Skip to content
Plotted · 2 buildings · 92 unitsRERA P50500047839 +1

Gurukul

Deedo IDDP-NGP-ZW86

Completion was pushed back 4 months, to Mar 2033; no MahaRERA orders on record; 72% of its units are booked.

Waranga, Nagpur 441108 · by Prakash Sales Corporation

DeliveryExtended 4 moPromised Nov 2032 · now due Mar 2033RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales72% booked66 of 92 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Mar 2033

  • P50500047839Registered 28 Nov 2022, completion promised 31 Oct 2032, revised to 28 Feb 2033.
  • P50500048905Registered 24 Jan 2023, completion promised 30 Nov 2032, revised to 30 Mar 2033.

No extension certificate on record.

2 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations2
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050004783928 Nov 202231 Oct 203228 Feb 2033Prakash Sales CorporationProject page
P5050004890524 Jan 202330 Nov 203230 Mar 2033Prakash Sales CorporationProject page
Documents270

87 documents held by Deedo, 183 filings listed on MahaRERA's project page

Registration certificate (2)

  • Registration certificateP50500047839 · 21 May 2024ViewSource
  • Registration certificateP50500048905 · 21 May 2024ViewSource

Other (24)

  • OtherP50500047839 · Date not statedView
  • OtherP50500047839 · Date not statedView
  • OtherP50500047839 · Date not statedView
  • OtherP50500047839 · Date not statedView
  • OtherP50500047839 · Date not statedView
  • OtherP50500048905 · Date not statedView
Show all 270 documentsShow fewer documents

Other (24)

  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView
  • OtherP50500048905 · Date not statedView

Building plan

  • Building planP50500047839 · Date not statedView

Commencement certificate (3)

  • Commencement certificateP50500047839 · Date not statedView
  • Commencement certificateP50500048905 · Date not statedView
  • Commencement certificateP50500048905 · Date not statedView

Form B (2)

  • Form BP50500047839 · Date not statedView
  • Form BP50500048905 · Date not statedView

Layout plan (11)

  • Layout planP50500047839 · Date not statedView
  • Layout planP50500047839 · Date not statedView
  • Layout planP50500047839 · Date not statedView
  • Layout planP50500047839 · Date not statedView
  • Layout planP50500048905 · Date not statedView
  • Layout planP50500048905 · Date not statedView
  • Layout planP50500048905 · Date not statedView
  • Layout planP50500048905 · Date not statedView
  • Layout planP50500048905 · Date not statedView
  • Layout planP50500048905 · Date not statedView
  • Layout planP50500048905 · Date not statedView

Form 1 (39)

  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500047839 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView
  • Form 1P50500048905 · Date not statedView

Form 2 (2)

  • Form 2P50500047839 · Date not statedView
  • Form 2P50500048905 · Date not statedView

Allotment letter

  • Allotment letterP50500048905 · Date not statedView

Title report

  • Title reportP50500048905 · Date not statedView

Encumbrance details

  • Encumbrance detailsP50500048905 · Date not statedView

Legal

  • Legal Title reportP50500047839 · Legal Title Rep Ram A Joshi.pdf · uploaded 11 Nov 2022Source
  • Declaration Form BP50500047839 · Form B Affidavit cum Declaration.pdf · uploaded 11 Nov 2022View
  • Declaration Form BP50500048905 · Form- B.pdf · uploaded 7 Dec 2022View
  • Legal Title reportP50500048905 · Legal Title report.pdf · uploaded 22 Dec 2022View
  • OthersP50500048905 · NMRDA Agreement 26Dec22_compressed.pdf · uploaded 18 Aug 2025Source

Migrated

  • 1 PAN CardP50500047839 · PSC PAN.pdf · uploaded 11 Nov 2022Source
  • 1 Copy of the legal title reportP50500047839 · Legal Title Rep Ram A Joshi.pdf · uploaded 11 Nov 2022Source
  • 1 a Details of encumbrances concerned to FinanceP50500047839 · Encum Cert.pdf · uploaded 11 Nov 2022Source
  • 1 b Details of encumbrances concerned to LegalP50500047839 · Encum Cert.pdf · uploaded 11 Nov 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentP50500047839 · NA Order Gurukul 2 30SEPT.pdf · uploaded 11 Nov 2022View
  • 1 Commencement Certificates / NA Order for plotted developmentP50500047839 · NA Order Gurukul 2 30SEPT.pdf · uploaded 11 Nov 2022View
  • 1 Declaration about Commencement CertificateP50500047839 · Com cert Declaration.pdf · uploaded 11 Nov 2022View
  • 1 Declaration in FORM BP50500047839 · Form B Affidavit cum Declaration.pdf · uploaded 11 Nov 2022View
  • 1 CERSAI detailsP50500047839 · CERSAI_Search_Report_200251897471_For_Asset_Based_Search_11_11_2022_14_24_48_999.pdf · uploaded 11 Nov 2022View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · CA certificate Gurukul 2_compressed.pdf · uploaded 11 Nov 2022View
  • 1 Proforma of Allotment letterP50500047839 · Model Form Of Allotment Letter .pdf · uploaded 11 Nov 2022Source
  • 1 Proforma of Agreement for saleP50500047839 · Proforma Agreement Prakash Sales Corp.pdf · uploaded 11 Nov 2022Source
  • 1 Deviation Report with respect to Allotment letterP50500047839 · Deviation Report All Letter.pdf · uploaded 11 Nov 2022Source
  • 1 Deviation Report with respect to model copy of AgreementP50500047839 · Deviation Report Agreement.pdf · uploaded 11 Nov 2022Source
  • 1 Copy of Layout Approval (in case of layout)P50500047839 · MAP GURUKUL_compressed.pdf · uploaded 12 Nov 2022View
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP50500047839 · Format A Bank F.pdf · uploaded 12 Nov 2022Source
  • 1 PAN CardP50500048905 · PSC PAN.pdf · uploaded 7 Dec 2022View
  • 1 Building Plan Approval / NA Order for plotted developmentP50500048905 · NA Order.pdf · uploaded 7 Dec 2022View
  • 1 Commencement Certificates / NA Order for plotted developmentP50500048905 · NA Order.pdf · uploaded 7 Dec 2022View
  • 1 Declaration about Commencement CertificateP50500048905 · declaration comm.pdf · uploaded 7 Dec 2022View
  • 1 Declaration in FORM BP50500048905 · Form- B.pdf · uploaded 7 Dec 2022View
  • 1 CERSAI detailsP50500048905 · CERSAI_Search_Report_200254225588_For_Asset_Based_Search_07_12_2022_19_18_22_329.pdf · uploaded 7 Dec 2022Source
  • 1 Proforma of Allotment letterP50500048905 · Model Allotment letter '.pdf · uploaded 7 Dec 2022View
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP50500048905 · formet A.pdf · uploaded 7 Dec 2022Source
  • 1 Deviation Report with respect to Allotment letterP50500048905 · Allotment letter.pdf · uploaded 7 Dec 2022View
  • 1 Deviation Report with respect to model copy of AgreementP50500048905 · Deviation report of agreement.pdf · uploaded 7 Dec 2022View
  • 1 Copy of the legal title reportP50500048905 · Legal Title report.pdf · uploaded 22 Dec 2022View
  • 1 a Details of encumbrances concerned to FinanceP50500048905 · encumbrance certificate.pdf · uploaded 22 Dec 2022View
  • 1 b Details of encumbrances concerned to LegalP50500048905 · encumbrance certificate.pdf · uploaded 22 Dec 2022View
  • 1 Copy of Layout Approval (in case of layout)P50500048905 · Gurukul 3 Final Sanction Map-compressed.pdf · uploaded 22 Dec 2022View
  • 1 Proforma of Agreement for saleP50500048905 · Gurukul 3 Agrt to Sale_compressed.pdf · uploaded 30 Dec 2022View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500048905 · From-3 Gurukul 3.pdf · uploaded 4 Jan 2023View
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP50500048905 · Ann A Ankit_merged.pdf · uploaded 6 Jan 2023View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500047839 · arc cert G2 310323.pdf · uploaded 1 Sep 2023View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500047839 · arc cer G2 300623.pdf · uploaded 1 Sep 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500047839 · eng cert G2 310323.pdf · uploaded 1 Sep 2023View
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500047839 · eng cert G2 300623.pdf · uploaded 1 Sep 2023View
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · CA Cert G2 310323.pdf · uploaded 1 Sep 2023View
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · CA Cert G2 300623.pdf · uploaded 1 Sep 2023View
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP50500047839 · New Annex A Prakash sale corp 010923.pdf · uploaded 1 Sep 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500048905 · ARCHCERT G3 310323.pdf · uploaded 4 Sep 2023View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500048905 · Arch cert G3 300623.pdf · uploaded 4 Sep 2023View
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500048905 · ENGCERT G3 31032023.pdf · uploaded 4 Sep 2023View
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500048905 · Eng Cert G3 300623.pdf · uploaded 4 Sep 2023View
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · G2 CA CERT 310323.pdf · uploaded 5 Sep 2023View
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · G2 CA CERT 300623.pdf · uploaded 5 Sep 2023View
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500048905 · G3 CA CERT 310323.pdf · uploaded 5 Sep 2023View
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500048905 · G3 CA CERT 300623.pdf · uploaded 5 Sep 2023View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P50500047839 · Form 2A G2.pdf · uploaded 6 Sep 2023View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P50500048905 · FORM 2A G3.pdf · uploaded 6 Sep 2023View
  • 1 Disclosure of sold/ booked inventoryP50500047839 · disclosure of sold book inventory G2.pdf · uploaded 25 Sep 2023View
  • 1 Disclosure of sold/ booked inventoryP50500048905 · disclosure of sold booked inventory G3.pdf · uploaded 25 Sep 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P50500047839 · Gurukul 2 Form 5.pdf · uploaded 26 Sep 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P50500048905 · Gurukul 3 FOrm 5.pdf · uploaded 26 Sep 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500047839 · G2 sept 23 eng cert F.pdf · uploaded 20 Oct 2023View
  • 2 Disclosure of sold/ booked inventoryP50500047839 · sold booked inv G2 sept23 F.pdf · uploaded 20 Oct 2023View
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500048905 · G 3 sept 23 eng cert F.pdf · uploaded 20 Oct 2023View
  • 2 Disclosure of sold/ booked inventoryP50500048905 · dis of sold n booked inventory G3.pdf · uploaded 20 Oct 2023View
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500048905 · form 3CA cer 18-10-23.pdf · uploaded 20 Oct 2023View
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500047839 · G2 form1arc cer 30 sept23.pdf · uploaded 21 Oct 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · G2 CA cert 30 sept 23.pdf · uploaded 21 Oct 2023View
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · tableC.pdf · uploaded 21 Oct 2023View
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500048905 · G3 form 1 arc cer 30sept 23.pdf · uploaded 21 Oct 2023View
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500047839 · arc cer 31-12-2022.pdf · uploaded 7 Nov 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500047839 · engineering cer 31-12-2022.pdf · uploaded 7 Nov 2023View
  • 3 Disclosure of sold/ booked inventoryP50500047839 · sold unsold inventory g3 dec22.pdf · uploaded 7 Nov 2023View
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · CAcer2-11-23.pdf · uploaded 7 Nov 2023View
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500047839 · G2 ENG CERT 31DEC23.pdf · uploaded 27 Jan 2024View
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · G2 FORM 3 31DEC23.pdf · uploaded 27 Jan 2024View
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500048905 · G3 ENG CERT 31DEC23.pdf · uploaded 27 Jan 2024View
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500048905 · G3 FORM 3 31DEC23.pdf · uploaded 27 Jan 2024View
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500047839 · G2 Arch cert.pdf · uploaded 29 Jan 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500048905 · G3 Arch cert.pdf · uploaded 29 Jan 2024View
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500047839 · G2 ARCH CERT MAR 24.pdf · uploaded 4 May 2024View
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500047839 · G2 ENGG CERT MAR24.pdf · uploaded 4 May 2024View
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · G2 FORM 3 MAR24.pdf · uploaded 4 May 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500048905 · G3 ARCH CERT MAR 24.pdf · uploaded 4 May 2024View
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500048905 · G3 ENGG CERT MAR 24.pdf · uploaded 4 May 2024View
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500048905 · G3 FORM 3 MAR24.pdf · uploaded 4 May 2024View
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500048905 · G3 FORM 3 MAR 24 Rf.pdf · uploaded 9 May 2024View
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500047839 · FORM -1 GURUKUL 2 30june24.pdf · uploaded 2 Aug 2024View
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500047839 · FORM 2 GURUKUL 2 30june24.pdf · uploaded 2 Aug 2024View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P50500047839 · FORM 2A GURUKUL 2 30june24.pdf · uploaded 2 Aug 2024View
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · FORM 3 GURUKUL 2 30june24_compressed.pdf · uploaded 2 Aug 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500048905 · FORM 1 G 3 30june24.pdf · uploaded 2 Aug 2024View
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500048905 · FORM -2 G3 30JUNE24.pdf · uploaded 2 Aug 2024View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P50500048905 · FORM -2A GURUKUL 3 30june2024.pdf · uploaded 2 Aug 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500048905 · (GURUKUL 3)CA CERTIFICATE 30-06-2024_compressed.pdf · uploaded 5 Aug 2024View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500047839 · gurukul 2 sept24 from 1.pdf · uploaded 21 Oct 2024View
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · gurukul 2 Oct24 from 3_compressed.pdf · uploaded 21 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500047839 · gurukul 2 sept24 from 2.pdf · uploaded 21 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500048905 · Gurukul 3 Sept24 from 1.pdf · uploaded 21 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500048905 · Gurukul 3 Oct24 from 3_compressed.pdf · uploaded 21 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500048905 · gurukul 2 sept24 from 2.pdf · uploaded 21 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500048905 · Gurukul 3 Sept24 from 2.pdf · uploaded 21 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500047839 · form 1 GURUKUL 2.pdf · uploaded 24 Jan 2025View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · form3 GURUKUL 2_compressed.pdf · uploaded 24 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500047839 · Form 2 GURUKUL 2.pdf · uploaded 24 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500047839 · Form 2 GURUKUL 2.pdf · uploaded 24 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryP50500047839 · sold unsold inventory GURUKUL 2.pdf · uploaded 24 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500048905 · fORM 1 GURUKUL 3.pdf · uploaded 24 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500048905 · form3 GURUKUL 3_compressed.pdf · uploaded 24 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500048905 · Form 2 GURUKUL 3.pdf · uploaded 24 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryP50500048905 · sold unsold inventory GURUKUL 3.pdf · uploaded 24 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500047839 · G2 FORM 1 MAR25.pdf · uploaded 22 Apr 2025View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500047839 · G2 FORM 3 MAR25.pdf · uploaded 22 Apr 2025View
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500047839 · G2 FORM 2 MAR25.pdf · uploaded 22 Apr 2025View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500048905 · G3 FORM 1 MAR25.pdf · uploaded 22 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500048905 · G3 FORM 3 MAR25.pdf · uploaded 22 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500048905 · G3 FORM 2 MAR25.pdf · uploaded 22 Apr 2025View
  • Form 1P50500047839 · ARCH CERT 30 JUN 25.pdf · uploaded 19 Jul 2025Source
  • Form 2P50500047839 · G2 ENG CERT 30 JUN 25 .pdf · uploaded 19 Jul 2025Source
  • Form 3P50500047839 · G2 Form 3 18 july 25_compressed.pdf · uploaded 19 Jul 2025Source
  • Disclosure of Sold and Booked InventoryP50500047839 · sold unsold inv G2 .pdf · uploaded 19 Jul 2025Source
  • Form 1P50500048905 · ARCH CERT G3 30 JUN25.pdf · uploaded 19 Jul 2025Source
  • Form 2P50500048905 · ENG CERT G3 30 JUN 25.pdf · uploaded 19 Jul 2025Source
  • Form 3P50500048905 · G3 FORM 3 18 JULY 25.pdf · uploaded 19 Jul 2025Source
  • Disclosure of Sold and Booked InventoryP50500048905 · SOLD UNSOLD INV G3 .pdf · uploaded 19 Jul 2025Source
  • Form 5 (FY 2024-2025)P50500047839 · FORM-5 G2 MAR-2025.pdf · uploaded 18 Sep 2025Source
  • Form 5 (FY 2024-2025)P50500048905 · FORM-5 G3 MAR-2025.pdf · uploaded 19 Sep 2025Source
  • Form 2A (FY 2024-2025)P50500047839 · FORM-2A G2 MAR-2025.pdf · uploaded 25 Sep 2025Source
  • Form 2A (FY 2024-2025)P50500048905 · FORM-2A G3 MAR-2025.pdf · uploaded 25 Sep 2025Source
  • Withdrawal Update Form 1P50500047839 · G-2 FORM 1 ARCHITECT CERTIFICATE.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 2P50500047839 · G-2 FORM 2 ENGINEER CERTIFICATE.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 3P50500047839 · G-2 FORE 3 CA CERTIFICATE.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 1P50500048905 · G-3 FORM 1 ARCHITECT CERTIFICATE.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 2P50500048905 · G-3 FORM 2 ENGINEER CERTIFICATE.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 3P50500048905 · G-3 FORM - 3 CA CERTIFICATE.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 1P50500047839 · FORM-1 GURUKUL-2 DEC-25.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 1P50500047839 · FORM-1 GURUKUL-2 DEC-25.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2P50500047839 · FORM-2 GURUKUL-2 DEC-25.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2P50500047839 · FORM-2 GURUKUL-2 DEC-25.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3P50500047839 · FORM-3 GURUKUL-2 DEC-25.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3P50500047839 · FORM-3 GURUKUL-2 DEC-25.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 1P50500048905 · FORM-1 GURUKUL-3 DEC-25.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2P50500048905 · FORM-2 GURUKUL-3 DEC-25.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3P50500048905 · FORM-3 GURUKUL-3 DEC-25.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 1P50500047839 · FORM-1 G-2 MAR-26.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 2P50500047839 · FORM-2 G-2 MAR-26.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 3P50500047839 · FORM-3 G-2 MAR-26_compressed.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 1P50500048905 · FORM-1 G-3 MAR-26.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 1P50500048905 · FORM-1 G-3 MAR-26.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 2P50500048905 · FORM-2 G-3 MAR-26.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 2P50500048905 · FORM-2 G-3 MAR-26.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 3P50500048905 · FORM-3 G-3 MAR-26_compressed.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 3P50500048905 · FORM-3 G-3 MAR-26_compressed.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 1P50500047839 · GURUKUL-2 FORM-1 JUNE-26.pdf · uploaded 16 Jul 2026Source
  • Withdrawal Update Form 2P50500047839 · GURUKUL-2 FORM-2 JUNE-26.pdf · uploaded 16 Jul 2026Source
  • Withdrawal Update Form 3P50500047839 · GURUKUL-2 FORM-3 JUNE-26_compressed.pdf · uploaded 16 Jul 2026Source
  • Withdrawal Update Form 1P50500048905 · GURUKUL-3 FORM-1 JUNE-26.pdf · uploaded 16 Jul 2026Source
  • Withdrawal Update Form 2P50500048905 · GURUKUL-3 FORM-2 JUNE-26.pdf · uploaded 16 Jul 2026Source
  • Withdrawal Update Form 3P50500048905 · GURUKUL-3 FORM-3 JUNE-26_compressed.pdf · uploaded 16 Jul 2026Source
  • Form 5 (FY 2025-2026)P50500047839 · FORM-5 GURUKUL-2 25-26.pdf · uploaded 29 Sep 2026Source
  • Form 5 (FY 2025-2026)P50500048905 · FORM-5 GURUKUL-3 25-26.pdf · uploaded 29 Sep 2026Source
  • Form 2A (FY 2025-2026)P50500047839 · FORM-2A GURUKUL 2 25-26.pdf · uploaded 30 Sep 2026Source
  • Form 2A (FY 2025-2026)P50500048905 · FORM-2A GURUKUL 3 25-26.pdf · uploaded 30 Sep 2026Source

Technical

  • DocumentP50500047839 · NA Order Gurukul 2 30SEPT.pdf · uploaded 11 Nov 2022View
  • DocumentP50500047839 · MAP GURUKUL_compressed.pdf · uploaded 12 Nov 2022View
  • DocumentP50500048905 · NA Order.pdf · uploaded 7 Dec 2022View
  • DocumentP50500048905 · Gurukul 3 Final Sanction Map-compressed.pdf · uploaded 22 Dec 2022View

Technical (Architect)

  • DocumentP50500047839 · gurukul 2 sept24 from 1.pdf · uploaded 21 Oct 2024View
  • DocumentP50500048905 · Gurukul 3 Sept24 from 1.pdf · uploaded 21 Oct 2024Source
  • DocumentP50500047839 · form 1 GURUKUL 2.pdf · uploaded 24 Jan 2025View
  • DocumentP50500048905 · fORM 1 GURUKUL 3.pdf · uploaded 24 Jan 2025Source
  • DocumentP50500047839 · G2 FORM 1 MAR25.pdf · uploaded 22 Apr 2025View
  • DocumentP50500048905 · G3 FORM 1 MAR25.pdf · uploaded 22 Apr 2025Source
  • DocumentP50500047839 · GURUKUL-2 FORM-1 JUNE-26.pdf · uploaded 16 Jul 2026Source
  • DocumentP50500048905 · GURUKUL-3 FORM-1 JUNE-26.pdf · uploaded 16 Jul 2026Source

Technical (Engineer)

  • DocumentP50500047839 · gurukul 2 sept24 from 2.pdf · uploaded 21 Oct 2024Source
  • DocumentP50500048905 · gurukul 2 sept24 from 2.pdf · uploaded 21 Oct 2024Source
  • DocumentP50500048905 · Gurukul 3 Sept24 from 2.pdf · uploaded 21 Oct 2024Source
  • DocumentP50500047839 · Form 2 GURUKUL 2.pdf · uploaded 24 Jan 2025Source
  • DocumentP50500047839 · Form 2 GURUKUL 2.pdf · uploaded 24 Jan 2025Source
  • DocumentP50500048905 · Form 2 GURUKUL 3.pdf · uploaded 24 Jan 2025Source
  • DocumentP50500047839 · G2 FORM 2 MAR25.pdf · uploaded 22 Apr 2025View
  • DocumentP50500048905 · G3 FORM 2 MAR25.pdf · uploaded 22 Apr 2025View
  • DocumentP50500047839 · GURUKUL-2 FORM-2 JUNE-26.pdf · uploaded 16 Jul 2026Source
  • DocumentP50500048905 · GURUKUL-3 FORM-2 JUNE-26.pdf · uploaded 16 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 159 Part

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Certificate Signed
Phases
2
Address
159 Part, khasra No 159 ( part) Waranga, WarangaPIN 441108
Village
Waranga, Nagpur (Rural) taluka
Land area for this project
7,078 sq m (76,187 sq ft)
Permissible built-up area
7,078 sq m (76,187 sq ft)
Sanctioned built-up area
7,078 sq m (76,187 sq ft)
Recreational open space
1,263 sq m (13,595 sq ft)
Designated bank account
76
Developed in phases
No
Also registered as
Gurukul 2, Gurukul 3

Survey, CTS, gat or plot numbers

159 Part

Land as published on MahaRERA's project page

159 Part

Boundaries

North
Khasra No 158
South
Khasra No 161 and 162
East
khasra no 160
West
Khasra No 159 part

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals38

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectDhawal Harshe—P50500048905
ArchitectDhawal Harshe—P50500047839
ArchitectPiyusha Deepak Dhakate—P50500047839
ArchitectPiyusha Deepak Dhakate—P50500048905
ArchitectSanjay Basantani—P50500048905
ArchitectSanjay Basantani—P50500047839
Chartered accountantAdhish Agrawal—P50500047839
Chartered accountantAdhish Agrawal—P50500048905
Show all 38 professionalsShow fewer professionals
RoleNameRegistration no.RERA
Chartered accountantRachana Agrawal—P50500047839
Chartered accountantRachana Agrawal—P50500048905
EngineerRamdas Wagh—P50500048905
EngineerRAmdas Wagh—P50500047839
EngineerUnmesh Manoj Ingle—P50500047839
EngineerUnmesh Manoj Ingle—P50500048905
Registered real estate agentAmit Krishnrao Bhopte—P50500047839
Registered real estate agentAmit Krishnrao Bhopte—P50500048905
Registered real estate agentDipti Mangesh Sawalkar—P50500048905
Registered real estate agentDipti Mangesh Sawalkar—P50500047839
Registered real estate agentHemant Yadaorao Yerkhede—P50500047839
Registered real estate agentHemant Yadaorao Yerkhede—P50500048905
Registered real estate agentLaxman Udaybhanji Atram—P50500048905
Registered real estate agentLaxman Udaybhanji Atram—P50500047839
Registered real estate agentNanda Praful Shelke—P50500048905
Registered real estate agentNanda Praful Shelke—P50500047839
Registered real estate agentNayan Natthuji Ghate—P50500048905
Registered real estate agentNayan Natthuji Ghate—P50500047839
Registered real estate agentNeha Nayan Ghate—P50500047839
Registered real estate agentNeha Nayan Ghate—P50500048905
Registered real estate agentNikesh Vijay Kachore—P50500047839
Registered real estate agentNikesh Vijay Kachore—P50500048905
Registered real estate agentPushpa Ishwarrao Sarode—P50500047839
Registered real estate agentPushpa Ishwarrao Sarode—P50500048905
Registered real estate agentRajesh Manoharrao Hirulkar—P50500047839
Registered real estate agentRajesh Manoharrao Hirulkar—P50500048905
Registered real estate agentSanket Jagdish Chitriv—P50500047839
Registered real estate agentSanket Jagdish Chitriv—P50500048905
Registered real estate agentSuraj Chhatrapati Bhandekar—P50500047839
Registered real estate agentSuraj Chhatrapati Bhandekar—P50500048905

Source: MahaRERA project page. Contact details are not shown.

Other projects in Waranga

All 7 projects in Waranga · Compare Gurukul with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology