Deedo IDDP-NSK-GYVYCompletion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 10% of its units are booked.
Nashik Road, Nashik 422101 · by Shree Disha Realty
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 25 Jan 2024, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51600054488
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600054488 | 25 Jan 2024 | 31 Dec 2026 | 30 Apr 2027 | Shree Disha Realty | Project page |
Documents51
2 documents held by Deedo, 49 filings listed on MahaRERA's project page
Show all 51 documentsShow fewer documents
Migrated
- 1 b Details of encumbrances concerned to LegalNo Encumbrance - Financial.pdf · uploaded 6 Nov 2023Source
- 2 b Details of encumbrances concerned to LegalNo Encumbrance - Legal.pdf · uploaded 6 Nov 2023Source
- 1 Copy of Layout Approval (in case of layout)Sanctioned Plan.pdf · uploaded 6 Nov 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentSanctioned Plan.pdf · uploaded 6 Nov 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 6 Nov 2023Source
- 1 Declaration about Commencement CertificateDeclaration About CC.pdf · uploaded 6 Nov 2023Source
- 1 Declaration in FORM BForm B - Builder.pdf · uploaded 6 Nov 2023Source
- 1 CERSAI detailsCersai Declaration.pdf · uploaded 6 Nov 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 6 Nov 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 6 Nov 2023Source
- 1 Proforma of Agreement for saleAgreement To Sale.pdf · uploaded 6 Nov 2023Source
- 1 Proforma of Allotment letterAllottment Letter.pdf · uploaded 6 Nov 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank Account.pdf · uploaded 6 Nov 2023Source
- 1 Deviation Report with respect to Allotment letterNo Deviation - Allotment Letter.pdf · uploaded 6 Nov 2023Source
- 1 Deviation Report with respect to model copy of AgreementNo Deviation - Agreement for Sale.pdf · uploaded 6 Nov 2023Source
- 1 Other – TechnicalVerification of CC.pdf · uploaded 22 Nov 2023Source
- 1 Copy of the legal title reportTitle Report.pdf · uploaded 9 Jan 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 23-24 Q4.pdf · uploaded 15 Feb 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 24-25 Q1.pdf · uploaded 15 Feb 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 24-25 Q2.pdf · uploaded 15 Feb 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 24-25 Q3.pdf · uploaded 15 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 SD 23-24 Q4.pdf · uploaded 15 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 SD 24-25 Q1.pdf · uploaded 15 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 SD 24-25 Q2.pdf · uploaded 15 Feb 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 SD 24-25 Q3.pdf · uploaded 15 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 23-24 Q4.pdf · uploaded 15 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 24-25 Q1.pdf · uploaded 15 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 24-25 Q2.pdf · uploaded 15 Feb 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 24-25 Q3.pdf · uploaded 15 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryInventory 31-12-2024.pdf · uploaded 15 Feb 2025View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A - 2024.pdf · uploaded 15 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - 2023-24.pdf · uploaded 15 Feb 2025Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Plot No. 8, Survey No. 48/2/1
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, Shop30 units in all
- Address
- Plot No. 8, Survey No. 48/2/1, Deolali Shiwar, Nashik, Jai Bhavani Road, Near Suman Hospital, Nashik RoadPIN 422101
- Village
- Nashik Road, Nashik taluka
- Land area for this project
- 821 sq m (8,839 sq ft)
- Permissible built-up area
- 2,974 sq m (32,016 sq ft)
- Sanctioned built-up area
- 2,090 sq m (22,498 sq ft)
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Plot No. 8, Survey No. 48/2/1, Deolali Shiwar, Nashik
Boundaries
- North
- Plot No 9
- South
- Plot No 7
- East
- 18 Meter Road
- West
- Plot No 13 and 14
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking30 units
3 of 30 units booked (10%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 60.81 sq m · 655 sq ft | 8 | 0 |
| 2BHK | 61.1 sq m · 658 sq ft | 12 | 0 |
| 2BHK | 62.2 sq m · 670 sq ft | 4 | 2 |
| Shop | 9.36 sq m · 101 sq ft | 1 | 1 |
| Shop | 9.37 sq m · 101 sq ft | 1 | 0 |
| Shop | 14.65 sq m · 158 sq ft | 1 | 0 |
| Shop | 19.64 sq m · 211 sq ft | 1 | 0 |
| Shop | 22.76 sq m · 245 sq ft | 2 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Other projects in Nashik Road
- Skyline AvenueRERA PM1220002601040
- Sujan Co-operative Housing SocietyRERA P51600080794
- Hill Top Heights ApartmentRERA P51600078566
- SterlingRERA P51600055850
- Shilp MeridianRERA P51600055808
- Primrose ResidencyRERA P51600055296
- Shyam PalaceRERA P51600055186
- Ganraj ResidencyRERA P51600053660
All 67 projects in Nashik Road · Compare Nilaya Pride with another project