Extended 18 mo3 floorsRERA P99000014211

Main building, Aashta

Deedo IDDP-PAL-G8VR-AASHTA

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

All of Aashta
Median saleNot on recordneeds 3 or more sales
Booked35%7 of 20 · MahaRERA
Completion30 Sep 202031 Mar 2019 · revised
Units & parking in Main building
TypeCarpet areaUnitsBooked
1 BHK30.4 m² (327 sq.ft)41
1 RK TYPE 120.1 m² (217 sq.ft)20
1 RK TYPE 220.4 m² (219 sq.ft)20
1 RK TYPE 322 m² (237 sq.ft)62
1 RK TYPE 421.3 m² (229 sq.ft)21
SHOP 17.9 m² (85 sq.ft)21
SHOP 25.8 m² (62 sq.ft)22
As registered with MahaRERA
RERA registration
P99000014211 · registered 16 Nov 2017
Promised completion
31 Mar 2019
Revised completion
30 Sep 2020
Sanctioned habitable floors
3
Building
AASHTA
Sanctioned floors (incl. basement, stilt, podium)
3
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
DP-PAL-G8VR-AASHTA
Questions about Main building

When is Main building due for completion?

The MahaRERA registration promises 31 Mar 2019, revised to 30 Sep 2020.

How many floors does Main building have?

3 sanctioned habitable floors, as registered with MahaRERA.