCrown Agreement for FSI-4-7.pdf · uploaded 11 Jun 2022Source
  • Declaration Form BCrown Agreement for FSI-8-11.pdf · uploaded 11 Jun 2022Source
  • Declaration Form BCrown Agreement for FSI-12-14.pdf · uploaded 11 Jun 2022Source
Show all 66 documentsShow fewer documents

Migrated

  • 1 PAN CardPAN CARD NHM.pdf · uploaded 9 Apr 2022Source
  • 1 Details of encumbrancesEncumbrances.pdf · uploaded 9 Apr 2022Source
  • 1 Declaration about Commencement Certificatedeclaration of cc CROWN.pdf · uploaded 9 Apr 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Ruby Form 1.pdf · uploaded 9 Apr 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Ninestar Crown Ruby.pdf · uploaded 9 Apr 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)RUBY FORM 3.pdf · uploaded 9 Apr 2022Source
  • 1 CERSAI detailsRuby CERSAI.pdf · uploaded 11 Apr 2022Source
  • 1 Declaration in FORM BCROWN FORM B REVISED.pdf · uploaded 19 Apr 2022Source
  • 1 Copy of the legal title reportTITLE REPORT CROWN.pdf · uploaded 10 Jun 2022Source
  • 1 Copy of Layout Approval (in case of layout)CROWN LAYOUT PLAN.pdf · uploaded 10 Jun 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentBLDG NO 2.pdf · uploaded 10 Jun 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCROWN NA ORDER.pdf · uploaded 10 Jun 2022Source
  • 2 Declaration in FORM BCrown Agreement for FSI-1-3.pdf · uploaded 11 Jun 2022Source
  • 3 Declaration in FORM BCrown Agreement for FSI-4-7.pdf · uploaded 11 Jun 2022Source
  • 4 Declaration in FORM BCrown Agreement for FSI-8-11.pdf · uploaded 11 Jun 2022Source
  • 5 Declaration in FORM BCrown Agreement for FSI-12-14.pdf · uploaded 11 Jun 2022Source
  • 1 Proforma of Allotment letterRuby.pdf · uploaded 11 Jun 2022Source
  • 2 Proforma of Allotment letter01-First Sell Agreement under RERA-Makane-NINE STAR CROWN_11062022.pdf · uploaded 11 Jun 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)NH-FORM-3-APR-23 TO JUN-23-NINE STAR CROWN-RUBY BLDG NO-02_compressed.pdf · uploaded 23 Aug 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 RUBY.pdf · uploaded 26 Aug 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 RUBY.pdf · uploaded 26 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Crown Bdg 201.pdf · uploaded 18 Sep 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 FORM 1 RUBY.pdf · uploaded 21 Oct 2023Source
  • 1 Disclosure of sold/ booked inventorySOLD CROWN RUBY.pdf · uploaded 21 Oct 2023Source
  • 2 Disclosure of sold/ booked inventorySOLD CROWN RUBY.pdf · uploaded 21 Oct 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)RUBY FORM 2.pdf · uploaded 25 Oct 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)NH-FORM-3-JUL-23 TO SEPT-23-NINE STAR CROWN-RUBY BLDG NO-02.pdf · uploaded 6 Aug 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)NH-FORM-3-OCT-23 TO DEC-23-NINE STAR CROWN-RUBY BLDG NO-02.pdf · uploaded 6 Aug 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)NH-FORM-3-JAN-24 TO MAR-24-NINE STAR CROWN-RUBY BLDG NO-02_compressed.pdf · uploaded 6 Aug 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)NH-FORM-5-FY-22-23-NINE STAR CROWN-RUBY BLDG NO-02.pdf · uploaded 6 Aug 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)NH FORM 3 APR-24 TO JUN 24 NINE STAR CROWN RUBY BLDG NO 2.pdf · uploaded 27 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)NH FORM 3 JUL 24 TO SEPT 24 NINE STAR CROWN RUBY BLDG NO 2.pdf · uploaded 27 Jan 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)NH FORM 3 OCT-24 TO DEC 24 NINE STAR CROWN RUBY BLDG NO 2.pdf · uploaded 27 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)NH FORM 5 FY 23 24 NINE STAR CROWN RUBY BLDG NO 2.pdf · uploaded 6 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)NH-FORM-3-JAN-25 TO MAR-25-NINE STAR CROWN -RUBY BLDG NO-02_compressed.pdf · uploaded 10 May 2025Source
  • Withdrawal Update Form 13 FORM 1 RUBY.pdf · uploaded 8 Sep 2025Source
  • Withdrawal Update Form 2RUBY FORM 2.pdf · uploaded 8 Sep 2025Source
  • Withdrawal Update Form 3ruby form 3.pdf · uploaded 8 Sep 2025Source
  • Withdrawal Update Form 13 FORM 1 RUBY.pdf · uploaded 30 Dec 2025Source
  • Withdrawal Update Form 2RUBY FORM 2.pdf · uploaded 30 Dec 2025Source
  • Withdrawal Update Form 3ruby form 3.pdf · uploaded 30 Dec 2025Source
  • Withdrawal Update Form 1FORM-01-RUBY-BLDG NO 2.pdf · uploaded 9 Feb 2026Source
  • Withdrawal Update Form 2FORM-02-RUBY-BLDG NO 2.pdf · uploaded 9 Feb 2026Source
  • Withdrawal Update Form 3FORM-03-RUBY-BLDG NO 2.pdf · uploaded 9 Feb 2026Source
  • Form 5 (FY 2022-2023)CA (Form 5) (FY 2022-23).pdf · uploaded 14 Mar 2026Source
  • Form 5 (FY 2023-2024)CA (Form 5) (FY 2023-24).pdf · uploaded 14 Mar 2026Source
  • Withdrawal Update Form 1ruby form 1.pdf · uploaded 29 Apr 2026Source
  • Withdrawal Update Form 2ruby form 2.pdf · uploaded 29 Apr 2026Source
  • Withdrawal Update Form 3ruby form 3.pdf · uploaded 29 Apr 2026Source
  • Form 2A (FY 2025-2026)FORM 2A 02 NHM CROWN RUBY BDG 2 (1).pdf · uploaded 29 Jun 2026Source
  • Form 5 (FY 2024-2025)Form 5 BLDG 2 Ruby 2024-25.pdf · uploaded 30 Jun 2026Source
  • Withdrawal Update Form 1NH-FORM-01-RUBY BLDG 2.pdf · uploaded 20 Aug 2026Source
  • Withdrawal Update Form 2NH-FORM-02-RUBY BLDG 2.pdf · uploaded 20 Aug 2026Source
  • Withdrawal Update Form 3NH-FORM-03-APR-26 TO JUN-26-NINE STAR CROWN-RUBY BLDG NO-2.pdf · uploaded 20 Aug 2026Source

Technical

  • DocumentCROWN LAYOUT PLAN.pdf · uploaded 10 Jun 2022Source
  • DocumentBLDG NO 2.pdf · uploaded 10 Jun 2022Source

Technical (Architect)

  • DocumentNH-FORM-01-RUBY BLDG 2.pdf · uploaded 20 Aug 2026Source

Technical (Engineer)

  • DocumentNH-FORM-02-RUBY BLDG 2.pdf · uploaded 20 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel GUT NO 203/2, GUT NO 268/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK62 units in all
Address
GUT NO 203/2, GUT NO 268/1, GUT NO 271, Mande-Makane Road, Mande-Makane RoadPIN 401102
Village
Makane, Palghar taluka
Land area for this project
3,175 sq m (34,171 sq ft)
Permissible built-up area
3,175 sq m (34,171 sq ft)
Sanctioned built-up area
3,175 sq m (34,171 sq ft)
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

GUT NO 203/2GUT NO 268/1GUT NO 271

Land as published on MahaRERA's project page

GUT NO 203/2, GUT NO 268/1, GUT NO 271

Boundaries

North
Building no 3
South
Main Road
East
Main Road
West
Internal Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking62 units

0 of 62 units booked (0%), as the promoter reported to MahaRERA

1BHK · 32 units2BHK · 30 units
BuildingTypeCarpet areaUnitsBooked
Bldg No 2 Ruby Wing A1BHK33.75 sq m · 363 sq ft10
Bldg No 2 Ruby Wing A1BHK36.2 sq m · 390 sq ft80
Bldg No 2 Ruby Wing A2BHK43.6 sq m · 469 sq ft70
Bldg No 2 Ruby Wing A2BHK48.99 sq m · 527 sq ft150
Bldg No 2 Ruby Wing B1BHK36.2 sq m · 390 sq ft230
Bldg No 2 Ruby Wing B2BHK43.6 sq m · 469 sq ft80

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRoshan Patil—
Chartered accountantRd Lukad—
Chartered accountantRd Lukad & Co—
EngineerAsrar Ahmed Jatoo—

Source: MahaRERA project page. Contact details are not shown.