Skip to content
Others · 1 building · 84 unitsRERA P51600017010

Devkrupa

Deedo IDDP-NSK-BXD8

MahaRERA shows it completed, after its date was pushed back 1 year and 5 months; no MahaRERA orders on record; 24% of its units are booked.

Igatpuri (M Cl), Nashik 422403 · by D. B. Developers

DeliveryCompletedAs MahaRERA shows · after a 1 yr 5 mo extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales24% booked20 of 84 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year and 5 months

  • This projectRegistered 28 Jun 2018, completion promised 31 May 2019, revised to 30 Oct 2020.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51600017010
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160001701028 Jun 201831 May 201930 Oct 2020D. B. DevelopersProject page
Documents62

28 documents held by Deedo, 34 filings listed on MahaRERA's project page

Title report

Commencement certificate (2)

Encumbrance details (2)

Form B

Form 1 (2)

Show all 62 documentsShow fewer documents

Form 2 (2)

Registration certificate

Extension certificate

Occupancy / completion certificate

  • Occupancy / completion certificate18 Apr 2023ViewSource

Other (5)

Form 2A (2)

Allotment letter (2)

Form 5 (4)

Layout plan (2)

Document library

  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 22 Nov 2017View
  • Copy of the legal title reportSearch Report Title.pdf · uploaded 22 Nov 2017View
  • Proforma of Allotment letterAgreement for Sale.pdf · uploaded 22 Nov 2017View
  • Declaration in FORM BFORM B.pdf · uploaded 12 May 2018View
  • Details of encumbrancesEncumbrance Certificate.pdf · uploaded 12 May 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Page 1 and 2.pdf · uploaded 12 May 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Page 3.pdf · uploaded 12 May 2018View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate Page 1 and 2.pdf · uploaded 12 May 2018View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate Page 3 and 4.pdf · uploaded 12 May 2018View
  • Building Plan Approval (IOD)BLUE PRINT _IGATPURI_PG 1FINAL.pdf · uploaded 16 Jun 2018View
  • Building Plan Approval (IOD)BLUE PRINT _IGATPURI_PG 2 FINAL.pdf · uploaded 16 Jun 2018View
  • Copy of Layout Approval (in case of layout)BLUE PRINT _IGATPURI_PG 1FINAL.pdf · uploaded 16 Jun 2018View
  • Copy of Layout Approval (in case of layout)BLUE PRINT _IGATPURI_PG 2 FINAL.pdf · uploaded 16 Jun 2018View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate Dt-25-2-21.pdf · uploaded 18 Apr 2023View
  • Declaration about Commencement CertificateDeclaration About Commencement Certificate.pdf · uploaded 13 May 2023View
  • Disclosure of sold/ booked inventoryDISCOLSURE OF SOLD_BOOKED INVENTORY.pdf · uploaded 13 May 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Quality Certificate.pdf · uploaded 20 May 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality Assurance Certificate.pdf · uploaded 20 May 2023View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Quality Assurance Certificate.pdf · uploaded 20 May 2023View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 20 May 2023View
  • a Details of encumbrances concerned to FinanceSearch Report for 30 years.pdf · uploaded 20 May 2023View
  • b Details of encumbrances concerned to LegalSearch Report for 30 years.pdf · uploaded 20 May 2023View
  • Proforma of Agreement for saleAgreement for Sale.pdf · uploaded 20 May 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FROM 5_MARCH19.pdf · uploaded 22 May 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FROM 5_MARCH20.pdf · uploaded 22 May 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FROM 5_MARCH21.pdf · uploaded 22 May 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FROM 5_MARCH22.pdf · uploaded 22 May 2023View

Promoter documents

  • Legal Title reportSearch Report Title.pdf · uploaded 22 Nov 2017View
  • Declaration Form BFORM B.pdf · uploaded 12 May 2018View

Technical documents

  • Building Plan ApprovalBLUE PRINT _IGATPURI_PG 1FINAL.pdfView
  • Building Plan ApprovalBLUE PRINT _IGATPURI_PG 2 FINAL.pdfView
  • Layout ApprovalBLUE PRINT _IGATPURI_PG 1FINAL.pdfView
  • Layout ApprovalBLUE PRINT _IGATPURI_PG 2 FINAL.pdfView

Proforma allotment letter

  • Proforma allotment letterAllotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 863/7

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Unit types
BHKA, BHKB, BHKC, Office, RK, Shop82 units in all
Address
863/7, Talegaon Road, IgatpuriPIN 422403
Village
Igatpuri (M Cl), Igatpuri taluka
Land area for this project
1,671 sq m (17,982 sq ft)
Permissible built-up area
2,339 sq m (25,174 sq ft)
Sanctioned built-up area
2,339 sq m (25,174 sq ft)
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

863/7

Land as published on MahaRERA's project page

863/7

Boundaries

North
City Survey No 879 and Road
South
Agricultural Land
East
City Survey No 879 14-A 2
West
Talegaon Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking82 units · 56 parking spaces

82 units registered

BHKA · 6 unitsBHKB · 16 unitsBHKC · 22 unitsOffice · 7 unitsRK · 12 unitsShop · 19 units
TypeCarpet areaUnits
BHKA42.1 sq m · 453 sq ft6
BHKB39.41 sq m · 424 sq ft16
BHKC37.55 sq m · 404 sq ft22
Office7.43 sq m · 80 sq ft1
Office13.48 sq m · 145 sq ft4
Office16.73 sq m · 180 sq ft2
RK25.84 sq m · 278 sq ft12
Shop7.99 sq m · 86 sq ft3
Show all 14 unit rowsShow fewer unit rows
TypeCarpet areaUnits
Shop8.36 sq m · 90 sq ft2
Shop9.29 sq m · 100 sq ft2
Shop10.69 sq m · 115 sq ft4
Shop15.8 sq m · 170 sq ft5
Shop20.45 sq m · 220 sq ft1
Shop21.38 sq m · 230 sq ft2

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000056
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Devkrupa

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure90%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyWORK IN PROGRESS25%
  • Sewerage (Chamber, Lines, Septic Tank , STP)WORK IN PROGRESS25%
  • Storm Water DrainsWORK IN PROGRESS25%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingWORK IN PROGRESS25%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationELECTRIC ROOM IS CONTRUCTED20%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSadanand Adole—
OtherVivek Infradevelopers Pvt Ltd—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology