Skip to content
Residential / Group Housing · 1 building · 46 unitsRERA P99000052117

Golden Bliss

Deedo IDDP-PAL-CPVS

Completion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 37% of its units are booked.

Makane, Palghar 401102 · by Mahalaxmi Homes

DeliveryExtended 4 moPromised Dec 2027 · now due Apr 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales37% booked17 of 46 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2028

  • This projectRegistered 24 Jul 2023, completion promised 31 Dec 2027, revised to 30 Apr 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000052117
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900005211724 Jul 202331 Dec 202730 Apr 2028Mahalaxmi HomesProject page
Documents92

1 document held by Deedo, 91 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 21 May 2023Source

Legal

  • Declaration Form BAffidavit cum Declaration.pdf · uploaded 21 May 2023Source
  • Other – LegalDeclaration of legal.pdf · uploaded 27 May 2023Source
  • Legal Title reportLegal title report.pdf · uploaded 20 Jun 2023Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 21 May 2023Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN GB.pdf · uploaded 21 May 2023Source
  • 1 Declaration about Commencement CertificateDeclaration CC.pdf · uploaded 21 May 2023Source
Show all 92 documentsShow fewer documents

Migrated

  • 1 Declaration in FORM BAffidavit cum Declaration.pdf · uploaded 21 May 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 10-05-23.pdf · uploaded 21 May 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Engineer’s Certificate on Cost Incurred on Project (Form 2) DATE 10-05-23.pdf · uploaded 21 May 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2a G B.pdf · uploaded 21 May 2023Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 21 May 2023Source
  • 1 Deviation Report with respect to Allotment letterDevation respect to allotment letter.pdf · uploaded 21 May 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentN A ORDER GB.pdf · uploaded 23 May 2023Source
  • 1 Proforma of Agreement for saleAgreement Mahalaxmi Homes.pdf · uploaded 23 May 2023Source
  • 1 Proforma of Allotment letterModel of Allotment letter.pdf · uploaded 23 May 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDevation model copy of agreement.pdf · uploaded 23 May 2023Source
  • 1 Other – LegalDeclaration of legal.pdf · uploaded 27 May 2023Source
  • 1 Copy of the legal title reportLegal title report.pdf · uploaded 20 Jun 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE (2).pdf · uploaded 22 Jun 2023Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Concerned to finance.pdf · uploaded 6 Jul 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Concerned to finance.pdf · uploaded 6 Jul 2023Source
  • 2 CERSAI detailsDeclaration of Cersai Certificate.pdf · uploaded 6 Jul 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank Account.pdf · uploaded 6 Jul 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Acceptance (1).pdf · uploaded 10 Jul 2023Source
  • 1 Building Plan Approval / NA Order for plotted development1 Building Plan Approval _ NA Order for plotted development MARKED.pdf · uploaded 11 Jul 2023Source
  • 1 Other – TechnicalDECLARATION IN FORM B.pdf · uploaded 11 Jul 2023Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about Separate Bank Account.pdf · uploaded 23 Aug 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)mahalaxmihomesForm3.pdf · uploaded 2 Feb 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Adobe Scan Mar 12, 2024.pdf · uploaded 14 Mar 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-01.pdf · uploaded 3 May 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 3 May 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 3 May 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form5Mahalaxmi.pdf · uploaded 5 Jun 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-01 _GOLDEN BLISS.pdf · uploaded 15 Jul 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 15 Jul 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 (2)_11zon.pdf · uploaded 15 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 22 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3.pdf · uploaded 22 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2.pdf · uploaded 22 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -01 _ GOLDEN BLESS.pdf · uploaded 19 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate form 3.pdf · uploaded 19 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate March 25.pdf · uploaded 19 Apr 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Unsold Inventory March 25.pdf · uploaded 23 Jul 2025Source
  • Form 1FORM -01 _ GOLDEN BLESS.pdf · uploaded 23 Jul 2025Source
  • Form 2Engineer certificate March 25.pdf · uploaded 23 Jul 2025Source
  • Form 3CA certificate form 3.pdf · uploaded 23 Jul 2025Source
  • Form 5 (FY 2023-2024)Form5Mahalaxmi.pdf · uploaded 23 Jul 2025Source
  • Form 5 (FY 2024-2025)Form 5 Mahalaxmi Homes.pdf · uploaded 23 Jul 2025Source
  • Form 1FORM-01.pdf · uploaded 24 Jul 2025Source
  • Form 2Form 2.pdf · uploaded 24 Jul 2025Source
  • Form 3Form3.pdf · uploaded 24 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Unsold Inventory Sept24.pdf · uploaded 24 Jul 2025Source
  • Form 1FORM-01.pdf · uploaded 24 Jul 2025Source
  • Form 2Form 2.pdf · uploaded 24 Jul 2025Source
  • Form 3form 3 (2)_11zon.pdf · uploaded 24 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Unsold Inventory June24.pdf · uploaded 24 Jul 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 24 Jul 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 24 Jul 2025Source
  • Withdrawal Update Form 2Form 2 (1).pdf · uploaded 24 Jul 2025Source
  • Withdrawal Update Form 2Form 2 (1).pdf · uploaded 24 Jul 2025Source
  • Withdrawal Update Form 3Form3 Mahalaxmi.pdf · uploaded 24 Jul 2025Source
  • Withdrawal Update Form 3Form3 Mahalaxmi.pdf · uploaded 24 Jul 2025Source
  • Withdrawal Update Form 1Form 01.pdf · uploaded 19 Oct 2025Source
  • Withdrawal Update Form 2Form 02.pdf · uploaded 19 Oct 2025Source
  • Withdrawal Update Form 3Form 03.pdf · uploaded 19 Oct 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 20 Jan 2026Source
  • Form 2A (FY 2023-2024)Adobe Scan 8 Apr 2026 (1).pdf · uploaded 8 Apr 2026Source
  • Form 2A (FY 2024-2025)Adobe Scan 8 Apr 2026 (2).pdf · uploaded 8 Apr 2026Source
  • Form 2A (FY 2025-2026)Adobe Scan 8 Apr 2026 (3).pdf · uploaded 8 Apr 2026Source
  • Withdrawal Update Form 1Form 01 Upload (1).pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2Form 02 Upload (1).pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3Withdrawal Application Form3 (2) (1).pdf · uploaded 20 Apr 2026Source
  • Form 1FORM 01.pdf · uploaded 23 May 2026Source
  • Form 2Form 2.pdf · uploaded 23 May 2026Source
  • Form 3Form 03.pdf · uploaded 23 May 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Unsold Inventory (1).pdf · uploaded 23 May 2026Source
  • Withdrawal Update Form 1Form 01.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2Form 02.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3Withdrawal Application Form3 (9) (2).pdf · uploaded 20 Jul 2026Source

Technical

  • DocumentLAYOUT PLAN GB.pdf · uploaded 21 May 2023Source
  • Document1 Building Plan Approval _ NA Order for plotted development MARKED.pdf · uploaded 11 Jul 2023Source
  • Other – TechnicalDECLARATION IN FORM B.pdf · uploaded 11 Jul 2023Source

Technical (Architect)

  • DocumentForm1.pdf · uploaded 22 Oct 2024Source
  • DocumentFORM -01 _ GOLDEN BLESS.pdf · uploaded 19 Apr 2025Source
  • DocumentForm 01.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • DocumentForm2.pdf · uploaded 22 Oct 2024Source
  • DocumentEngineer certificate March 25.pdf · uploaded 19 Apr 2025Source
  • DocumentForm 02.pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel G NO 227/PT

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK46 units in all
Address
G No 227/Pt, Makane Mande Road, Central Park AvenuePIN 401102
Village
Makane, Palghar taluka
Land area for this project
2,027 sq m (21,815 sq ft)
Permissible built-up area
2,027 sq m (21,815 sq ft)
Sanctioned built-up area
2,027 sq m (21,815 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

G NO 227/PT

Land as published on MahaRERA's project page

G NO 227/PT

Boundaries

North
Amenity Center
South
Bldg No 1
East
Gut No 224
West
Layout Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking46 units

17 of 46 units booked (37%), as the promoter reported to MahaRERA

1BHK · 38 units2BHK · 8 units
TypeCarpet areaUnitsBooked
1BHK29.74 sq m · 320 sq ft235
1BHK33.16 sq m · 357 sq ft83
1BHK38.06 sq m · 410 sq ft74
2BHK41.23 sq m · 444 sq ft10
2BHK46.13 sq m · 497 sq ft75

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRoshan R Patil—
Chartered accountantSachin Hukumchand Chordiya—
Chartered accountantSurendra Kumar Trivedi—
EngineerCon Arch India—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Makane

All 86 projects in Makane · Compare Golden Bliss with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology