Jail Road, Nashik 422101 |Promoter: Kiran Patel

Residential / Group HousingRERAP51600011987
1 Sep 2017Registered with MahaRERA
30 Dec 2019Promised completion
1Building
16Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
1BHK, 2BHK16 units in all
Land area for this project
544 sq m (5,860 sq ft)
Permissible built-up area
760 sq m (8,179 sq ft)
Sanctioned built-up area
760 sq m (8,179 sq ft)
Address
65/9 to 12PIN 422101
Designated bank account
Idbi Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.97134, 73.84042
Sai Arcade is at latitude 19.97134, longitude 73.84042.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2019

The latest completion date on record passed 6 years and 10 months ago.

Registered
1 Sep 2017
Promised
30 Dec 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P516000119871 Sep 201730 Dec 2019—Kiran PatelProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Sai Arcade616

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

16 units registered

1BHK · 2 units2BHK · 14 units
TypeCarpet areaUnits
1BHK45.89 sq m · 494 sq ft2
2BHK51.51 sq m · 554 sq ft14

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Sai Arcade

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
  • Sanitary Fittings within the flats / premises70%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyTo be Obtained after Completion0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Septic Tank Outlet connected to municipal Sewer60%
  • Storm Water DrainsWill be completed60%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterWill be provided only if required by NMC DC Rules0%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRWH Near Borewell Completed60%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationWill be completed on completion0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

11 documents held by Deedo, 15 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Copy of the legal title reportTitle Certificate.pdf · uploaded 5 Aug 2017View
  • Details of encumbrancesEncumbrance certificate.pdf · uploaded 5 Aug 2017View
  • Copy of Layout Approval (in case of layout)Commencement Plan.pdf · uploaded 5 Aug 2017View
  • Proforma of Allotment letterAgreement Format.pdf · uploaded 5 Aug 2017View
  • Declaration in FORM BAffidavit _ Sai Arcade.pdf · uploaded 5 Aug 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate _ Sai Arcade.pdf · uploaded 5 Aug 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Cert.pdf · uploaded 5 Aug 2017View
  • Commencement Certificates / NA Order for plotted developmentCommencement Cet _ Sai Arcade.pdf · uploaded 5 Aug 2017View
  • Building Plan Approval (IOD)Commencement Plan.pdf · uploaded 5 Aug 2017View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate.pdf · uploaded 11 Apr 2023View

Promoter documents

  • Legal Title reportTitle Certificate.pdf · uploaded 5 Aug 2017View
  • Declaration Form BAffidavit _ Sai Arcade.pdf · uploaded 5 Aug 2017View

Technical documents

  • Layout ApprovalCommencement Plan.pdfView
  • Building Plan ApprovalCommencement Plan.pdfView

Proforma allotment letter

  • Proforma allotment letterAgreement Format.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Jail Road, Nashik taluka

Survey, CTS, gat or plot numbers

65/9 to 12

As published on MahaRERA's project page

65/9 to 12

Boundaries

North
Colony road
South
Adjoining Sr No 65p
East
Adjoining Property
West
Plot No 8

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr D R Gade—

Source: MahaRERA project page. Contact details are not shown.