Residential / Group Housing · 1 building · 30 unitsRERA P99000054978

Santosh Apartment

Deedo IDDP-PAL-BQ9S

Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 3% of its units are booked.

Dhansar, Palghar 401404 · by Future Star Construction

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales3% booked1 of 30 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 21 Feb 2024, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000054978
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900005497821 Feb 202431 Dec 202830 Apr 2029Future Star ConstructionProject page
Documents62

1 document held by Deedo, 61 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan card Future star construction .pdf · uploaded 3 Jan 2024Source

Legal

  • Declaration Form BForm -B Affidavit cum Declaration of Santoshkumar Amarbahadur Singh.pdf · uploaded 3 Jan 2024Source
  • Legal Title reportLegal Title Report.pdf · uploaded 24 Jan 2024Source

Migrated

  • 1 PAN CardPan card Future star construction .pdf · uploaded 3 Jan 2024Source
  • 1 a Details of encumbrances concerned to FinanceFinancial Encumbrance Declaration.pdf · uploaded 3 Jan 2024Source
  • 1 b Details of encumbrances concerned to LegalFinancial Encumbrance Declaration.pdf · uploaded 3 Jan 2024Source
  • 1 Declaration about Commencement CertificateDeclaration about commencement certificate Format -D.pdf · uploaded 3 Jan 2024Source
Show all 62 documentsShow fewer documents

Migrated

  • 1 Declaration in FORM BForm -B Affidavit cum Declaration of Santoshkumar Amarbahadur Singh.pdf · uploaded 3 Jan 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Engineers Certificate.pdf · uploaded 3 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form-2A.pdf · uploaded 3 Jan 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest inother Real Estate Org.pdf · uploaded 3 Jan 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest inother Real Estate Org Ali.pdf · uploaded 3 Jan 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about Separate Bank State for Real estate project.pdf · uploaded 3 Jan 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report - Allotment Letter.pdf · uploaded 3 Jan 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report - Agreement for sale.pdf · uploaded 3 Jan 2024Source
  • 1 Other – TechnicalPartner ship Deed Com.pdf · uploaded 3 Jan 2024Source
  • 2 a Details of encumbrances concerned to FinanceLegal Encumbrance Declaration.pdf · uploaded 4 Jan 2024Source
  • 2 b Details of encumbrances concerned to LegalLegal Encumbrance Declaration.pdf · uploaded 4 Jan 2024Source
  • 2 Declaration about Commencement CertificateEmail of CC to MahaRERA.pdf · uploaded 4 Jan 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 4 Jan 2024Source
  • 1 Disclosure of sold/ booked inventorySold-unsold inventory.pdf · uploaded 4 Jan 2024Source
  • 1 CERSAI detailsCersai Certificate - Attested.pdf · uploaded 4 Jan 2024Source
  • 1 Proforma of Allotment letterAllotment Letter Format.pdf · uploaded 4 Jan 2024Source
  • 2 Other – TechnicalTechnical Declaration.pdf · uploaded 4 Jan 2024Source
  • 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 24 Jan 2024Source
  • 1 Copy of Layout Approval (in case of layout)Plan Scan Copy (Layout Plan)Com.pdf · uploaded 24 Jan 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan Scan Copy(Building Plan) Com.pdf · uploaded 24 Jan 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 24 Jan 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentAppendix F.pdf · uploaded 24 Jan 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3.pdf · uploaded 24 Jan 2024Source
  • 1 Proforma of Agreement for saleFinal Draft of Agreement for sale.pdf · uploaded 24 Jan 2024Source
  • 3 Other – TechnicalTechnical Declaration.pdf · uploaded 24 Jan 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 as on 17-05-24.pdf · uploaded 6 Aug 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 as on 31-03-2024.pdf · uploaded 6 Aug 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form-2A.pdf · uploaded 6 Aug 2024Source
  • 2 Disclosure of sold/ booked inventorySold Unsold Inventory as on 31-03-2024.pdf · uploaded 6 Aug 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 as on 31-03-2024.pdf · uploaded 6 Aug 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 as on 30th June 2024.pdf · uploaded 12 Aug 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 as on 30th June 2024.pdf · uploaded 12 Aug 2024Source
  • 3 Disclosure of sold/ booked inventorySold Unsold as on 30th June 2024.pdf · uploaded 12 Aug 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 as on 30-06-2024.pdf · uploaded 12 Aug 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 as on 30-09-2024.pdf · uploaded 24 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 as on 30-09-2024.pdf · uploaded 24 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 as on 30-09-2024.pdf · uploaded 24 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold unsold.pdf · uploaded 24 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.pdf · uploaded 25 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Dec-2024 (F).pdf · uploaded 4 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec-2024.pdf · uploaded 4 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Dec-2024.pdf · uploaded 4 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold-Unsold.pdf · uploaded 4 Mar 2025Source

Technical

  • Other – TechnicalPartner ship Deed Com.pdf · uploaded 3 Jan 2024Source
  • Other – TechnicalTechnical Declaration.pdf · uploaded 4 Jan 2024Source
  • DocumentPlan Scan Copy (Layout Plan)Com.pdf · uploaded 24 Jan 2024Source
  • DocumentPlan Scan Copy(Building Plan) Com.pdf · uploaded 24 Jan 2024Source
  • Other – TechnicalTechnical Declaration.pdf · uploaded 24 Jan 2024Source

Technical (Architect)

  • DocumentForm 1 as on 30th June 2024.pdf · uploaded 12 Aug 2024Source
  • DocumentForm 1 as on 30-09-2024.pdf · uploaded 24 Oct 2024Source
  • DocumentForm 1 Dec-2024 (F).pdf · uploaded 4 Mar 2025Source

Technical (Engineer)

  • DocumentForm 2 as on 30th June 2024.pdf · uploaded 12 Aug 2024Source
  • DocumentForm 2 as on 30-09-2024.pdf · uploaded 24 Oct 2024Source
  • DocumentForm 2 Dec-2024.pdf · uploaded 4 Mar 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 30/2, 31

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—30 units in all
Address
31 and 30/2, New Satpati Road, DhansarPIN 401404
Village
Dhansar, Palghar taluka
Designated bank account
17
Developed in phases
No

Survey, CTS, gat or plot numbers

30/231

Boundaries

North
Survey No 281 to 315
South
9 Mtr Wide Internal Road
East
Building No-6 Type I
West
Building No-5 Type G

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking30 units

30 units registered

— · 30 units
TypeCarpet areaUnits
——30

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Kalyani Raut—
Chartered accountantBharat Dhonde & Co.—
EngineerOptimax Consulting Structural Engneers—
OtherAmita K. Patil—
OtherAnju Construction—
OtherBldgtech Enterprises—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology