Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 53% of its units are booked.

Makane, Palghar 401102 · by Ace Developers

Delivery11 mo past duePromised Dec 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales53% booked16 of 30 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 29 May 2021, completion promised 31 Dec 2025, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000029401
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900002940129 May 202131 Dec 202531 Dec 2025Ace DevelopersProject page
Documents159

2 documents held by Deedo, 157 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardPan Card Ace Developers.pdf · uploaded 8 Apr 2021Source

Legal

  • Legal Title reportTitle Search Report.pdf · uploaded 8 Apr 2021Source
  • Declaration Form BACE (affidavit) FORM B.pdf · uploaded 8 Apr 2021Source
  • OtherForm B.pdf · uploaded 15 May 2021Source
  • OtherOther -2.pdf · uploaded 15 May 2021Source
  • OtherPOA.pdf · uploaded 15 May 2021Source
Show all 159 documentsShow fewer documents

Legal

  • OtherProject details.pdf · uploaded 15 May 2021Source
  • OtherRPM_MCHI_990000_PAL_779.pdf · uploaded 21 May 2021Source
  • Declaration Form Bform b affidavite 2025.pdf · uploaded 13 Feb 2025Source
  • Declaration Form Bform b affidavite 2025.pdf · uploaded 13 Feb 2025Source
  • Otherarihant time line.pdf · uploaded 1 Apr 2025Source
  • Otherarihant time line.pdf · uploaded 1 Apr 2025Source
  • Declaration Form Btitle1.pdf · uploaded 1 Apr 2026Source

Migrated

  • 1 PAN CardPan Card Ace Developers.pdf · uploaded 8 Apr 2021Source
  • 1 Copy of the legal title reportTitle Search Report.pdf · uploaded 8 Apr 2021Source
  • 1 Copy of Layout Approval (in case of layout)Complex Layout Plan Approval.pdf · uploaded 8 Apr 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Approval Plan.pdf · uploaded 8 Apr 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC Copy.pdf · uploaded 8 Apr 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentNA Order.pdf · uploaded 8 Apr 2021Source
  • 1 Declaration in FORM BACE (affidavit) FORM B.pdf · uploaded 8 Apr 2021Source
  • 1 Proforma of Allotment letterRera Allotment.pdf · uploaded 8 Apr 2021Source
  • 2 Proforma of Allotment letterAce Developers Sale Agreement.pdf · uploaded 8 Apr 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 6 May 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Certificate.pdf · uploaded 6 May 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA RERA Certificate.pdf · uploaded 6 May 2021Source
  • 1 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 15 May 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentBuilding Plan.pdf · uploaded 15 May 2021Source
  • 3 Building Plan Approval / NA Order for plotted developmentComplex Layout Plan Approval.pdf · uploaded 15 May 2021Source
  • 1 OtherForm B.pdf · uploaded 15 May 2021Source
  • 2 OtherOther -2.pdf · uploaded 15 May 2021Source
  • 3 OtherPOA.pdf · uploaded 15 May 2021Source
  • 4 OtherProject details.pdf · uploaded 15 May 2021Source
  • 5 OtherRPM_MCHI_990000_PAL_779.pdf · uploaded 21 May 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form -01 _galaxy apartment.pdf · uploaded 27 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)F II BLDG NO 13A OCT DEC 2024 Final.pdf · uploaded 27 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)F-II BLDG NO 13A OCT DEC 2024 Ace and Arihant.pdf · uploaded 27 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form -01 _galaxy apartment.pdf · uploaded 27 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)F II BLDG NO 13A OCT DEC 2024 Final.pdf · uploaded 27 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)F-II BLDG NO 13A OCT DEC 2024 Ace and Arihant.pdf · uploaded 27 Jan 2025Source
  • 1 Declaration in FORM Bform b affidavite 2025.pdf · uploaded 13 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryInventory Disclosure Final.pdf · uploaded 13 Feb 2025Source
  • 1 Declaration in FORM Bform b affidavite 2025.pdf · uploaded 13 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryInventory Disclosure Final.pdf · uploaded 13 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Building No13A JUL SEP 2023.pdf · uploaded 27 Mar 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 June 2023.pdf · uploaded 27 Mar 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 Sep 2023.pdf · uploaded 27 Mar 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 Dec 2023.pdf · uploaded 27 Mar 2025Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 June 2024.pdf · uploaded 27 Mar 2025Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 Mar 2024.pdf · uploaded 27 Mar 2025Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 Sep 2024.pdf · uploaded 27 Mar 2025Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 Mar 2023.pdf · uploaded 27 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Building No13A APR JUN 2023.pdf · uploaded 27 Mar 2025Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Mar 2024_compressed.pdf · uploaded 27 Mar 2025Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec 2024_compressed.pdf · uploaded 27 Mar 2025Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sep 2024_compressed.pdf · uploaded 27 Mar 2025Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Jun 2024_compressed.pdf · uploaded 27 Mar 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec 2023_compressed.pdf · uploaded 27 Mar 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sep 2023_compressed.pdf · uploaded 27 Mar 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Jun 2023_compressed.pdf · uploaded 27 Mar 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Mar 2023_compressed.pdf · uploaded 27 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 01 Mar 2023.pdf · uploaded 27 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Building No 13A ARIHANT Developers JAN MAR 2023.pdf · uploaded 27 Mar 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Building No 13A ARIHANT Developers APR JUN 2023.pdf · uploaded 27 Mar 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Building No 13A ARIHANT Developers JUL SEP 2023.pdf · uploaded 27 Mar 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Building No 13A ARIHANT Developers OCT DEC 2023.pdf · uploaded 27 Mar 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Building No 13A ARIHANT Developers JAN MAR 2024.pdf · uploaded 27 Mar 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Building No 13A ARIHANT Developers JUL SEP 2024.pdf · uploaded 27 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Arihant Ace Developers Year Ending march 2023.pdf · uploaded 27 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 FY 2022-2023.pdf · uploaded 27 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Arihant Ace Developers Year Ending March 2024.pdf · uploaded 27 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 FY 2023-2024.pdf · uploaded 27 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Building No13A APR JUN 2024.pdf · uploaded 1 Apr 2025Source
  • 1 Otherarihant time line.pdf · uploaded 1 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Building No13A APR JUN 2024.pdf · uploaded 1 Apr 2025Source
  • 1 Otherarihant time line.pdf · uploaded 1 Apr 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 June 2023.pdf · uploaded 13 Apr 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 Sep 2023.pdf · uploaded 13 Apr 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 Dec 2023.pdf · uploaded 13 Apr 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 Mar 2024.pdf · uploaded 13 Apr 2025Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 June 2024.pdf · uploaded 13 Apr 2025Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 Sep 2024.pdf · uploaded 13 Apr 2025Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 Dec 2024.pdf · uploaded 13 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 Mar 2023.pdf · uploaded 13 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Mar 2023.pdf · uploaded 13 Apr 2025Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Dec 2024.pdf · uploaded 13 Apr 2025Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sep 2024.pdf · uploaded 13 Apr 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Jun 2024.pdf · uploaded 13 Apr 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Mar 2024.pdf · uploaded 13 Apr 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Dec 2023.pdf · uploaded 13 Apr 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sep 2023.pdf · uploaded 13 Apr 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Jun 2023.pdf · uploaded 13 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryDiscloser Inventary sold unsold.pdf · uploaded 13 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form1.pdf · uploaded 20 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3.pdf · uploaded 20 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2.pdf · uploaded 20 May 2025Source
  • 1 Disclosure of sold/ booked inventorysold unsold 31-03-2025.pdf · uploaded 20 May 2025Source
  • Withdrawal Update Form 1form -01 _ galaxy apartment (1).pdf · uploaded 11 Dec 2025Source
  • Withdrawal Update Form 1FORM -01 _ GALAXY APARTMENT.pdf · uploaded 11 Dec 2025Source
  • Withdrawal Update Form 2F-II 30 JUN 2025.pdf · uploaded 11 Dec 2025Source
  • Withdrawal Update Form 2F-II JUL SEP 2025.pdf · uploaded 11 Dec 2025Source
  • Withdrawal Update Form 3Rera Certificate Merge (1).pdf · uploaded 11 Dec 2025Source
  • Withdrawal Update Form 3Rera Certificate Merge Sep 2025.pdf · uploaded 11 Dec 2025Source
  • Form 5 (FY 2024-2025)Form 5_merged.pdf · uploaded 27 Dec 2025Source
  • Withdrawal Update Form 1FORM -01 GALAXY APRTMEN Dec 2025.pdf · uploaded 31 Jan 2026Source
  • Withdrawal Update Form 2FII BLDG NO 13A OCT DEC 2025.pdf · uploaded 31 Jan 2026Source
  • Withdrawal Update Form 3Rera Certificate Sacnned Merage.pdf · uploaded 31 Jan 2026Source
  • Form 2A (FY 2022-2023)Form 2A Arihant Ace Developers Year Ending march 2023.pdf · uploaded 6 Oct 2026Source
  • Form 2A (FY 2023-2024)Form 2A Arihant Ace Developers Year Ending march 2023.pdf · uploaded 6 Oct 2026Source

Technical

  • DocumentBuilding Plan.pdf · uploaded 15 May 2021Source
  • DocumentComplex Layout Plan Approval.pdf · uploaded 15 May 2021Source
  • Othersform c application.pdf · uploaded 31 Dec 2025Source
  • Othersform C consent.pdf · uploaded 31 Dec 2025Source
  • DocumentBLDG No 13 Layout Plan_compressed.pdf · uploaded 1 Apr 2026Source
  • DocumentBLDG NO 13 BLDG Plan_compressed.pdf · uploaded 1 Apr 2026Source

Technical (Architect)

  • Documentform -01 _galaxy apartment.pdf · uploaded 27 Jan 2025Source
  • Documentform -01 _galaxy apartment.pdf · uploaded 27 Jan 2025Source
  • DocumentBuilding No13A APR JUN 2023.pdf · uploaded 27 Mar 2025Source
  • DocumentBuilding No13A JUL SEP 2023.pdf · uploaded 27 Mar 2025Source
  • DocumentFORM 01 June 2023.pdf · uploaded 27 Mar 2025Source
  • DocumentFORM 01 Sep 2023.pdf · uploaded 27 Mar 2025Source
  • DocumentFORM 01 Dec 2023.pdf · uploaded 27 Mar 2025Source
  • DocumentFORM 01 June 2024.pdf · uploaded 27 Mar 2025Source
  • DocumentFORM 01 Mar 2024.pdf · uploaded 27 Mar 2025Source
  • DocumentFORM 01 Sep 2024.pdf · uploaded 27 Mar 2025Source
  • DocumentFORM 01 Mar 2023.pdf · uploaded 27 Mar 2025Source
  • DocumentFORM 01 Mar 2023.pdf · uploaded 13 Apr 2025Source
  • DocumentFORM 01 June 2023.pdf · uploaded 13 Apr 2025Source
  • DocumentFORM 01 Sep 2023.pdf · uploaded 13 Apr 2025Source
  • DocumentFORM 01 Dec 2023.pdf · uploaded 13 Apr 2025Source
  • DocumentFORM 01 Mar 2024.pdf · uploaded 13 Apr 2025Source
  • DocumentFORM 01 June 2024.pdf · uploaded 13 Apr 2025Source
  • DocumentFORM 01 Sep 2024.pdf · uploaded 13 Apr 2025Source
  • DocumentFORM 01 Dec 2024.pdf · uploaded 13 Apr 2025Source
  • Documentform1.pdf · uploaded 20 May 2025Source
  • DocumentFORM 1 Galaxy Apartment March 2026.pdf · uploaded 17 Aug 2026Source

Technical (Engineer)

  • DocumentF II BLDG NO 13A OCT DEC 2024 Final.pdf · uploaded 27 Jan 2025Source
  • DocumentF-II BLDG NO 13A OCT DEC 2024 Ace and Arihant.pdf · uploaded 27 Jan 2025Source
  • DocumentF II BLDG NO 13A OCT DEC 2024 Final.pdf · uploaded 27 Jan 2025Source
  • DocumentF-II BLDG NO 13A OCT DEC 2024 Ace and Arihant.pdf · uploaded 27 Jan 2025Source
  • DocumentBuilding No 13A ARIHANT Developers JAN MAR 2023.pdf · uploaded 27 Mar 2025Source
  • DocumentBuilding No 13A ARIHANT Developers APR JUN 2023.pdf · uploaded 27 Mar 2025Source
  • DocumentBuilding No 13A ARIHANT Developers JUL SEP 2023.pdf · uploaded 27 Mar 2025Source
  • DocumentBuilding No 13A ARIHANT Developers OCT DEC 2023.pdf · uploaded 27 Mar 2025Source
  • DocumentBuilding No 13A ARIHANT Developers JAN MAR 2024.pdf · uploaded 27 Mar 2025Source
  • DocumentBuilding No 13A ARIHANT Developers JUL SEP 2024.pdf · uploaded 27 Mar 2025Source
  • DocumentBuilding No13A APR JUN 2024.pdf · uploaded 1 Apr 2025Source
  • DocumentBuilding No13A APR JUN 2024.pdf · uploaded 1 Apr 2025Source
  • DocumentForm 2 Mar 2023.pdf · uploaded 13 Apr 2025Source
  • DocumentForm 2 Jun 2023.pdf · uploaded 13 Apr 2025Source
  • DocumentForm 2 Sep 2023.pdf · uploaded 13 Apr 2025Source
  • DocumentForm 2 Dec 2023.pdf · uploaded 13 Apr 2025Source
  • DocumentForm 2 Mar 2024.pdf · uploaded 13 Apr 2025Source
  • DocumentForm 2 Jun 2024.pdf · uploaded 13 Apr 2025Source
  • DocumentForm 2 Sep 2024.pdf · uploaded 13 Apr 2025Source
  • DocumentForm 2 Dec 2024.pdf · uploaded 13 Apr 2025Source
  • DocumentForm2.pdf · uploaded 20 May 2025Source
  • DocumentBLDG No 13A JAN MAR 2026.pdf · uploaded 17 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel G. NO. 224, GUT NO 226/2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK30 units in all
Address
G. No. 224, Gut No 226/2, Gut No 226/3, Pandit Pada, Saphale WestPIN 401102
Village
Makane, Palghar taluka
Land area for this project
1,109 sq m (11,934 sq ft)
Permissible built-up area
1,109 sq m (11,934 sq ft)
Sanctioned built-up area
1,109 sq m (11,934 sq ft)
Designated bank account
82
Developed in phases
No

Survey, CTS, gat or plot numbers

G. NO. 224GUT NO 226/2GUT NO 226/3

Land as published on MahaRERA's project page

G. NO. 224, GUT NO 226/2 ,GUT NO 226/3

Boundaries

North
9 mt wide road
South
Garden
East
Building No 14
West
Building No 12

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking30 units

16 of 30 units booked (53%), as the promoter reported to MahaRERA

1BHK · 25 units2BHK · 5 units
TypeCarpet areaUnitsBooked
1BHK25.32 sq m · 273 sq ft2011
1BHK28.52 sq m · 307 sq ft52
2BHK39.57 sq m · 426 sq ft53

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Roshan Ravindra Patil—
Chartered accountantKishor Sheth M Sheth—
EngineerJay Shree Krishna Consulting Engg.—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Makane

All 86 projects in Makane · Compare Galaxy Apartment with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology