7 projects under 8 MahaRERA registrations, registered 2021–2026. 25% have a completion date extended beyond the one promised.
Locality
7RERA projects
8Registrationssome projects hold several
6Completion still due2 past their completion date
4 monthsMedian extension beyond promised date25% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2021 | 1 |
| 2022 | 2 |
| 2023 | 0 |
| 2024 | 3 |
| 2025 | 0 |
| 2026 | 2 |
Projects in Zari
7 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Harihar Nagar Zari Phase II Building No. 4 & 5Harihar Infrastructure Development Corporation Limited | PR1190002502559 | 2 Mar 2026 | 31 Dec 2035 | 30 Apr 2036 | Extended 4 mo | 0 |
| Krishnam Nagari - 8Alliance Hari Om Infra | PP1190002502047 | 12 Jan 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Krishna NagariAnkit Pankaj Dalmia | P50500054708, P50500054743 | 6 Feb 2024 | 31 Dec 2028 | 31 Dec 2028 | Not yet due | 0 |
| Krishna Nagari - 6Jagriti Suppliers Private Limited | P50500054264 | 10 Jan 2024 | 30 Jun 2028 | 30 Jun 2028 | Not yet due | 0 |
| Shivtirth Nagar - 4Sharma Associates | P50500033701 | 2 Mar 2022 | 31 Dec 2027 | 31 Dec 2027 | Not yet due | 0 |
| Prime PlatinumUmakant Vitthal Mendhe | P50500033201 | 9 Feb 2022 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Sharma Lay Out - ZariAnil Radheshyam Sharma | P50500027896 | 14 Jan 2021 | 30 Jun 2025 | 30 Jun 2025 | Promised date passed | 0 |
Other localities in Nagpur (Rural)
Most active promoters
By projects registered here, as named on MahaRERA.
- Alliance Hari Om Infra1 project
- Anil Radheshyam Sharma1 project
- Ankit Pankaj Dalmia1 project
- Harihar Infrastructure Development Corporation Limited1 project
- Jagriti Suppliers Private Limited1 project
- Sharma Associates1 project
- Umakant Vitthal Mendhe1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology