RERA projects in Dhovali

3 projects under 3 MahaRERA registrations, registered 2026–2026. 67% have a completion date extended beyond the one promised.

Locality
3RERA projects
3Registrations
3Completion still due0 past their completion date
4 monthsMedian extension beyond promised date67% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20263

Projects in Dhovali

3 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Genisia PinnacleGenisia RealtyPR12400026014043 Aug 202630 Jun 202930 Jun 2029Not yet due0
Sunteck Beach Residences - Tower A4Sunteck Real Estates Private LimitedPR124000260085418 Jun 202631 Dec 203430 Apr 2035Extended 4 mo0
Sunteck Beach Residences - Tower A8Sunteck Real Estates Private LimitedPR124000260071610 Jun 202631 Dec 203430 Apr 2035Extended 4 mo0

Other localities in Vasai

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Sunteck Real Estates Private Limited2 projects
  2. Genisia Realty1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology