Residential / Group Housing · 1 buildingRERA P51100050996

Vrandawan Apartment

Deedo IDDP-NAN-7807

Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record.

Koutha, Nanded 431603 · by Visava Developers

Delivery11 mo past duePromised Dec 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 19 May 2023, completion promised 30 Dec 2025, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51100050996
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5110005099619 May 202330 Dec 202530 Dec 2025Visava DevelopersProject page
Documents77

1 document held by Deedo, 76 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardVISAVA PAN_compressed.pdf · uploaded 14 Mar 2023Source

Legal

  • Legal Title reportlegal title report raju sambhi gore landowner-merged.pdf · uploaded 14 Mar 2023Source
  • Declaration Form BFORM B BALAJI EBITDAR.pdf · uploaded 14 Mar 2023Source
  • Declaration Form BFORM B MUDHOL.pdf · uploaded 14 Mar 2023Source
  • Declaration Form BFORM B RAJU GORE.pdf · uploaded 14 Mar 2023Source
  • Declaration Form BFORM B BALAJI EBITDAR.pdf · uploaded 14 Mar 2023Source

Migrated

  • 1 PAN CardVISAVA PAN_compressed.pdf · uploaded 14 Mar 2023Source
Show all 77 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportlegal title report raju sambhi gore landowner-merged.pdf · uploaded 14 Mar 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentMAP N PERMISSION LETTER-3_compressed.pdf · uploaded 14 Mar 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentMAP N PERMISSION LETTER-4_compressed (1).pdf · uploaded 14 Mar 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentMAP N PERMISSION LETTER-1-2.pdf · uploaded 14 Mar 2023Source
  • 1 Declaration about Commencement Certificatescanner_20230401_124629 (1).pdf · uploaded 14 Mar 2023Source
  • 1 Declaration in FORM BFORM B BALAJI EBITDAR.pdf · uploaded 14 Mar 2023Source
  • 2 Declaration in FORM BFORM B MUDHOL.pdf · uploaded 14 Mar 2023Source
  • 3 Declaration in FORM BFORM B RAJU GORE.pdf · uploaded 14 Mar 2023Source
  • 4 Declaration in FORM BFORM B BALAJI EBITDAR.pdf · uploaded 14 Mar 2023Source
  • 1 CERSAI detailscersai declaration visawa.pdf · uploaded 15 Mar 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FINAL CA CERTIFICATE (1).pdf · uploaded 15 Mar 2023Source
  • 1 a Details of encumbrances concerned to Financebond 2_compressed.pdf · uploaded 16 Mar 2023Source
  • 1 b Details of encumbrances concerned to Legalbond 2_compressed.pdf · uploaded 16 Mar 2023Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsannexure a disclosure of interest in other real estate organizations.pdf · uploaded 16 Mar 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A bank declaration.pdf · uploaded 16 Mar 2023Source
  • 1 Deviation Report with respect to Allotment letterbond 3_compressed.pdf · uploaded 16 Mar 2023Source
  • 1 Deviation Report with respect to model copy of Agreementbond 3_compressed.pdf · uploaded 16 Mar 2023Source
  • 1 Proforma of Allotment letterallotment.pdf · uploaded 17 Mar 2023Source
  • 1 Copy of Layout Approval (in case of layout)FINAL LAYOUT_compressed.pdf · uploaded 18 Mar 2023Source
  • 1 Proforma of Agreement for saleVIKRI karar - RERA-1.pdf · uploaded 18 Mar 2023Source
  • 2 Declaration about Commencement Certificatescanner_20230401_124629 (1).pdf · uploaded 1 Apr 2023Source
  • 2 a Details of encumbrances concerned to FinanceNO ENCUMBRANCE CONCERN TO LEGAL.pdf · uploaded 10 Apr 2023Source
  • 3 a Details of encumbrances concerned to Finance10-04-23, 6_15 PM Microsoft Lens.pdf · uploaded 10 Apr 2023Source
  • 4 a Details of encumbrances concerned to FinanceNO ENCUMBRANCE CONCERN TO LEGAL.pdf · uploaded 10 Apr 2023Source
  • 2 b Details of encumbrances concerned to LegalNO ENCUMBRANCE CONCERN TO LEGAL.pdf · uploaded 10 Apr 2023Source
  • 3 b Details of encumbrances concerned to Legal10-04-23, 6_15 PM Microsoft Lens.pdf · uploaded 10 Apr 2023Source
  • 4 b Details of encumbrances concerned to LegalNO ENCUMBRANCE CONCERN TO LEGAL.pdf · uploaded 10 Apr 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Self Declaration-2.pdf · uploaded 12 Mar 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Self Declaration-1.pdf · uploaded 12 Mar 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Self Declaration-3.pdf · uploaded 12 Mar 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Self Declaration-2.pdf · uploaded 12 Mar 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Self Declaration-1.pdf · uploaded 12 Mar 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Self Declaration-3.pdf · uploaded 12 Mar 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Self Declaration-2.pdf · uploaded 12 Mar 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Self Declaration-1.pdf · uploaded 12 Mar 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Self Declaration-3.pdf · uploaded 12 Mar 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)From 1 Jun23.pdf · uploaded 28 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Sep23.pdf · uploaded 28 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Dec23.pdf · uploaded 28 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Mar24.pdf · uploaded 28 Feb 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Jun24.pdf · uploaded 28 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Jun23.pdf · uploaded 28 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sep23.pdf · uploaded 28 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Dec23.pdf · uploaded 28 Feb 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Mar24.pdf · uploaded 28 Feb 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Jun24.pdf · uploaded 28 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 Sep24_001.pdf · uploaded 20 Mar 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 Dec24_001.pdf · uploaded 20 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Sep24_001.pdf · uploaded 20 Mar 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Dec24_001.pdf · uploaded 20 Mar 2025Source

Technical

  • DocumentMAP N PERMISSION LETTER-3_compressed.pdf · uploaded 14 Mar 2023Source
  • DocumentMAP N PERMISSION LETTER-4_compressed (1).pdf · uploaded 14 Mar 2023Source
  • DocumentFINAL LAYOUT_compressed.pdf · uploaded 18 Mar 2023Source

Technical (Architect)

  • DocumentSelf Declaration-3.pdf · uploaded 12 Mar 2024Source
  • DocumentFrom 1 Jun23.pdf · uploaded 28 Feb 2025Source
  • DocumentForm 1 Sep23.pdf · uploaded 28 Feb 2025Source
  • DocumentForm 1 Dec23.pdf · uploaded 28 Feb 2025Source
  • DocumentForm 1 Mar24.pdf · uploaded 28 Feb 2025Source
  • DocumentForm 1 Jun24.pdf · uploaded 28 Feb 2025Source
  • DocumentFORM-1 Sep24_001.pdf · uploaded 20 Mar 2025Source
  • DocumentFORM-1 Dec24_001.pdf · uploaded 20 Mar 2025Source

Technical (Engineer)

  • DocumentSelf Declaration-3.pdf · uploaded 12 Mar 2024Source
  • DocumentForm 2 Jun23.pdf · uploaded 28 Feb 2025Source
  • DocumentForm 2 Sep23.pdf · uploaded 28 Feb 2025Source
  • DocumentForm 2 Dec23.pdf · uploaded 28 Feb 2025Source
  • DocumentForm 2 Mar24.pdf · uploaded 28 Feb 2025Source
  • DocumentForm 2 Jun24.pdf · uploaded 28 Feb 2025Source
  • DocumentFORM-2 Sep24_001.pdf · uploaded 20 Mar 2025Source
  • DocumentFORM-2 Dec24_001.pdf · uploaded 20 Mar 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 229

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Address
229, Kautha, KauthaPIN 431603
Village
Nanded Waghala (M Corp.), Nanded taluka
Land area for this project
719 sq m (7,738 sq ft)
Permissible built-up area
2,300 sq m (24,752 sq ft)
Sanctioned built-up area
2,300 sq m (24,752 sq ft)
Designated bank account
212
Developed in phases
No

Survey, CTS, gat or plot numbers

229

Land as published on MahaRERA's project page

229

Boundaries

North
9 M Road
South
Part Gut 229
East
9 M Road
West
Part Gut 229

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShailesh Vakharia—
Chartered accountantCA Shailendra V Wattamwar—
EngineerStructeq Consulting Engineers—

Source: MahaRERA project page. Contact details are not shown.