CD Ayodhya Gardens
Deedo IDDP-PAL-GQ07It is due for completion in Dec 2029, with no extension on record; no MahaRERA orders on record; 0% of its units are booked.
Achole, Palghar 401209 · by 1) C D Infratech 2) Chetan H Desai Proprietor of C D Builders & Developers
Buying a flat here?
See every deed registered on it.
It is due for completion in Dec 2029, with no extension on record
- This projectRegistered 29 Sep 2025, completion promised 31 Dec 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPM1241012501017
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PM1241012501017 | 29 Sep 2025 | 31 Dec 2029 | 31 Dec 2029 | 1) C D Infratech 2) Chetan H Desai Proprietor of C D Builders & Developers | Project page |
Documents65
2 documents held by Deedo, 63 filings listed on MahaRERA's project page
Registration certificate (2)
Finance
Show all 65 documentsShow fewer documents
Legal
Migrated
- Withdrawal Update Form 1Form 1 D Wing 15th to 22nd Floor (Oct - Dec 25) (1).pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 1Form 1 D Wing 15th to 22nd Floor (Oct - Dec 25) (1).pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 1FORM1-SEP.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 1FORM1-SEP.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 1Form 1 D Wing - Gr to 7th Floor (Oct - Dec 25).pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 1Form 2 D Wing Gr to 7th Floor (Oct - Dec 25).pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 2Form 2 D Wing 15th to 22nd floor (Oct - DEc 25).pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 2Form 2 D Wing 15th to 22nd floor (Oct - DEc 25).pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 2FORM2 SEP.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 2FORM2 SEP.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 2Form 1 D Wing 8th to 14th floor (Oct - Dec 25) (1).pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 2Form 2 D Wing 8th to 14 Floor (Oct - Dec 25).pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 3Form 3 D wing CD Ayodhya (Oct - Dec).pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 3Form 3 D wing CD Ayodhya (Oct - Dec).pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 3FORM3 SEP_compressed.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 3FORM3 SEP_compressed.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 3Form 3 D wing CD Ayodhya (Oct - Dec).pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 3Form 3 D wing CD Ayodhya (Oct - Dec).pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 1Form 1 CD Ayodhya Gr to 7th Floor - Jan - Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 1Form 1 Cd Ayodhya 15 to 22nd floor - Jan - Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 2CD Ayodhya Form 2 - Jan to Mar 2026.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 2CD Ayodhya Form 2 15th to 22nd Floor Jan - Mar 2026.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 3Form 3-March-26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 3Form 3-March-26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 1CD Ayodhya Gardens Form 1 - 15th to 22nd (1).pdf · uploaded 22 Jul 2026Source
- Withdrawal Update Form 2CD Ayodhya Gradens Form 2 15th to 22nd (1).pdf · uploaded 22 Jul 2026Source
- Withdrawal Update Form 3CD Ayodhya gardens Form 3 (1).pdf · uploaded 22 Jul 2026Source
- Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 1 Aug 2026Source
Technical
- DocumentPlan Wing D_01.pdf · uploaded 5 Sep 2025Source
- DocumentPlan Wing D_02.pdf · uploaded 5 Sep 2025Source
- DocumentPlan Wing D_01.pdf · uploaded 5 Sep 2025Source
- DocumentPlan Wing D_02.pdf · uploaded 5 Sep 2025Source
- DocumentAnnexure A.pdf · uploaded 5 Sep 2025Source
- OthersForm 1.pdf · uploaded 5 Sep 2025Source
- OthersForm 2.pdf · uploaded 5 Sep 2025Source
- OthersLand Area Calculation.pdf · uploaded 5 Sep 2025Source
- DocumentPlan all_1 (2).pdf · uploaded 24 Sep 2025Source
- OthersOther Tech.pdf · uploaded 24 Sep 2025Source
- OthersD WING - DA Gr+7 01.pdf · uploaded 24 Sep 2025Source
- OthersD WING - DA Gr+7 02.pdf · uploaded 24 Sep 2025Source
- OthersD WING - DA Gr+7 03.pdf · uploaded 24 Sep 2025Source
- OthersD WING - DA 8 to14 01.pdf · uploaded 24 Sep 2025Source
- OthersD WING - DA 8 to14 02.pdf · uploaded 24 Sep 2025Source
- OthersD WING - DA 8 to14 03.pdf · uploaded 24 Sep 2025Source
- OthersD WING - DA 8 to14 04.pdf · uploaded 24 Sep 2025Source
- OthersD WING - DA 8 to14 05.pdf · uploaded 24 Sep 2025Source
- OthersD WING - DA 15 to 22 01.pdf · uploaded 24 Sep 2025Source
- OthersD WING - DA 15 to 22 02.pdf · uploaded 24 Sep 2025Source
- OthersD WING - DA 15 to 22 03.pdf · uploaded 24 Sep 2025Source
- OthersD WING - DA 15 to 22 04.pdf · uploaded 24 Sep 2025Source
- OthersSUPPLIMENTORY DEED (CD INFRATECH).pdf · uploaded 24 Sep 2025Source
Technical (Architect)
- DocumentCD Ayodhya Gardens Form 1 - 15th to 22nd (1).pdf · uploaded 22 Jul 2026Source
Technical (Engineer)
- DocumentCD Ayodhya Gradens Form 2 15th to 22nd (1).pdf · uploaded 22 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 51, 52
As registered with MahaRERA and published on its project page
- Project type
- Mixed
- Status on MahaRERA
- Certificate Signed
- Unit types
- —142 units in all
- Address
- Survey No 49, 50, 51, 52, 53, 54, 55, 56, 77 H No 3, AcholePIN 401209
- Village
- Vasai-Virar City (M Corp), Vasai taluka
- Location
- 19.40557, 72.85574
- Land area for this project
- 3,610 sq m (38,853 sq ft)
- Permissible built-up area
- 7,309 sq m (78,676 sq ft)
- Sanctioned built-up area
- 7,309 sq m (78,676 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 212
- Developed in phases
- No
- Also registered as
- Hilltone Arcade, Hilton Arcade
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S.No.49, H.No.3, S.No. 50,51,52,53,54,55, S.No.56, H.No.3, S.No.77 of Village - Achole (Plot-A)
Boundaries
- North
- As per Plan
- South
- As per Plan
- East
- As per Plan
- West
- As per Plan
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking142 units
142 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 142 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Other projects in Achole
- ShamRERA PM1240002602202
- Dhananjay IconRERA PM1240002602053
- Shri Sai Prasad ChslRERA PR1240002602004
- Sanskruti PrideRERA PM1240002601800
- Dharma ResidencyRERA PM1240002601595
- Chandresh Shraddha H Wing Co-Op Hsg Soc LtdRERA PR1240002600195
- Niyara ResidencyRERA PR1240002503062
- New Shivkrupa Chs LtdRERA PM1240002502846
All 28 projects in Achole · Compare CD Ayodhya Gardens with another project