Extended 18 mo3 floorsRERA P99000014211
Main building, Aashta
Deedo IDDP-PAL-G8VR-AASHTAMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked35%7 of 20 · MahaRERA
Completion30 Sep 202031 Mar 2019 · revised
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 30.4 m² (327 sq.ft) | 4 | 1 |
| 1 RK TYPE 1 | 20.1 m² (217 sq.ft) | 2 | 0 |
| 1 RK TYPE 2 | 20.4 m² (219 sq.ft) | 2 | 0 |
| 1 RK TYPE 3 | 22 m² (237 sq.ft) | 6 | 2 |
| 1 RK TYPE 4 | 21.3 m² (229 sq.ft) | 2 | 1 |
| SHOP 1 | 7.9 m² (85 sq.ft) | 2 | 1 |
| SHOP 2 | 5.8 m² (62 sq.ft) | 2 | 2 |
As registered with MahaRERA
- RERA registration
- P99000014211 · registered 16 Nov 2017
- Promised completion
- 31 Mar 2019
- Revised completion
- 30 Sep 2020
- Sanctioned habitable floors
- 3
- Building
- AASHTA
- Sanctioned floors (incl. basement, stilt, podium)
- 3
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PAL-G8VR-AASHTA
Questions about Main building
When is Main building due for completion?
The MahaRERA registration promises 31 Mar 2019, revised to 30 Sep 2020.
How many floors does Main building have?
3 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology