Town Square Apartment
Deedo IDDP-NSK-ST70Completion was pushed back 1 year to Dec 2025, and that date has passed too; no MahaRERA orders on record; 23% of its units are booked.
Deolali (Cb), Nashik 422401 · by Harak Patil Realtors · 67% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year to Dec 2025, and that date has passed too
- This projectRegistered 26 Jun 2021, completion promised 30 Dec 2024, revised to 31 Dec 2025, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
15 buildings
Open a building to see every flat, floor by floor.
- 6gSize not on record0% booked
- A12 floors · 6 units17% booked
- A21 floor · 3 units0% booked
- B3 floors · 18 units44% booked
- B11Size not on record0% booked
- Building (P51600029695)Size not on record9% booked
- C3 floors · 10 units80% booked
- D3 floors · 10 units50% booked
- E2 floors · 18 units0% booked
- F2 floors · 18 units50% booked
- G3 floors · 78 units6% booked
- H3 floors · 2 units100% booked
Show all 15 buildingsShow fewer buildings
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51600029695
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600029695 | 26 Jun 2021 | 30 Dec 2024 | 31 Dec 2025 | Harak Patil Realtors | Project page |
Documents81
3 documents held by Deedo, 78 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN CardPAN CARD - HARAK PATIL REALTORS.pdf · uploaded 5 Jun 2021Source
Show all 81 documentsShow fewer documents
Migrated
- 1 PAN CardPAN CARD - HARAK PATIL REALTORS.pdf · uploaded 5 Jun 2021Source
- 1 Copy of the legal title reportTITLE SPEARCH REPORT (1).pdf · uploaded 5 Jun 2021Source
- 1 Details of encumbrancesENCUMBRANCE CERTIFICATE.pdf · uploaded 5 Jun 2021Source
- 1 Copy of Layout Approval (in case of layout)PLAN LAYOUT.pdf · uploaded 5 Jun 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentharak 1 compressed.pdf · uploaded 5 Jun 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentharak 2_compressed.pdf · uploaded 5 Jun 2021Source
- 3 Building Plan Approval / NA Order for plotted developmentharak 3_compressed.pdf · uploaded 5 Jun 2021Source
- 4 Building Plan Approval / NA Order for plotted developmentharak 4-1_compressed.pdf · uploaded 5 Jun 2021Source
- 5 Building Plan Approval / NA Order for plotted developmentharak 5_compressed (1).pdf · uploaded 5 Jun 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE (1).pdf · uploaded 5 Jun 2021Source
- 1 Declaration in FORM BFORM B affidavit town square.pdf · uploaded 5 Jun 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTS CERTIFICATE .pdf · uploaded 5 Jun 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_TOWN SQUARE.pdf · uploaded 5 Jun 2021Source
- 1 Proforma of Allotment letterAGREEMENT TO SALE (3).pdf · uploaded 5 Jun 2021Source
- 2 Proforma of Allotment letterLEETER OF ALLOTMENT (1).pdf · uploaded 5 Jun 2021Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Partnership deed_compressed_compressed.pdf · uploaded 5 Jun 2021Source
- 1 Declaration about Commencement Certificateformat D.pdf · uploaded 19 Jun 2021Source
- 1 Declaration in FORM BForm B.pdf · uploaded 27 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Form -1 31_03_2022.pdf · uploaded 27 Jan 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)2 Form - 1 31_3_2023.pdf · uploaded 27 Jan 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 Form - 1 31_3_2024.pdf · uploaded 27 Jan 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)4 form 1 30-6-24.pdf · uploaded 27 Jan 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 Form- 1 30_09_2024.pdf · uploaded 27 Jan 2025Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)6 Form - 1 31_12_2024.pdf · uploaded 27 Jan 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)4 Form 2 30-6-24.pdf · uploaded 27 Jan 2025Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)6 Form 2 31-12-24.pdf · uploaded 27 Jan 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)5 Form 2 30-9-24.pdf · uploaded 27 Jan 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Form -2 31-3-23.pdf · uploaded 27 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Form- 2 31-3-22.pdf · uploaded 27 Jan 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)3 Form -2 31-3-24.pdf · uploaded 27 Jan 2025Source
- 6 Disclosure of sold/ booked inventory6 Disclosure 31-12-24.pdf · uploaded 27 Jan 2025View
- 5 Disclosure of sold/ booked inventory5 Disclosure 30-9-24.pdf · uploaded 27 Jan 2025Source
- 4 Disclosure of sold/ booked inventory4 Disclosure 30-6-24.pdf · uploaded 27 Jan 2025Source
- 3 Disclosure of sold/ booked inventory3 Disclosure 31-3-24.pdf · uploaded 27 Jan 2025Source
- 2 Disclosure of sold/ booked inventory2 Disclosure of sold 31-3-23.pdf · uploaded 27 Jan 2025Source
- 1 Disclosure of sold/ booked inventory1 Disclosure of sold HPR 31-3-2022.pdf · uploaded 27 Jan 2025Source
- 1 CERSAI detailsDeclaration Nil CERSAI.pdf · uploaded 27 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 2A 21-22.pdf · uploaded 27 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 21-22.pdf · uploaded 27 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 22-23.pdf · uploaded 27 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 23-24.pdf · uploaded 27 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_March 22.pdf · uploaded 28 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_March 23.pdf · uploaded 28 Jan 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_March 24.pdf · uploaded 28 Jan 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_June 24.pdf · uploaded 28 Jan 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Sep 24.pdf · uploaded 28 Jan 2025Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Dec 24.pdf · uploaded 28 Jan 2025Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)RERA Audit Report_21-22.pdf · uploaded 28 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA Audit Report_22-23.pdf · uploaded 28 Jan 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)RERA Audit Report_23-24.pdf · uploaded 28 Jan 2025Source
- 1 Declaration in FORM BHarak Patil realtor Rera notry.pdf · uploaded 21 Mar 2025Source
- 1 Other – TechnicalUpdation Town square aprt.pdf · uploaded 21 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Final.pdf · uploaded 9 Apr 2025Source
Technical
- DocumentPLAN LAYOUT.pdf · uploaded 5 Jun 2021Source
- Documentharak 1 compressed.pdf · uploaded 5 Jun 2021Source
- Documentharak 2_compressed.pdf · uploaded 5 Jun 2021Source
- Documentharak 3_compressed.pdf · uploaded 5 Jun 2021Source
- Documentharak 4-1_compressed.pdf · uploaded 5 Jun 2021Source
- Documentharak 5_compressed (1).pdf · uploaded 5 Jun 2021Source
- Other – TechnicalUpdation Town square aprt.pdf · uploaded 21 Mar 2025Source
Technical (Architect)
- DocumentARCHITECTS CERTIFICATE .pdf · uploaded 5 Jun 2021Source
- Document1 Form -1 31_03_2022.pdf · uploaded 27 Jan 2025Source
- Document2 Form - 1 31_3_2023.pdf · uploaded 27 Jan 2025Source
- Document3 Form - 1 31_3_2024.pdf · uploaded 27 Jan 2025Source
- Document4 form 1 30-6-24.pdf · uploaded 27 Jan 2025Source
- Document5 Form- 1 30_09_2024.pdf · uploaded 27 Jan 2025Source
- Document6 Form - 1 31_12_2024.pdf · uploaded 27 Jan 2025Source
Technical (Engineer)
- Document1 Form- 2 31-3-22.pdf · uploaded 27 Jan 2025Source
- Document2 Form -2 31-3-23.pdf · uploaded 27 Jan 2025Source
- Document3 Form -2 31-3-24.pdf · uploaded 27 Jan 2025Source
- Document4 Form 2 30-6-24.pdf · uploaded 27 Jan 2025Source
- Document5 Form 2 30-9-24.pdf · uploaded 27 Jan 2025Source
- Document6 Form 2 31-12-24.pdf · uploaded 27 Jan 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel SURVEY NO. 4/2A/2
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, Shop, 1BHK, Bungalow164 units in all
- Address
- Survey No. 4/2a/2, Survey No. 4/2a/2, Bhagur Shivar, Bhagur Pandurli Road, Deolali Camp, NashikPIN 422401
- Village
- Deolali (CB), Nashik taluka
- Land area for this project
- 7,361 sq m (79,233 sq ft)
- Permissible built-up area
- 3,626 sq m (39,026 sq ft)
- Sanctioned built-up area
- 3,626 sq m (39,026 sq ft)
- Designated bank account
- 229
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SURVEY NO. 4/2A/2
Boundaries
- North
- Survey No 4-1
- South
- Road
- East
- Bhagur Pandurli Road
- West
- Survey No 4-2a-1
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking164 units
38 of 164 units booked (23%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A1 | 2BHK | 81.34 sq m · 876 sq ft | 5 | 0 |
| A1 | 2BHK | 87.82 sq m · 945 sq ft | 1 | 1 |
| A2 | Shop | 16.12 sq m · 174 sq ft | 1 | 0 |
| A2 | Shop | 17.23 sq m · 185 sq ft | 1 | 0 |
| A2 | Shop | 17.33 sq m · 187 sq ft | 1 | 0 |
| B | 1BHK | 33.9 sq m · 365 sq ft | 2 | 1 |
| B | 1BHK | 34.35 sq m · 370 sq ft | 2 | 0 |
| B | 1BHK | 35.22 sq m · 379 sq ft | 7 | 1 |
Show all 31 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| B | 1BHK | 45.69 sq m · 492 sq ft | 2 | 2 |
| B | 1BHK | 46.2 sq m · 497 sq ft | 1 | 1 |
| B | 2BHK | 46.45 sq m · 500 sq ft | 1 | 0 |
| B | 2BHK | 61.39 sq m · 661 sq ft | 3 | 3 |
| C | 1BHK | 36.22 sq m · 390 sq ft | 1 | 0 |
| C | 1BHK | 47.2 sq m · 508 sq ft | 3 | 3 |
| C | 1BHK | 47.88 sq m · 515 sq ft | 2 | 1 |
| C | 2BHK | 62.46 sq m · 672 sq ft | 4 | 4 |
| D | 1BHK | 36.22 sq m · 390 sq ft | 2 | 0 |
| D | 1BHK | 47.2 sq m · 508 sq ft | 2 | 2 |
| D | 1BHK | 47.88 sq m · 515 sq ft | 4 | 1 |
| D | 2BHK | 62.46 sq m · 672 sq ft | 2 | 2 |
| E | Shop | 25.53 sq m · 275 sq ft | 18 | 0 |
| F | Shop | 25.53 sq m · 275 sq ft | 18 | 9 |
| G | 1BHK | 33.49 sq m · 360 sq ft | 4 | 1 |
| G | 1BHK | 34.99 sq m · 377 sq ft | 12 | 1 |
| G | 1BHK | 46.28 sq m · 498 sq ft | 4 | 0 |
| G | 1BHK | 47.01 sq m · 506 sq ft | 3 | 1 |
| G | 2BHK | 61.95 sq m · 667 sq ft | 1 | 1 |
| G | Shop | 15.25 sq m · 164 sq ft | 16 | 1 |
| G | Shop | 16.95 sq m · 182 sq ft | 38 | 0 |
| H | Shop | 16.95 sq m · 182 sq ft | 2 | 2 |
| I | Bungalow | 150.71 sq m · 1,622 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals11
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Dharam H Papneja | — |
| Chartered accountant | Jagdish Patil | — |
| Engineer | Sunil Patel | — |
| Other | Godse Fabricators | — |
| Other | Jagan G Chavan | — |
| Other | Jitendrakumar Mohan Sahu | — |
| Other | Jitendra S Chaurasiya | — |
| Other | Mehandi Hasan | — |
Show all 11 professionalsShow fewer professionals
| Role | Name | Registration no. |
|---|---|---|
| Other | Nitin M Jadhav | — |
| Other | Sham Vishwakarma | — |
| Other | Uttam Pable | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Deolali (Cb)
- Shri Ram Residence ParkRERA PR1220002601993
- Ishwar PremRERA PR1220002601847
- Shri Anant AvenueRERA PR1220002601755
- Shubhsankalp Co-Operative Housing Society LimitedRERA PM1220002600757
- Shree GurudarshanRERA PR1220002600346
- Sagar Co Op Housing SocietyRERA PR1220002502585
- Ayodhya Central ParkRERA P51600079639
- Yamuna ParkRERA P51600079414
All 50 projects in Deolali (Cb) · Compare Town Square Apartment with another project